Skip to content

Building D · Ratnamani Greens Phase 1

Dahanu (M Cl) · RERA P99000076663

IDBLD_0833423 floorsExtended 4 mo
3Sanctioned habitable floorsregistration certificate
30 Apr 2033Revised completionpromised 31 Dec 2032

Floors

3 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P99000076663 · registered 20 Jun 2024
Promised completion
31 Dec 2032
Revised completion
30 Apr 2033
Sanctioned habitable floors
3
ProjectId
47,089
ProjectName
Ratnamani Greens Phase 1
TotalUnitCount
12
ProjectBuildingId
1,34,442
BuildingNameNumber
Building D
FsiWithSanctionSqmts
4
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
12
ProjectRegistartionNo
P99000076663
ProjectBuildingWingsId
1,37,859
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Building D
NoOfBuildingWingFloorProposed
4
NoOfBuildingWingFloorHabitable
3
NoOfBuildingWingFloorSanctioned
4

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——12not published
Total12
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology