Amrut Shilp

Certificate Signed

Nashik 422101 |Promoter: Suprabhat Constructions

Residential / Group HousingRERAP51600012316
17 Nov 2017Registered with MahaRERA
31 Dec 2017Promised completion
1Building
42Units registered35 booked (83%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Amrut shilp42 units in all
Address
125/3PIN 422101
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51418, 73.87533
Amrut Shilp is at latitude 18.51418, longitude 73.87533.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2017

The latest completion date on record passed 8 years and 10 months ago.

Registered
17 Nov 2017
Promised
31 Dec 2017

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160001231617 Nov 201731 Dec 201731 Dec 2017Suprabhat ConstructionsProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Amrut Shilp942

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

35 of 42 units booked (83%), as the promoter reported to MahaRERA

Amrut shilp · 42 units
TypeCarpet areaUnitsBooked
Amrut shilp2,575.92 sq m · 27,727 sq ft4235

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 32 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFIRM PAN CARD.pdf · uploaded 14 Aug 2017Source
  • PAN CardANAND DHATRAK PAN CARD.pdf · uploaded 14 Aug 2017Source
  • PAN CardSAGAR MOTKARI PAN CARD.pdf · uploaded 14 Aug 2017Source

Legal

  • Legal Title reportLegal Title Report-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • Declaration Form BDECALRATION FORM B.pdf · uploaded 14 Aug 2017Source
  • OtherCOMPLITION CERTIFICATE.pdf · uploaded 19 Jan 2018Source

Migrated

  • 1 PAN CardFIRM PAN CARD.pdf · uploaded 14 Aug 2017Source
Show all 33 documentsShow fewer documents

Migrated

  • 2 PAN CardANAND DHATRAK PAN CARD.pdf · uploaded 14 Aug 2017Source
  • 3 PAN CardSAGAR MOTKARI PAN CARD.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of the legal title reportLegal Title Report-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 1 Details of encumbrances712 uttara.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)building plan approval 1-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 2 Copy of Layout Approval (in case of layout)building plan approval 2-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 1 Building Plan Approval (IOD)building plan approval 1-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 2 Building Plan Approval (IOD)building plan approval 2-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate copy-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • 1 Declaration in FORM BDECALRATION FORM B.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH CERTIFICATE.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)enginerring certificate.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 14 Aug 2017Source
  • 1 Proforma of Allotment letterPROFORMA OF ALLOTMENT LEETER.pdf · uploaded 14 Aug 2017Source
  • 2 Proforma of Allotment letterAGREEMENT FOR SALE-ilovepdf-compressed (1).pdf · uploaded 14 Aug 2017Source
  • 1 OtherCOMPLITION CERTIFICATE.pdf · uploaded 19 Jan 2018Source
  • 1 Certificates of Architect (Form 4)FORM 4 ARCHITECT CERTIFICATE AFTER COMLETION OF PROJECT.pdf · uploaded 29 Mar 2018Source
  • 2 Certificates of Architect (Form 4)FORM 4 WITH COMPLETION CERTIFICATE.pdf · uploaded 11 Apr 2018Source
  • 1 Certificates of CA (Form 5)SUPRABHAT CONSTRUCTION.pdf · uploaded 29 Sep 2018Source

Technical

  • Documentbuilding plan approval 1-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • Documentbuilding plan approval 2-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • Documentbuilding plan approval 1-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source
  • Documentbuilding plan approval 2-ilovepdf-compressed.pdf · uploaded 14 Aug 2017Source

Technical (Architect)

  • DocumentARCHITECH CERTIFICATE.pdf · uploaded 14 Aug 2017Source

Technical (Engineer)

  • Documentenginerring certificate.pdf · uploaded 14 Aug 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik, Nashik taluka

Survey, CTS, gat or plot numbers

125/3

Boundaries

North
9 Mtr Road
South
22
East
Plot No 4
West
Plot No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUmesh Bagul—
EngineerAvinash Malpani—
OtherSagar Shah—
OtherSuyog Khodke—