Valencia Riverside Apartment
Certificate SignedNashik 422013 |Promoter: Vinayaka Builders
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 4BHK, Office space, Shop, 3BHK28 units in all
- Address
- PLOT NO 1 2 3 OF S NO 704/1/4/5/2, Savarkar Nagar Daate Nagar, Gangapur RoadPIN 422013
- Designated bank account
- 76
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Sep 2026
The latest completion date on record passed 1 month ago.
- Registered
- 28 Apr 2022
- Promised
- 30 Sep 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600034969 | 28 Apr 2022 | 30 Sep 2026 | 30 Sep 2026 | Vinayaka Builders | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Valencia Riverside Apartment Wing A | 8 | 14 |
| Valencia Riverside Apartment Wing B | 7 | 14 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
3 of 28 units booked (11%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 1 |
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 1 |
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | 4BHK | 165.9 sq m · 1,786 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Office space | 31.26 sq m · 336 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Office space | 31.33 sq m · 337 sq ft | 1 | 0 |
Show all 28 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Valencia Riverside Apartment Wing A | Office space | 47.62 sq m · 513 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Office space | 54.86 sq m · 591 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Shop | 31.33 sq m · 337 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Shop | 31.44 sq m · 338 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Shop | 32.74 sq m · 352 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing A | Shop | 36.88 sq m · 397 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 1 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 3BHK | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
| Valencia Riverside Apartment Wing B | 4BHK | 138.15 sq m · 1,487 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 135 filings listed on MahaRERA's project page
Finance
- PAN CardVinayaka Builders - PAN Card.pdf · uploaded 19 Apr 2022Source
Legal
Migrated
- 1 PAN CardVinayaka Builders - PAN Card.pdf · uploaded 19 Apr 2022Source
- 1 Copy of the legal title reportFormat A title report_11zon.pdf · uploaded 19 Apr 2022Source
- 1 Details of encumbrancesEncumbrance certificate.pdf · uploaded 19 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 19 Apr 2022Source
Show all 136 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan 1.pdf · uploaded 19 Apr 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2.pdf · uploaded 19 Apr 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan 3.pdf · uploaded 19 Apr 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 19 Apr 2022Source
- 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 19 Apr 2022Source
- 1 Declaration in FORM BForm B - Pramod Somaiya.pdf · uploaded 19 Apr 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vinayaka Builder's - Form 1_11zon.pdf · uploaded 19 Apr 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200235426053_For_Asset_Based_Search_19_04_2022_18_29_53_235.pdf · uploaded 19 Apr 2022Source
- 2 CERSAI detailsCersai Declaration.pdf · uploaded 19 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Vinayaka Builders.pdf · uploaded 19 Apr 2022Source
- 1 Proforma of Allotment letterDRAFT AGREEMENT TO SALE.pdf · uploaded 19 Apr 2022Source
- 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 19 Apr 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architects letter 30062022.pdf · uploaded 4 Mar 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Architects letter 30092022.pdf · uploaded 4 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architects letter 31122022.pdf · uploaded 4 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Architects letter 31032023.pdf · uploaded 4 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Architects letter 30062023.pdf · uploaded 4 Mar 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Architects letter 30092023.pdf · uploaded 4 Mar 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Architects letter 31122023.pdf · uploaded 4 Mar 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Adhar engineers 30062022.pdf · uploaded 4 Mar 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Adhar engineers 30092022.pdf · uploaded 4 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Adhar engineers 31122022.pdf · uploaded 4 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Adhar engineers 31032023.pdf · uploaded 4 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Aadhar engineers 30062023.pdf · uploaded 4 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 aadhar engineers 30092023.pdf · uploaded 4 Mar 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Adhar engineers 31122023.pdf · uploaded 4 Mar 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 CA letter 30062022.pdf · uploaded 4 Mar 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 CA letter 30092022.pdf · uploaded 4 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 CA letter 31122022.pdf · uploaded 4 Mar 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 CA letter 31032023.pdf · uploaded 4 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 CA letter 30062023.pdf · uploaded 4 Mar 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 CA letter 30092023.pdf · uploaded 4 Mar 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 CA letter 31122023.pdf · uploaded 4 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 22-23 Signed.pdf · uploaded 4 Mar 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)8 Form 1 31032024.pdf · uploaded 24 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)9 Form 1 30062024.pdf · uploaded 24 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Form 1 30092024.pdf · uploaded 24 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)11 Form 1 31122024.pdf · uploaded 24 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 Form 3 - 31032024.pdf · uploaded 24 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 Form 3 - 30062024.pdf · uploaded 24 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 Form 3 - 30092024.pdf · uploaded 24 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)11 Form 3 - 31122024.pdf · uploaded 24 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 31032024.pdf · uploaded 24 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 30062024.pdf · uploaded 24 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 30092024.pdf · uploaded 24 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 31122024.pdf · uploaded 24 Feb 2025Source
- Form 131032025 Form 1 Signed.pdf · uploaded 30 Dec 2025Source
- Form 2Withdrawal Application Form2 - 31032025.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31032025.pdf · uploaded 30 Dec 2025Source
- Form 3Withdrawal Application Form3 - 31032025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 130062025 Form 1 Signed.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 130092025 Form 1 Signed.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2Withdrawal Application Form2 - 30062025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2Withdrawal Application Form2 - 30092025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3 - 30062025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3 - 30092025.pdf · uploaded 30 Dec 2025Source
- Form 1Form 1 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30062022.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 30062022 reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30062022.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 31122022 reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 31122022 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 31122022 Reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31122022.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 31032023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 31032023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 31032023 Reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31032023.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 30062023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 30062023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 30062023 Reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30062023.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 30092023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 30092023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 30092023 Reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30092023.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 31122023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 31122023 Reduced.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 31122023 Reduced.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31122023.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 31032024.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 31032024.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 31032024.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31032024.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 30062024.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 30062024.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 - 30062024.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30062024.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 - 30092024.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 - 30092024.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 - 30092024.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 30092024.pdf · uploaded 25 Apr 2026Source
- Form 1Form 1 31122024.pdf · uploaded 25 Apr 2026Source
- Form 2Form 2 31122024.pdf · uploaded 25 Apr 2026Source
- Form 3Form 3 - 31122024.pdf · uploaded 25 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD 31122024.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 1Form 1 signed.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 1Form 1 signed.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2Form2 Signed.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2Form 2 Signed.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3Form 3 31122025.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3Form3 31032026.pdf · uploaded 29 Apr 2026Source
- Form 2A (FY 2022-2023)22-23.pdf · uploaded 2 May 2026Source
- Form 2A (FY 2023-2024)23-24.pdf · uploaded 2 May 2026Source
- Form 2A (FY 2024-2025)24-25.pdf · uploaded 2 May 2026Source
- Form 2A (FY 2025-2026)25-26.pdf · uploaded 2 May 2026Source
- Form 5 (FY 2022-2023)Form 5 22-23.pdf · uploaded 2 May 2026Source
- Form 5 (FY 2023-2024)Form 5 23-24.pdf · uploaded 2 May 2026Source
- Form 5 (FY 2024-2025)Form 5 24-25.pdf · uploaded 2 May 2026Source
- Form 5 (FY 2025-2026)Form 5 25-26.pdf · uploaded 2 May 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nashik, Nashik taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- House No 1
- South
- 9 Meter Wide Road
- East
- Plot No 4
- West
- 18 Meter Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Sameer Madiyar | — |
| Chartered accountant | P H Mehta & Co | — |
| Engineer | Aadhar Engineers | — |
Source: MahaRERA project page. Contact details are not shown.