Wallfort Garden

Lapsed

Malegaon (M Corp.), Nashik 423203 |Promoter: Navakar Developers

Residential / Group HousingRERAP51600013498
9 Oct 2017Registered with MahaRERA
31 Mar 2021Promised completion
3Buildings
2MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
3
Land area for this project
4,379 sq m (47,139 sq ft)
Permissible built-up area
7,883 sq m (84,850 sq ft)
Sanctioned built-up area
4,140 sq m (44,559 sq ft)
Recreational open space
2,969 sq m (31,959 sq ft)
Planning authority
Malegaon Municipal Corporation
Address
Final Plot No. 78 Pt 10 and 11PIN 423203
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20670, 77.29798
Wallfort Garden is at latitude 19.20670, longitude 77.29798.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2021

The latest completion date on record passed 5 years and 7 months ago.

Registered
9 Oct 2017
Promised
31 Mar 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000134989 Oct 201731 Mar 2021—Navakar DevelopersProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building (P51600013498)——
WALLFORT GARDEN C,D,EandF6—
Wallfort Garden Wing Aand B6—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
WALLFORT GARDEN C,D,EandFClosed/Covered00001
WALLFORT GARDEN C,D,EandFOpen Space00004
Wallfort Garden Wing Aand BClosed/Covered000096
Wallfort Garden Wing Aand BOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

WALLFORT GARDEN C,D,EandF

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure90%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Wallfort Garden Wing Aand B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
  • Sanitary Fittings within the flats / premises85%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsInternal Roads Created100%
  • Water SupplyUG/OH WATER TANK & WATER LINES INSTALLED80%
  • Sewerage (Chamber, Lines, Septic Tank , STP)IC80%
  • Storm Water DrainsSEPTIC TANK0%
  • Landscaping & Tree PlantingDRAINGE LINES LAID30%
  • Street LightingWORK YET TO START100%
  • Community BuildingsPLANTATION STARTEDNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterWORK YET TO STARTNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting60%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsRAIN WATER LINES TAKEN DOWN60%
  • Electrical meter room, sub-station, receiving station70%
  • Aggregate area of recreational Open SpaceUG FIRE TANK CONSTRUCTED20%
  • Open ParkingMETER ROOM CONSTRUCTEDNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

40 documents held by Deedo, 49 filings listed on MahaRERA's project page

Title

Encumbrances

Commencement certificates

Form 1

Form 2s

Form b

Registration certificate

Form 5s

Others

Allotment letters

Layout plans

Building plans

Document library

  • Copy of Layout Approval (in case of layout)LAYOUT_A3.pdf · uploaded 22 Sep 2017View
  • Copy of the legal title report712_Plot11.pdf · uploaded 22 Sep 2017View
  • Other712_Plot10.pdf · uploaded 22 Sep 2017View
  • Building Plan Approval (IOD)PLOT11.pdf · uploaded 22 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentPLOT10.pdf · uploaded 22 Sep 2017View
  • Details of encumbrancesNO_ENCUMBRANCES.pdf · uploaded 22 Sep 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH_CERTIFICATE.pdf · uploaded 22 Sep 2017View
  • Proforma of Allotment letterALLOTMENT_LETTER.pdf · uploaded 22 Sep 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)jpg2pdf.pdf · uploaded 26 Sep 2017View
  • Declaration in FORM BAFFIDAVIT.pdf · uploaded 27 Sep 2017View
  • Building Plan Approval (IOD)PLAN.pdf · uploaded 27 Sep 2017View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Navakar FY 2022_compressed.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Navakar FY 2021_compressed.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Navakar FY 2022_compressed.pdf · uploaded 11 Apr 2023View
  • Declaration about Commencement CertificatePlot No 11 Further CC.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)ITR-V_AAFFN4919C_2017-18_237891531101017.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Navakar FY 2019_compressed.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Navkar FY 2017-18.pdf · uploaded 11 Apr 2023View
  • Commencement Certificates / NA Order for plotted developmentPlot no 10 Commncement.pdf · uploaded 1 Jun 2023View
  • Commencement Certificates / NA Order for plotted developmentPlot no 10 Further CC.pdf · uploaded 1 Jun 2023View
  • Commencement Certificates / NA Order for plotted developmentPlot No 11 Commencement.pdf · uploaded 1 Jun 2023View
  • Commencement Certificates / NA Order for plotted developmentPlot No 11 Further CC.pdf · uploaded 1 Jun 2023View
  • Copy of Layout Approval (in case of layout)Layout Approval 05112012.pdf · uploaded 1 Jun 2023View
  • Copy of Layout Approval (in case of layout)Revised Layout 24082021.pdf · uploaded 1 Jun 2023View
  • Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 1 Jun 2023View
  • Disclosure of sold/ booked inventoryDisclosure of Sold.pdf · uploaded 3 Jun 2023View
  • Deviation Report with respect to Allotment letterDeviation Report.pdf · uploaded 3 Jun 2023View
  • CERSAI detailsUndertaking on report from cersai.pdf · uploaded 3 Jun 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 -2017-2018.pdf · uploaded 3 Jun 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5-2018-2019.pdf · uploaded 3 Jun 2023View
  • a Details of encumbrances concerned to FinanceNon Encumbrance Cer.pdf · uploaded 3 Jun 2023View
  • b Details of encumbrances concerned to LegalNon Encumbrance Cer.pdf · uploaded 3 Jun 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5- 2019-2020.pdf · uploaded 3 Jun 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 -2020-2021.pdf · uploaded 3 Jun 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 -2021-2022.pdf · uploaded 3 Jun 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2- 31032018.pdf · uploaded 5 Jun 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2- 31032019.pdf · uploaded 5 Jun 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 -31032020.pdf · uploaded 5 Jun 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2-31032021.pdf · uploaded 5 Jun 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2- 31032022.pdf · uploaded 5 Jun 2023View

Promoter documents

  • Legal Title report712_Plot11.pdf · uploaded 22 Sep 2017View
  • Declaration Form BAFFIDAVIT.pdf · uploaded 27 Sep 2017View

Technical documents

  • Layout ApprovalLAYOUT_A3.pdfView
  • Building Plan ApprovalPLOT11.pdfView
  • Building Plan ApprovalPLAN.pdfView
  • Layout ApprovalLayout Approval 05112012.pdfView
  • Layout ApprovalRevised Layout 24082021.pdfView

Other legal documents

  • Other712_Plot10.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT_LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Malegaon (M Corp.), Malegaon taluka

Survey, CTS, gat or plot numbers

11Final Plot No. 78 Pt 10

As published on MahaRERA's project page

Final Plot No. 78 Pt 10 and 11

Boundaries

North
Play Ground Plot and Road
South
Open Space and Plot 78pt
East
DP Road
West
DP Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Ritesh R Kankaria—
EngineerSantosh Yamasa Kokane—

Source: MahaRERA project page. Contact details are not shown.