Shatabdi Row Houses
Certificate SignedNagpur (M Corp.), Nagpur 440035 |Promoter: Shayona Co-Operant
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 4BHK7 units in all
- Address
- Plot No 18, 19, 20 & 21, Punapur, Ward No 21PIN 440035
- Designated bank account
- 220
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Jan 2029
- Registered
- 27 Mar 2023
- Promised
- 31 Jan 2029
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500050254 | 27 Mar 2023 | 31 Jan 2029 | 31 Jan 2029 | Shayona Co-Operant | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Shatabdi Row Houses | 3 | 7 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
2 of 7 units booked (29%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4BHK | 137.7 sq m · 1,482 sq ft | 1 | 0 |
| 4BHK | 138.18 sq m · 1,487 sq ft | 1 | 0 |
| 4BHK | 138.42 sq m · 1,490 sq ft | 3 | 1 |
| 4BHK | 141.67 sq m · 1,525 sq ft | 1 | 0 |
| 4BHK | 144.59 sq m · 1,556 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
54 documents held by Deedo, 88 filings listed on MahaRERA's project page
Show all 142 documentsShow fewer documents
Commencement certificate (2)
Form 1 (21)
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
Title report
- Title reportDate not statedView
Encumbrance details (4)
Layout plan (9)
Form B
- Form BDate not statedView
Legal
Migrated
- 1 PAN CardPAN CARD SHAYONA.pdf · uploaded 21 Jan 2023View
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 21 Jan 2023View
- 1 a Details of encumbrances concerned to FinanceTitle Verification Report.pdf · uploaded 21 Jan 2023View
- 2 a Details of encumbrances concerned to Financeencumbrance certificate (3).pdf · uploaded 21 Jan 2023View
- 1 b Details of encumbrances concerned to LegalTitle Verification Report.pdf · uploaded 21 Jan 2023View
- 2 b Details of encumbrances concerned to Legalencumbrance certificate (3).pdf · uploaded 21 Jan 2023View
- 1 Copy of Layout Approval (in case of layout)1 (1).pdf · uploaded 21 Jan 2023View
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Permit.pdf · uploaded 21 Jan 2023View
- 2 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 21 Jan 2023View
- 3 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 21 Jan 2023View
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permit.pdf · uploaded 21 Jan 2023View
- 1 Declaration about Commencement Certificateform d.pdf · uploaded 21 Jan 2023View
- 1 Declaration in FORM Bform b revi.pdf · uploaded 21 Jan 2023View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ANNEXURE 1 (3).pdf · uploaded 21 Jan 2023View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (2).pdf · uploaded 21 Jan 2023View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (3)_compressed.pdf · uploaded 21 Jan 2023View
- 1 Disclosure of Interest in Other Real Estate OrganizationsDECLARATION FOR NO INTEREST.pdf · uploaded 21 Jan 2023View
- 1 Proforma of Allotment letterALLOTMENT LETTER_merged.pdf · uploaded 21 Jan 2023View
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank account declaration (2).pdf · uploaded 21 Jan 2023View
- 1 Deviation Report with respect to Allotment letterALLOTMENT LETTER_merged.pdf · uploaded 21 Jan 2023View
- 1 Other – LegalCREDAI Certificate (1)_compressed-2.pdf · uploaded 21 Jan 2023View
- 3 a Details of encumbrances concerned to FinanceENCUMBRANCE NEW.pdf · uploaded 6 Feb 2023View
- 3 b Details of encumbrances concerned to LegalENCUMBRANCE NEW.pdf · uploaded 6 Feb 2023View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 REV_compressed.pdf · uploaded 9 Feb 2023View
- 1 CERSAI detailsLATEST CERSAI.pdf · uploaded 13 Mar 2023View
- 1 Proforma of Agreement for saleFINAL AS2.pdf · uploaded 14 Mar 2023View
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION.pdf · uploaded 14 Mar 2023View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 2 Jun 2023View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 2 Jun 2023View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 2 Jun 2023View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 28 Aug 2023View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Enginees's Certificate.pdf · uploaded 28 Aug 2023View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate_compressed.pdf · uploaded 28 Aug 2023View
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE.pdf · uploaded 27 Oct 2023View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINER'S CERTIFICATE.pdf · uploaded 27 Oct 2023View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CHARTERED ACCOUNTANT'S CERTIFICATE_compressed (1).pdf · uploaded 27 Oct 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ANNUAL REPORT.pdf · uploaded 27 Oct 2023View
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH CERTIFICATE.pdf · uploaded 14 Feb 2024View
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CERTIFICATE.pdf · uploaded 14 Feb 2024View
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 14 Feb 2024View
- Form 1ARCHITECT'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 2ENGINER'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 3CHARTERED ACCOUNTANT'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 3CHARTERED ACCOUNTANT'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 3CHARTERED ACCOUNTANT'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 3CHARTERED ACCOUNTANT'S CERTIFICATE 30092023.pdf · uploaded 5 Oct 2024Source
- Form 1ARCH CERTIFICATE 31122023.pdf · uploaded 5 Oct 2024Source
- Form 2ENG CERTIFICATE 31122023.pdf · uploaded 5 Oct 2024Source
- Form 3FORM 3 31122023.pdf · uploaded 5 Oct 2024Source
- Form 1ENG CERTIFICATE 31122023.pdf · uploaded 5 Oct 2024Source
- Form 2ARCH CERTIFICATE 31122023.pdf · uploaded 5 Oct 2024Source
- Form 3FORM 3 31032024.pdf · uploaded 5 Oct 2024Source
- Form 3FORM 3 31122023.pdf · uploaded 5 Oct 2024Source
- Form 1FORM 2 31032024.pdf · uploaded 5 Oct 2024Source
- Form 3FORM 1 31032024.pdf · uploaded 5 Oct 2024Source
- Form 2FORM 3 31032024.pdf · uploaded 5 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31032024.pdf · uploaded 17 Oct 2024View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30062024.pdf · uploaded 17 Oct 2024View
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 17 Oct 2024View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31032024.pdf · uploaded 17 Oct 2024View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30062024.pdf · uploaded 17 Oct 2024View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31032024.pdf · uploaded 17 Oct 2024View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30062024.pdf · uploaded 17 Oct 2024View
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 17 Oct 2024View
- 2 Architect’s Certificate on Completion of Project (Form 4)FORM 4 FINAL.pdf · uploaded 19 Oct 2024View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SHATABDI.pdf · uploaded 13 Nov 2024View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHATABDI FORM 3.pdf · uploaded 13 Nov 2024View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SHATABDI (2).pdf · uploaded 13 Nov 2024View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31122024_compressed.pdf · uploaded 21 Feb 2025View
Technical
- Document1 (1).pdf · uploaded 21 Jan 2023View
- DocumentBuilding Permit.pdf · uploaded 21 Jan 2023View
- Document2.pdf · uploaded 21 Jan 2023View
- Document3.pdf · uploaded 21 Jan 2023View
- Annexure-A as per order 50/2024FORM 1 31032024.pdf · uploaded 23 Sep 2024Source
- OthersFORM 1 30062024.pdf · uploaded 23 Sep 2024Source
- OthersFORM 2 31032024.pdf · uploaded 23 Sep 2024Source
- OthersFORM 2 30062024.pdf · uploaded 23 Sep 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nagpur (M Corp.), Nagpur (Urban) taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Kh No 30-2
- South
- Kh No 30-1
- East
- Pandhan And Punapur Road
- West
- Portion Of Kh No30-3 Owned By Hariram Wath
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sarju Pravin Patel Patel | — |
| Chartered accountant | Shanu Bose Bose | — |
| Chartered accountant | S K Panpaliya | — |
| Engineer | Devendra Patel Patel | — |
Source: MahaRERA project page. Contact details are not shown.