Bhanudhan Plaza
LapsedNandurbar 425412 |Promoter: Shah Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Lapsed
- Buildings
- 6
- Land area for this project
- 3,038 sq m (32,698 sq ft)
- Permissible built-up area
- 5,468 sq m (58,856 sq ft)
- Sanctioned built-up area
- 4,231 sq m (45,545 sq ft)
- Planning authority
- Nandurbar Municipal Council
- Address
- S NO 174/1/1 PLOT NO 28 TO 30 AND 36 TO 40, NandurbarPIN 425412
- Designated bank account
- Axis Bank
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 1 Sep 2017
- Promised
- 30 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P49700011929 | 1 Sep 2017 | 30 Dec 2023 | — | Shah Enterprises | Project page |
6 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| Bhanudhan Plaza Building No 1 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 1 | Open Space | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 2 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 2 | Open Space | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 3 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 3 | Open Space | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 4 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Building No 4 | Open Space | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Row House 1 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Row House 1 | Open Space | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Row House 2 | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Bhanudhan Plaza Row House 2 | Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Bhanudhan Plaza Building No 1
Bhanudhan Plaza Building No 2
Bhanudhan Plaza Building No 3
Bhanudhan Plaza Building No 4
Bhanudhan Plaza Row House 1
Bhanudhan Plaza Row House 2
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
24 documents held by Deedo, 27 filings listed on MahaRERA's project page
Others
Form 1s
Form 2s
Document library
- Details of encumbrancesNo Encumbrance Certiificate.pdf · uploaded 29 Aug 2017View
- Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 Aug 2017View
- Copy of the legal title reportTitle Report.pdf · uploaded 30 Aug 2017View
- Declaration in FORM BForm B.pdf · uploaded 30 Aug 2017View
- Building Plan Approval (IOD)Building Plan.pdf · uploaded 31 Aug 2017View
- Copy of Layout Approval (in case of layout)Building Plan.pdf · uploaded 31 Aug 2017View
- Proforma of Allotment letterAgreement Draft.pdf · uploaded 31 Aug 2017View
- Proforma of Allotment letterAllotment Letter.pdf · uploaded 31 Aug 2017View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 9 Dec 2022View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA Audit Report 18-19 final.pdf · uploaded 1 Jul 2024Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Audit Report 19-20 final.pdf · uploaded 1 Jul 2024Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Audit Report 20-21 final.pdf · uploaded 1 Jul 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)RERA Audit Report_March 18 final.pdf · uploaded 1 Jul 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect Certificate Mar 18.pdf · uploaded 1 Aug 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Architect Certificate Mar 19.pdf · uploaded 1 Aug 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architect Certificate Mar 20.pdf · uploaded 1 Aug 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Architect Certificate July 20.pdf · uploaded 1 Aug 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)5 engineer certificate Mar 18.pdf · uploaded 1 Aug 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Engineer Certificate Mar 19.pdf · uploaded 1 Aug 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)7 engineer certificate Mar 20.pdf · uploaded 1 Aug 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)8 engineer certificate Jul 20.pdf · uploaded 1 Aug 2024View
- Form 5 (FY 2017-2018)RERA Audit Report_March 18 final.pdf · uploaded 14 Jul 2026View
Promoter documents
Proforma allotment letter
- Proforma allotment letterAllotment Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nandurbar, Nandurbar taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
S NO 174/1/1 PLOT NO 28 TO 30 AND 36 TO 40
Boundaries
- North
- Plot No 31 And 36
- South
- Plot No 7 And 41
- East
- 12 Mtr Road And 24 Mtr Dp Road
- West
- 9 Mtr Colony Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hemant Premraj Maheshwari | — |
| Chartered accountant | P.N. SABADRA & Associates | — |
| Chartered accountant | RSPH & Associates | — |
| Engineer | Hemant Premraj Maheshwari | — |
| Engineer | Milind Shyamsundar Rathi | — |
Source: MahaRERA project page. Contact details are not shown.