Navshya Elite

Completed

Aanandwali, Nashik 422013 |Promoter: Dhruv Developers

Residential / Group HousingRERAP51600009682
22 Aug 2017Registered with MahaRERA
31 Dec 2017Promised completion
31 Mar 2018Revised completionPushed back 3 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
963 sq m (10,362 sq ft)
Permissible built-up area
1,339 sq m (14,417 sq ft)
Sanctioned built-up area
1,339 sq m (14,417 sq ft)
Address
S.No.65/1/1A Plot No.2 and 3PIN 422013
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.01584, 73.74439
Navshya Elite is at latitude 20.01584, longitude 73.74439.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 months

The latest completion date on record passed 8 years and 7 months ago.

Registered
22 Aug 2017
Promised
31 Dec 2017
Revised
31 Mar 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160000968222 Aug 201731 Dec 201731 Mar 2018Dhruv DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Navshya Elite17—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000018
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Navshya Elite

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWork Done Borwell100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Chambers100%
  • Storm Water DrainsLines and Septic TankNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Energy managemcntWork DoneNot applicable
  • Fire protection and fire safety requirements100%
  • Electrical meter room, sub-station, receiving stationWork DoneNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

24 documents held by Deedo, 32 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Form 5

Allotment letter (2)

Show all 56 documentsShow fewer documents

Allotment letter (2)

Registration certificate

Extension certificate

Form 4

Other (10)

Layout plan

Building plan

Document library

  • Details of encumbrancesDetails of encumbrances.pdf · uploaded 15 Aug 2017View
  • Declaration in FORM BDeclaration Form B.pdf · uploaded 15 Aug 2017View
  • Building Plan Approval (IOD)Building plan Approval.pdf · uploaded 15 Aug 2017View
  • Copy of the legal title reportCopy of legal title report.pdf · uploaded 15 Aug 2017View
  • Copy of Layout Approval (in case of layout)Copy of layout approval.pdf · uploaded 15 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 15 Aug 2017View
  • Otherpartnership deed new.pdf · uploaded 15 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certificate of Architect Form-1.PDF · uploaded 15 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)certificate of Engineer Form-2.PDF · uploaded 15 Aug 2017View
  • Certificates of CA (Form 5)Certificate of CA Form 5.PDF · uploaded 15 Aug 2017View
  • Proforma of Allotment letteragreemen to sale.pdf · uploaded 15 Aug 2017View
  • OtherDevelopment Agreement Part 1.PDF · uploaded 16 Aug 2017View
  • Otherdevelopment agreement Part 2.pdf · uploaded 16 Aug 2017View
  • OtherDevelopment Agreement Part 3.pdf · uploaded 16 Aug 2017View
  • Proforma of Allotment letterProforma of Allotment Letter.PDF · uploaded 16 Aug 2017View
  • OtherReceipt for Application for Completion Certificate.pdf · uploaded 16 Aug 2017View
  • OtherCompletion Certificate Navshya Elite.pdf · uploaded 14 Jan 2018View
  • Certificates of Architect (Form 4)Form-4.pdf · uploaded 22 Jan 2018View
  • Status of Formation of Legal EntityDeclaration index-II.pdf · uploaded 21 Mar 2018View
  • Status of Conveyancedeed_of_apartment_index-II_compressed.pdf · uploaded 21 Mar 2018View
  • Status of ConveyanceDeclaration index-II.pdf · uploaded 21 Mar 2018View

Promoter documents

  • Declaration Form BDeclaration Form B.pdf · uploaded 15 Aug 2017View
  • Legal Title reportCopy of legal title report.pdf · uploaded 15 Aug 2017View

Technical documents

  • Building Plan ApprovalBuilding plan Approval.pdfView
  • Layout ApprovalCopy of layout approval.pdfView

Other legal documents

  • Otherpartnership deed new.pdfView
  • OtherDevelopment Agreement Part 1.PDFView
  • Otherdevelopment agreement Part 2.pdfView
  • OtherDevelopment Agreement Part 3.pdfView
  • OtherReceipt for Application for Completion Certificate.pdfView
  • OtherCompletion Certificate Navshya Elite.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of Allotment Letter.PDFView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aanandwali, Nashik taluka

Survey, CTS, gat or plot numbers

23365/1/1AS.No.65/1/1A Plot No.2

As published on MahaRERA's project page

S.No.65/1/1A Plot No.2 and 3

Boundaries

North
24 Meter Road
South
7-50 Meter Road
East
Plot No 1
West
9 Meter Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRishikesh Pawar—
EngineerAmit Sanap and Associates—
EngineerYogin Kulkarni—

Source: MahaRERA project page. Contact details are not shown.