Balaji Park

Lapsed

Nashik 422007 |Promoter: Kalantri And Musale Realcon LLP

5 Dec 2019Registered with MahaRERA
30 Dec 2025Promised completion
14Buildings
110Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
14
Unit types
Row house, Shop110 units in all
Land area for this project
8,830 sq m (95,046 sq ft)
Permissible built-up area
3,304 sq m (35,566 sq ft)
Sanctioned built-up area
3,304 sq m (35,566 sq ft)
Recreational open space
981 sq m (10,561 sq ft)
Address
S.no. 449 Satpur, Ambad Link Road, Medge Nagar, SatpurPIN 422007
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Balaji Park is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
5 Dec 2019
Promised
30 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000231825 Dec 201930 Dec 2025—Kalantri And Musale Realcon LLPProject page

14 buildings

Buildings and wings named in the registration

Show all 14 buildingsShow fewer buildings
BuildingSanctioned floorsUnits
G Building213
H Building213
I Building29
J Building19
K Building119
Split——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

110 units registered

Row house · 91 unitsShop · 19 units
BuildingTypeCarpet areaUnits
A BuildingRow house36.26 sq m · 390 sq ft11
A BuildingRow house36.75 sq m · 396 sq ft2
B BuildingRow house36 sq m · 388 sq ft1
B BuildingRow house36.19 sq m · 390 sq ft1
B BuildingRow house36.21 sq m · 390 sq ft5
C BuildingRow house36 sq m · 388 sq ft1
C BuildingRow house36.21 sq m · 390 sq ft5
C BuildingRow house36.41 sq m · 392 sq ft1
Show all 26 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnits
D BuildingRow house36 sq m · 388 sq ft1
D BuildingRow house36.21 sq m · 390 sq ft5
D BuildingRow house36.41 sq m · 392 sq ft1
E BuildingRow house36 sq m · 388 sq ft1
E BuildingRow house36.21 sq m · 390 sq ft5
E BuildingRow house36.41 sq m · 392 sq ft1
F BuildingRow house26.53 sq m · 286 sq ft6
G BuildingRow house26.53 sq m · 286 sq ft12
G BuildingRow house35.89 sq m · 386 sq ft1
H BuildingRow house26.53 sq m · 286 sq ft10
H BuildingRow house35.89 sq m · 386 sq ft1
H BuildingRow house35.89 sq m · 386 sq ft1
H BuildingRow house36.56 sq m · 394 sq ft1
I BuildingRow house26.53 sq m · 286 sq ft7
I BuildingRow house35.88 sq m · 386 sq ft2
J BuildingRow house26.53 sq m · 286 sq ft9
K BuildingShop9.53 sq m · 103 sq ft2
K BuildingShop9.75 sq m · 105 sq ft17

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A BuildingClosed/Covered00000
A BuildingOpen Space000013
B BuildingClosed/Covered00000
B BuildingOpen Space00007
C BuildingClosed/Covered00000
C BuildingOpen Space00007
D BuildingClosed/Covered00000
D BuildingOpen Space00000
Show all 22 parking rowsShow fewer parking rows
BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
E BuildingClosed/Covered00000
E BuildingOpen Space00000
F BuildingClosed/Covered00000
F BuildingOpen Space00002
G BuildingClosed/Covered00000
G BuildingOpen Space00004
H BuildingClosed/Covered00000
H BuildingOpen Space00006
I BuildingClosed/Covered00000
I BuildingOpen Space00005
J BuildingClosed/Covered00000
J BuildingOpen Space00003
K BuildingClosed/Covered00000
K BuildingOpen Space000014

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

B Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

C Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Show all 12 buildings and common areasShow fewer buildings and common areas

D Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

E Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

F Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

G Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

H Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

I Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

J Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

K Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsINTERNAL ROADS DONE100%
  • Water SupplyOBTAINED FROM NMC100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK DONE100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingLAWN IN OPEN SPACE PROVIDED100%
  • Street LightingSOLAR LIGHTS PROVIDED100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING DONE100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationINDIVIDUAL ELECTRIC METER FOR EACH UNIT100%
  • Aggregate area of recreational Open SpaceDEVELOPED100%
  • Open ParkingAS PER PLAN100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

43 documents held by Deedo, 51 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Allotment letter (2)

Registration certificate

Form 1 (7)

Show all 94 documentsShow fewer documents

Form 1 (7)

Form 2 (7)

Form 5 (6)

Other (6)

Form 2A (5)

Layout plan

Building plan (4)

Document library

  • Copy of the legal title reportTitle Report.pdf · uploaded 14 Nov 2019View
  • Details of encumbrancesNo Encumbrance.pdf · uploaded 14 Nov 2019View
  • Copy of Layout Approval (in case of layout)Plot Layout.pdf · uploaded 14 Nov 2019View
  • Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 14 Nov 2019View
  • Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 14 Nov 2019View
  • Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 14 Nov 2019View
  • Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 14 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 14 Nov 2019View
  • Declaration in FORM BForm B.pdf · uploaded 14 Nov 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Nov 2019View
  • Proforma of Allotment letterAgreement To Sale.pdf · uploaded 14 Nov 2019View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 14 Nov 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Nov 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 - 2019 20.pdf · uploaded 17 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 - 2020 21.pdf · uploaded 17 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - 2021 22.pdf · uploaded 17 Feb 2023View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Declaration of Apartment.pdf · uploaded 17 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Feb 2023View
  • Other – LegalReply to Rera Notice.pdf · uploaded 17 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - 2022-23.pdf · uploaded 8 Mar 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - 2020.pdf · uploaded 19 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - 2021.pdf · uploaded 19 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A - 2022.pdf · uploaded 19 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - 2023.pdf · uploaded 19 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - 2024.pdf · uploaded 19 Mar 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - 2023-24.pdf · uploaded 19 Mar 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - 2024-25.pdf · uploaded 19 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 23-24 Q2.pdf · uploaded 31 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 23-24 Q3.pdf · uploaded 31 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 23-24 Q1.pdf · uploaded 31 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 23-24 Q4.pdf · uploaded 31 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 24-25 Q1.pdf · uploaded 31 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 24-25 Q2.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q1.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q2.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q3.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q3.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q4.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 24-25 Q1.pdf · uploaded 31 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 24-25 Q2.pdf · uploaded 31 Mar 2025View
  • Disclosure of sold/ booked inventoryInventory 30-09-2024.pdf · uploaded 31 Mar 2025View

Promoter documents

  • Legal Title reportTitle Report.pdf · uploaded 14 Nov 2019View
  • Declaration Form BForm B.pdf · uploaded 14 Nov 2019View

Technical documents

  • Layout ApprovalPlot Layout.pdfView
  • Building Plan ApprovalPlan 1.pdfView
  • Building Plan ApprovalPlan 2.pdfView
  • Building Plan ApprovalPlan 3.pdfView
  • Building Plan ApprovalPlan 4.pdfView

Other legal documents

  • Other – LegalReply to Rera Notice.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik, Nashik taluka

Survey, CTS, gat or plot numbers

449S.NO. 449 SATPUR

As published on MahaRERA's project page

S.NO. 449 SATPUR

Boundaries

North
Adj G No 453
South
30 Meter Road
East
Adj G No 448
West
Adj G No 452

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPankaj Jadhav—
Chartered accountantSagar Kothawade—
EngineerMilind Rathi—
EngineerSagar S Shah—
OtherDeepak Bhagat—
OtherDeepak Vishwakarma—
OtherGovind Jadhav—
OtherIshwarlal Mahato—
Show all 20 professionalsShow fewer professionals
RoleNameRegistration no.
OtherJitendra Pandit—
OtherKamlesh Pal—
OtherLalji Kori—
OtherOmprakash Jaiswal—
OtherPrabhu Pandit—
OtherRahees Khan—
OtherRajaram Bagad—
OtherRavi Patil—
OtherSanjay Shinde—
OtherSNS Rera Consultants—
OtherSubodh Shah—
OtherTatyabhau Ahire—

Source: MahaRERA project page. Contact details are not shown.