Aniruddha Buildcon

Completed

Shankarpur, Nagpur 441108 |Promoter: Aniruddha Buildcon

21 Jun 2019Registered with MahaRERA
30 Sep 2022Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
13,534 sq m (1,45,675 sq ft)
Permissible built-up area
21,735 sq m (2,33,954 sq ft)
Sanctioned built-up area
21,735 sq m (2,33,954 sq ft)
Recreational open space
2,438 sq m (26,239 sq ft)
Address
Kh No. 42 Mouza Shankarpur, Shankarpur Street, ShankarpurPIN 441108
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Aniruddha Buildcon is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2022

The latest completion date on record passed 4 years and 1 month ago.

Registered
21 Jun 2019
Promised
30 Sep 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050002129921 Jun 201930 Sep 2022—Aniruddha BuildconProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & Footpaths0100%
  • Water Supply0100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)0100%
  • Storm Water Drains0100%
  • Landscaping & Tree Planting0100%
  • Street Lighting0100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Water0100%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open Space0100%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

4 documents held by Deedo, 23 filings listed on MahaRERA's project page

Title

Form b

Registration certificate

Other

Document library

  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1_compressed (1).pdf · uploaded 8 Jun 2019Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2_compressed.pdf · uploaded 8 Jun 2019Source
  • Copy of the legal title reportTitle Report_compressed.pdf · uploaded 8 Jun 2019View
  • Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 8 Jun 2019Source
  • Building Plan Approval (IOD)Layout Plan.pdf · uploaded 8 Jun 2019Source
  • Commencement Certificates / NA Order for plotted developmentCommencement CeRT compressed.pdf · uploaded 8 Jun 2019Source
  • Details of encumbrancesForm-B Compressed.pdf · uploaded 10 Jun 2019View
  • Declaration in FORM BForm-B Compressed.pdf · uploaded 10 Jun 2019View
  • Proforma of Allotment letterSale_Draft_-_Draft.pdf · uploaded 11 Jun 2019Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 25 Aug 2021Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 02.pdf · uploaded 25 Aug 2021Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A.pdf · uploaded 25 Aug 2021Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRL Letters.pdf · uploaded 25 Aug 2021Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 18-19.pdf · uploaded 20 May 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 19-20.pdf · uploaded 20 May 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20-21.pdf · uploaded 20 May 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 20 May 2023Source
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 20 May 2023Source

Promoter documents

  • Legal Title reportTitle Report_compressed.pdf · uploaded 8 Jun 2019View
  • Declaration Form BForm-B Compressed.pdf · uploaded 10 Jun 2019View

Technical documents

  • NA Order for Plotted DevelopmentLayout Plan.pdfSource
  • Layout ApprovalLayout Plan.pdfSource

Proforma allotment letter

  • Proforma allotment letterSale_Draft_-_Draft.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shankarpur, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

Kh No. 42 Mouza Shankarpur

As published on MahaRERA's project page

Kh No. 42 Mouza Shankarpur

Boundaries

North
Survey No 35-1k 35-1kh 35-2
South
Survey No 43-143-2
East
Pandhan
West
Survey No 41-141-2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRavi Chaudhari—
Chartered accountantChhajed & Co—
EngineerMahendra S Bhandari—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology