Completed

Nagpur (M Corp.), Nagpur 440012 |Promoter: Vignesh Nirman

18 Aug 2017Registered with MahaRERA
31 Dec 2018Promised completion
1Building
14Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
Residential cum comm14 units in all
Land area for this project
542 sq m (5,834 sq ft)
Permissible built-up area
1,403 sq m (15,102 sq ft)
Sanctioned built-up area
1,241 sq m (13,358 sq ft)
Address
20PIN 440012
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
Yes
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.44769, 73.97150
Vignesh Square is at latitude 18.44769, longitude 73.97150.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2018

The latest completion date on record passed 7 years and 10 months ago.

Registered
18 Aug 2017
Promised
31 Dec 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050000825818 Aug 201731 Dec 2018—Vignesh NirmanProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vignesh Square1414

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 units registered

Residential cum comm · 14 units
TypeCarpet areaUnits
Residential cum comm542 sq m · 5,834 sq ft14

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vignesh Square

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor95%
  • Slabs of Super Structure30%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAFTER POSSESSION0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER PLAN0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAS PER PLAN0%
  • Electrical meter room, sub-station, receiving stationONLY ELECTRICAL PANNEL0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAS PER PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

5 documents held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Other

Layout plans

Building plan

Document library

  • Copy of the legal title reportLegal title.pdf · uploaded 14 Aug 2017Source
  • Copy of Layout Approval (in case of layout)dRAWING 1.pdf · uploaded 14 Aug 2017View
  • Copy of Layout Approval (in case of layout)Drawing3.pdf · uploaded 14 Aug 2017View
  • Copy of Layout Approval (in case of layout)New Doc 2017-08-14 (6)_2.pdf · uploaded 14 Aug 2017View
  • Proforma of Allotment letterAGREEMENT-RERA-VIGNESH NIRMAN.pdf · uploaded 14 Aug 2017Source
  • Proforma of Allotment letterE-ALLOTMENT LETTER.pdf · uploaded 14 Aug 2017Source
  • Declaration in FORM BForm B by Atif.pdf · uploaded 14 Aug 2017Source
  • Details of encumbranceseNCUMBRANCE.pdf · uploaded 14 Aug 2017Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate.pdf · uploaded 14 Aug 2017Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate.pdf · uploaded 14 Aug 2017Source
  • Building Plan Approval (IOD)Building Permit.pdf · uploaded 14 Aug 2017View
  • Building Plan Approval (IOD)dRAWING 1.pdf · uploaded 14 Aug 2017View
  • Building Plan Approval (IOD)Drawing3.pdf · uploaded 14 Aug 2017View
  • Building Plan Approval (IOD)New Doc 2017-08-14 (6)_2.pdf · uploaded 14 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentOCCUPANCY CERTIFICATE.pdf · uploaded 27 May 2019Source
  • Certificates of Architect (Form 4)square.pdf · uploaded 31 Jul 2019Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentVignesh Square, Occupancy Certificate (1).pdf · uploaded 20 Feb 2023Source

Promoter documents

  • Legal Title reportLegal title.pdf · uploaded 14 Aug 2017Source
  • Declaration Form BForm B by Atif.pdf · uploaded 14 Aug 2017Source

Technical documents

  • Layout ApprovaldRAWING 1.pdfView
  • Layout ApprovalDrawing3.pdfView
  • Layout ApprovalNew Doc 2017-08-14 (6)_2.pdfView
  • Building Plan ApprovalBuilding Permit.pdfView
  • Building Plan ApprovaldRAWING 1.pdfView
  • Building Plan ApprovalDrawing3.pdfView
  • Building Plan ApprovalNew Doc 2017-08-14 (6)_2.pdfView

Proforma allotment letter

  • Proforma allotment letterE-ALLOTMENT LETTER.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

20

As published on MahaRERA's project page

20

Boundaries

North
Road
South
Cts No 351
East
Road
West
Portion Of Plot No20

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLokesh Kadu—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology