BLD_006176Completed4 floors
Tower - 1, C -Wing · Chhoriya Residency Nandurbar
Nandurbar (M Cl) · RERA P49700009502
4Sanctioned habitable floorsregistration certificate
31 Dec 2019Revised completionpromised 31 Dec 2018
Floors
4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P49700009502 · registered 22 Aug 2017
- Promised completion
- 31 Dec 2018
- Revised completion
- 31 Dec 2019
- Sanctioned habitable floors
- 4
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Flat | 106.1 m² (1,142 sq.ft) | 10 | not published |
| Flat | 107.7 m² (1,159 sq.ft) | 2 | not published |
| Shops | 24.9 m² (268 sq.ft) | 2 | not published |
| Shops | 34.6 m² (373 sq.ft) | 2 | not published |
| Shops | 41.9 m² (451 sq.ft) | 2 | not published |
| Total | 18 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 7 |
| Open Space | 0 | 0 | 0 | 5 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor0%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
- Sanitary Fittings within the flats / premises85%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Data through8 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology