The Avenue Bliss

Certificate Signed

Nashik 422009 |Promoter: The Avenue Builders And Developers

17 Mar 2022Registered with MahaRERA
31 Dec 2025Promised completion
1Building
43Units registered22 booked (51%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Shop43 units in all
Address
Plot No. 31+32 Of S.no/G.no.788/1 Of Nashik City-4 Shiwar, Nashik., Govind Nagar, Chowk No.5, Lane No.1, Bh. Prakash Petrol Pump, Nr.ashwini Hospital, Govind Nagar, Nashik- 422009PIN 422009
Designated bank account
86
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
17 Mar 2022
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160003405717 Mar 202231 Dec 202531 Dec 2025The Avenue Builders And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
The Avenue Bliss843

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

22 of 43 units booked (51%), as the promoter reported to MahaRERA

2BHK · 21 units3BHK · 14 unitsShop · 8 units
TypeCarpet areaUnitsBooked
2BHK52.18 sq m · 562 sq ft71
2BHK52.93 sq m · 570 sq ft74
2BHK53.62 sq m · 577 sq ft75
3BHK72.5 sq m · 780 sq ft75
3BHK75.05 sq m · 808 sq ft76
Shop13.37 sq m · 144 sq ft41
Shop13.52 sq m · 146 sq ft10
Shop13.58 sq m · 146 sq ft10
Shop14.85 sq m · 160 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 69 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardTABD.pdf · uploaded 16 Feb 2022Source

Legal

  • OtherLetter of Authorisation.pdf · uploaded 16 Feb 2022Source
  • Declaration Form BFORM B (Declaration ).pdf · uploaded 16 Feb 2022Source
  • Legal Title reportBLISS - Search Report_compressed.pdf · uploaded 7 Mar 2022Source

Migrated

  • 1 PAN CardTABD.pdf · uploaded 16 Feb 2022Source
  • 1 Details of encumbrancesNon Encumbrance Certificate.pdf · uploaded 16 Feb 2022Source
  • 1 Copy of Layout Approval (in case of layout)BLISS - Amalgamation Plan convert.pdf · uploaded 16 Feb 2022Source
Show all 70 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentBLISS - Approved Plan convert.pdf · uploaded 16 Feb 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentBLISS - Commencement Certificate convert.pdf · uploaded 16 Feb 2022Source
  • 1 Declaration about Commencement CertificateDeclaration in Form D.pdf · uploaded 16 Feb 2022Source
  • 1 Declaration in FORM BFORM B (Declaration ).pdf · uploaded 16 Feb 2022Source
  • 1 OtherLetter of Authorisation.pdf · uploaded 16 Feb 2022Source
  • 1 Copy of the legal title reportBLISS - Search Report_compressed.pdf · uploaded 7 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1-.pdf · uploaded 7 Mar 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)BLISS - Form 2.pdf · uploaded 7 Mar 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold inventory.pdf · uploaded 7 Mar 2022Source
  • 1 CERSAI detailsLatest CERSAI_Search_Report_200231796164_For_Asset_Based_Search_07_03_2022_15_56_08_390.pdf · uploaded 7 Mar 2022Source
  • 1 Proforma of Allotment letterProforma - Allotment Letter.pdf · uploaded 7 Mar 2022Source
  • 2 Proforma of Allotment letterBLISS - Draft Agreement.pdf · uploaded 7 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Certificate new-compressed.pdf · uploaded 9 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)ABW-- RERA CA Certificate-Form 5.PDF · uploaded 27 Sep 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)ABW-- RERA CA Certificate-Form 5.PDF · uploaded 27 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)ABW-- RERA CA Certificate-Form 5.PDF · uploaded 30 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate.pdf · uploaded 24 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate.pdf · uploaded 24 Nov 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue bliss.pdf · uploaded 24 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.PDF · uploaded 24 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1FORM1.pdf · uploaded 30 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3FORM 3bliss fy 23 24 SIGN.pdf · uploaded 30 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2Form 2 - Avenue Bliss - Q4 FY 23-24.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Bliss - Form 1 - FY 24-25 Q1.pdf · uploaded 8 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Bliss - Form 1 - FY 24-25 Q2.pdf · uploaded 8 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Bliss - FY 24-25 - Q1.pdf · uploaded 8 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Bliss - FY 24-25 - Q2.pdf · uploaded 8 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Bliss - Form 2 - FY 24-25 Q1.pdf · uploaded 8 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Bliss - Form 2 - FY 24-25 Q2 .pdf · uploaded 8 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Bliss - Q3 FY 24-25.pdf · uploaded 31 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Bliss - Form 3 - Q3 FY 24-25 Signed.pdf · uploaded 31 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Bliss - Form 2 - Q3 FY 24-25 (1).pdf · uploaded 31 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)The Avenue Builders and Developers_0001.pdf · uploaded 11 Apr 2025Source
  • 1 Proforma of Agreement for saleBliss Draft Agreement.pdf · uploaded 8 May 2025Source
  • Form 1Bliss Architect certificate.pdf · uploaded 27 May 2025Source
  • Form 2Bliss - Form 2 - Q4 FY 24-25.pdf · uploaded 27 May 2025Source
  • Form 3Final Form 3 Q4 24-25.pdf · uploaded 27 May 2025Source
  • Form 1Bliss Architect certificate.pdf · uploaded 16 Apr 2026Source
  • Form 2Bliss Q1 FY 2526 Form 2.pdf · uploaded 16 Apr 2026Source
  • Form 3Form 3.pdf · uploaded 16 Apr 2026Source
  • Disclosure of Sold and Booked InventorySold unsold Q1.pdf · uploaded 16 Apr 2026Source
  • Form 1Bliss Architect certificate.pdf · uploaded 16 Apr 2026Source
  • Form 2Bliss Q2 FY 2526 Form 2.pdf · uploaded 16 Apr 2026Source
  • Form 3The Avenue Builders and Developers (Q-2)_0001.pdf · uploaded 16 Apr 2026Source
  • Disclosure of Sold and Booked InventoryQ2 Sold unsold.pdf · uploaded 16 Apr 2026Source
  • Form 1Bliss Architect certificate.pdf · uploaded 16 Apr 2026Source
  • Form 2Bliss Q3 FY 2526 Form 2.pdf · uploaded 16 Apr 2026Source
  • Form 3The Avenue Builders and Developers (Q-3)_0001.pdf · uploaded 16 Apr 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Q3.pdf · uploaded 16 Apr 2026Source
  • Occupational CertificateBliss Completion Certificate.pdf · uploaded 16 Apr 2026Source

Technical

  • DocumentBLISS - Amalgamation Plan convert.pdf · uploaded 16 Feb 2022Source
  • DocumentBLISS - Approved Plan convert.pdf · uploaded 16 Feb 2022Source

Technical (Architect)

  • DocumentForm 1 - Architect Certificate.pdf · uploaded 24 Nov 2023Source
  • Document1FORM1.pdf · uploaded 30 Oct 2024Source
  • DocumentBliss - Form 1 - FY 24-25 Q1.pdf · uploaded 8 Feb 2025Source
  • DocumentBliss - Form 1 - FY 24-25 Q2.pdf · uploaded 8 Feb 2025Source
  • DocumentForm 1 - Bliss - Q3 FY 24-25.pdf · uploaded 31 Mar 2025Source

Technical (Engineer)

  • DocumentForm 2 Engineer certificate.pdf · uploaded 24 Nov 2023Source
  • Document2Form 2 - Avenue Bliss - Q4 FY 23-24.pdf · uploaded 30 Oct 2024Source
  • DocumentBliss - Form 2 - FY 24-25 Q1.pdf · uploaded 8 Feb 2025Source
  • DocumentBliss - Form 2 - FY 24-25 Q2 .pdf · uploaded 8 Feb 2025Source
  • DocumentBliss - Form 2 - Q3 FY 24-25 (1).pdf · uploaded 31 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik, Nashik taluka

Survey, CTS, gat or plot numbers

PLOT NO. 31+32 OF S.NO/G.NO.788/1 OF NASHIK CITY4 SHIWAR

Boundaries

North
Plot No 30
South
Plot No 33
East
12 mtr Wide D P Road
West
Plot No 18 19 and 20

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKapil Thakkar—
Chartered accountantBhavana Bhushan Loya—
Chartered accountantCa Chetan Bumb—
EngineerBhanuvilas Bhavsar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology