Skip to content
Deedo home
Menu

Royal Crest

Completed

Nagpur (M Corp.), Nagpur 440001 |Promoter: Navabharat Infraventures Ltd.

Residential / Group HousingRERAP50500001369
27 Jul 2017Registered with MahaRERA
31 Mar 2019Promised completion
1Building
46Units registered
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
3 BHK46 units in all
Land area for this project
1,692 sq m (18,213 sq ft)
Permissible built-up area
5,901 sq m (63,514 sq ft)
Sanctioned built-up area
3,201 sq m (34,451 sq ft)
Recreational open space
100 sq m (1,076 sq ft)
Address
455PIN 440001
Designated bank account
Indusind Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.13239, 79.08169
Royal Crest is at latitude 21.13239, longitude 79.08169.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2019

The latest completion date on record passed 7 years and 7 months ago.

Registered
27 Jul 2017
Promised
31 Mar 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050000136927 Jul 201731 Mar 2019—Navabharat Infraventures Ltd.Project page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Royal Crest1746

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

46 units registered

3 BHK · 46 units
TypeCarpet areaUnits
3 BHK67.84 sq m · 730 sq ft46

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space000025

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Royal Crest

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
  • Sanitary Fittings within the flats / premises85%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyPlumbing work80%
  • Sewerage (Chamber, Lines, Septic Tank , STP)O.H & UG Tanks completed.100%
  • Storm Water DrainsCompleted100%
  • Landscaping & Tree PlantingWork in Progress40%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Energy managemcnt100Not applicable
  • Fire protection and fire safety requirements80%
  • Electrical meter room, sub-station, receiving stationPump & Hose reels pending80%
  • Aggregate area of recreational Open SpaceWork in progress80%
  • Open Parking100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

16 documents held by Deedo, 29 filings listed on MahaRERA's project page

Allotment letters

Title

Form b

Registration certificate

Form 5s

Form 4

Others

Building plans

Layout plan

Document library

  • Copy of the legal title report2-Title verification.pdf · uploaded 26 Jul 2017View
  • Details of encumbrances3-Details of Encumbrance.pdf · uploaded 26 Jul 2017Source
  • Proforma of Allotment letter5-A-Allotment letter.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)7-Certificate of Architect-Form 1.pdf · uploaded 26 Jul 2017Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11-Certificate of Engineer Form 2.pdf · uploaded 26 Jul 2017Source
  • Building Plan Approval (IOD)13-A- Building Permit.pdf · uploaded 26 Jul 2017View
  • Building Plan Approval (IOD)13-B- Approved Building Plan.pdf · uploaded 26 Jul 2017View
  • Copy of Layout Approval (in case of layout)4- Layout Approval.pdf · uploaded 26 Jul 2017View
  • Proforma of Allotment letter5-B Draft Agreement To Sale.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM B6-Declration-Form B.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM B6-Declration-Form B.pdf · uploaded 26 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 11 Apr 2018Source
  • Form 2AForm 2a.pdf · uploaded 10 Jun 2019Source
  • Certificates of CA (Form 5)form 5.pdf · uploaded 10 Jun 2019View
  • Certificates of Architect (Form 4)Form 4.pdf · uploaded 10 Jun 2019View
  • OtherOccupancy Crtificate.pdf · uploaded 10 Jun 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)SELF DECLARATION.pdf · uploaded 11 Oct 2019View
  • Status of ConveyanceStatus of conveyance.pdf · uploaded 24 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Audit Statement of 2019-20.pdf · uploaded 24 Dec 2019View
  • Status of ConveyanceStatus of conveyance.pdf · uploaded 24 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Audit 2018-19.pdf · uploaded 24 Dec 2019View

Promoter documents

  • Legal Title report2-Title verification.pdf · uploaded 26 Jul 2017View
  • Declaration Form B6-Declration-Form B.pdf · uploaded 26 Jul 2017View
  • Declaration Form B6-Declration-Form B.pdf · uploaded 26 Jul 2017View

Technical documents

  • Building Plan Approval13-A- Building Permit.pdfView
  • Building Plan Approval13-B- Approved Building Plan.pdfView
  • Layout Approval4- Layout Approval.pdfView

Other legal documents

  • OtherOccupancy Crtificate.pdfView

Proforma allotment letter

  • Proforma allotment letter5-B Draft Agreement To Sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

455

As published on MahaRERA's project page

455

Boundaries

North
12 m Wide Road
South
Krishna Bhamani Apartment
East
9 m Wide Road
West
Mayuresh Apartment

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectChoudhary consultants—
EngineerP S Patankar—

Source: MahaRERA project page. Contact details are not shown.