Hari Kunj Mayflower

Lapsed

Nashik 422009 |Promoter: Kbc Global Limited

29 Mar 2019Registered with MahaRERA
31 Mar 2021Promised completion
30 Dec 2024Revised completionPushed back 3 years and 9 months
6Buildings
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
6
Land area for this project
5,440 sq m (58,556 sq ft)
Permissible built-up area
12,999 sq m (1,39,920 sq ft)
Sanctioned built-up area
6,123 sq m (65,908 sq ft)
Recreational open space
524 sq m (5,640 sq ft)
Address
Sr No 763/2/2/1, Nashik, NashikPIN 422009
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.99745, 73.78980
Hari Kunj Mayflower is at latitude 19.99745, longitude 73.78980.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 9 months

The latest completion date on record passed 1 year and 10 months ago.

Registered
29 Mar 2019
Promised
31 Mar 2021
Revised
30 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160002024929 Mar 201931 Mar 202130 Dec 2024Kbc Global LimitedProject page

6 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building A7—
Building B7—
Building C7—
Building D7—
Building E7—
Building (P51600020249)——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Building AClosed/Covered00001
Building AOpen Space000018
Building BClosed/Covered00001
Building BOpen Space00008
Building CClosed/Covered00001
Building COpen Space00008
Building DClosed/Covered00001
Building DOpen Space00007
Building EClosed/Covered00001
Building EOpen Space00008

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building A

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Building B

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Building C

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Show all 6 buildings and common areasShow fewer buildings and common areas

Building D

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Building E

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

72 documents held by Deedo, 91 filings listed on MahaRERA's project page

Title report

Encumbrance details (4)

Commencement certificate (3)

Show all 163 documentsShow fewer documents

Form B

Registration certificate

Form 2A (8)

Form 5

Extension certificate

Other (31)

Allotment letter (2)

Layout plan

Building plan (18)

Document library

  • Details of encumbrancesEncumberance.pdf · uploaded 14 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 14 Mar 2019View
  • Copy of the legal title reportTitle Report.pdf · uploaded 14 Mar 2019View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 14 Mar 2019View
  • Proforma of Allotment letterPROFORMA.pdf · uploaded 14 Mar 2019View
  • Building Plan Approval (IOD)Building Plan-1-2.pdf · uploaded 14 Mar 2019View
  • Building Plan Approval (IOD)Building Plan-3-4-1.pdf · uploaded 14 Mar 2019View
  • Building Plan Approval (IOD)Building Plan-3-4-2.pdf · uploaded 14 Mar 2019View
  • Declaration in FORM BForm B PROMOTER.pdf · uploaded 26 Mar 2019View
  • Form 2AKunj mayflower-FORM 2A.pdf · uploaded 15 May 2019View
  • Annual Audit Report of Statutory CA (Form 5)Form 5 - Hari Kunj Mayflower_compressed.pdf · uploaded 30 Sep 2019View
  • Form 2AForm 2A mayflower.pdf · uploaded 24 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 - Hari Kunj MayFlower_compressed.pdf · uploaded 30 Sep 2020View
  • Building Plan Approval (IOD)Plans -1.pdf · uploaded 19 Oct 2020View
  • Building Plan Approval (IOD)Plans -2.pdf · uploaded 19 Oct 2020View
  • Building Plan Approval (IOD)Plans -3.pdf · uploaded 19 Oct 2020View
  • Building Plan Approval (IOD)New Revised Plan (1)-1.pdf · uploaded 15 Dec 2020View
  • Building Plan Approval (IOD)New Revised Plan (1)-2_compressed.pdf · uploaded 15 Dec 2020View
  • Commencement Certificates / NA Order for plotted developmentRevised Commencement 26-3-2021.pdf · uploaded 15 Apr 2021View
  • Building Plan Approval (IOD)KUNJ-1.pdf · uploaded 15 Apr 2021View
  • Building Plan Approval (IOD)KUNJ-2.pdf · uploaded 15 Apr 2021View
  • Building Plan Approval (IOD)KUNJ-3.pdf · uploaded 15 Apr 2021View
  • Building Plan Approval (IOD)KUNJ-4.pdf · uploaded 15 Apr 2021View
  • Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE-KUNJ.pdf · uploaded 15 Aug 2021View
  • Disclosure of sold/ booked inventoryMayflower (4).pdf · uploaded 7 Oct 2021View
  • Disclosure of sold/ booked inventoryKunj Mayf;lower.pdf · uploaded 8 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)hari kunj- may flower.pdf · uploaded 8 Oct 2021View
  • Disclosure of sold/ booked inventorymaflowe.pdf · uploaded 9 Oct 2021View
  • Form 2AMayflower.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Mayflower.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Mayflower.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Mayflower.pdf · uploaded 14 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Mayflower.pdf · uploaded 14 Oct 2021View
  • Disclosure of sold/ booked inventoryMAYFLOWER.pdf · uploaded 15 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)mayflower 2A.pdf · uploaded 12 Feb 2022View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 12 Feb 2022View
  • Building Plan Approval (IOD)scan0347 (2).pdf · uploaded 28 Mar 2022View
  • Building Plan Approval (IOD)scan0348_(2).pdf · uploaded 28 Mar 2022View
  • Building Plan Approval (IOD)scan0349_(2).pdf · uploaded 28 Mar 2022View
  • Building Plan Approval (IOD)scan0350_(2).pdf · uploaded 28 Mar 2022View
  • Building Plan Approval (IOD)scan0351_(2).pdf · uploaded 28 Mar 2022View
  • Building Plan Approval (IOD)scan0353_(2).pdf · uploaded 28 Mar 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Hari Kunj Mayflower.pdf · uploaded 21 Apr 2022View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER.pdf · uploaded 29 Apr 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Hari Kunj Mayflower.pdf · uploaded 24 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Hari Kunj Mayflower.pdf · uploaded 24 Mar 2023View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 5 Apr 2023View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 5 Apr 2023View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 6 Apr 2023View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 6 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Hari Kunj Mayflower.pdf · uploaded 17 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)H Kunj Mayflower.pdf · uploaded 15 Jul 2023View
  • Disclosure of sold/ booked inventoryMayflower.pdf · uploaded 15 Jul 2023View
  • Disclosure of sold/ booked inventoryHari Kunj Mayflower.pdf · uploaded 11 Oct 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Kunj Mayflower.pdf · uploaded 16 Oct 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)hari KunjMay Flower.pdf · uploaded 20 Jan 2024View
  • Disclosure of sold/ booked inventoryHari Kunj mayflower.pdf · uploaded 24 Jan 2024View
  • Details of encumbrancesEncumbrance certificate (1)_page-0001.pdf · uploaded 23 Feb 2024View
  • a Details of encumbrances concerned to FinanceEncumbrance certificate finance_page-0001.pdf · uploaded 23 Feb 2024View
  • b Details of encumbrances concerned to LegalEncumbrance certificate finance_page-0001.pdf · uploaded 23 Feb 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank acc details_page-0001.pdf · uploaded 23 Feb 2024View
  • Deviation Report with respect to Allotment letterEncumbrance certificate-model allotment letter_page-0001.pdf · uploaded 23 Feb 2024View
  • Deviation Report with respect to model copy of AgreementEncumbrance certificate-model agreement_page-0001.pdf · uploaded 23 Feb 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Kunj Mayflower.pdf · uploaded 26 Apr 2024View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER.pdf · uploaded 29 Apr 2024View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER JUNE.pdf · uploaded 14 Feb 2025View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER SEPT.pdf · uploaded 14 Feb 2025View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER DEC.pdf · uploaded 14 Feb 2025View
  • Disclosure of sold/ booked inventoryHARI KUNJ MAYFLOWER MAR.pdf · uploaded 12 Jun 2025View

Promoter documents

  • Legal Title reportTitle Report.pdf · uploaded 14 Mar 2019View
  • Declaration Form BForm B PROMOTER.pdf · uploaded 26 Mar 2019View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalBuilding Plan-1-2.pdfView
  • Building Plan ApprovalBuilding Plan-3-4-1.pdfView
  • Building Plan ApprovalBuilding Plan-3-4-2.pdfView
  • Building Plan ApprovalKUNJ-1.pdfView
  • Building Plan ApprovalKUNJ-2.pdfView
  • Building Plan ApprovalKUNJ-3.pdfView
  • Building Plan ApprovalKUNJ-4.pdfView
  • Building Plan ApprovalNew Revised Plan (1)-2_compressed.pdfView
  • Building Plan ApprovalPlans -1.pdfView
  • Building Plan ApprovalPlans -2.pdfView
  • Building Plan ApprovalPlans -3.pdfView
  • Building Plan ApprovalNew Revised Plan (1)-1.pdfView
  • Building Plan Approvalscan0347 (2).pdfView
  • Building Plan Approvalscan0348_(2).pdfView
  • Building Plan Approvalscan0349_(2).pdfView
  • Building Plan Approvalscan0350_(2).pdfView
  • Building Plan Approvalscan0351_(2).pdfView
  • Building Plan Approvalscan0353_(2).pdfView

Proforma allotment letter

  • Proforma allotment letterPROFORMA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik, Nashik taluka

Survey, CTS, gat or plot numbers

SR NO 763/2/2/1

As published on MahaRERA's project page

SR NO 763/2/2/1

Boundaries

North
Sr No 763-2-2-2
South
Sr No 766-3-1
East
Sr No 763-2-1
West
Sr No763-1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSumit Kumath—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology