BLD_008998Completed9 floors

Wing C and D · Shri Swami Puram Wing C and D

Nagpur (M Corp.) · RERA P50500008250

9Sanctioned habitable floorsregistration certificate
31 Dec 2017Promised completion

Floors

9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500008250 · registered 18 Aug 2017
Promised completion
31 Dec 2017
Sanctioned habitable floors
9

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK32.4 m² (349 sq.ft)14not published
2BHK49.2 m² (530 sq.ft)27not published
2BHK49.5 m² (532 sq.ft)27not published
2BHK52.9 m² (569 sq.ft)56not published
3BHK84.5 m² (909 sq.ft)13not published
SHOP11 m² (118 sq.ft)1not published
SHOP12 m² (129 sq.ft)2not published
SHOP12.1 m² (131 sq.ft)1not published
SHOP12.4 m² (133 sq.ft)3not published
SHOP13.1 m² (141 sq.ft)1not published
SHOP14.5 m² (156 sq.ft)1not published
SHOP14.7 m² (158 sq.ft)1not published
SHOP14.9 m² (160 sq.ft)1not published
SHOP15.5 m² (166 sq.ft)4not published
SHOP15.5 m² (167 sq.ft)1not published
SHOP17 m² (183 sq.ft)1not published
SHOP17.1 m² (184 sq.ft)1not published
SHOP19.2 m² (207 sq.ft)1not published
SHOP19.7 m² (212 sq.ft)1not published
SHOP20.8 m² (223 sq.ft)1not published
SHOP23.5 m² (253 sq.ft)1not published
SHOP25.2 m² (272 sq.ft)1not published
SHOP25.5 m² (275 sq.ft)1not published
Total161

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered000185
Open Space00044

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology