Skip to content
Deedo home
Menu

Enrico Heights

Lapsed

Nagpur (M Corp.), Nagpur 440015 |Promoter: Universal Drinks Private Limited

7 Aug 2017Registered with MahaRERA
30 Jun 2018Promised completion
30 Oct 2020Revised completionPushed back 2 years and 4 months
1Building
86Units registered
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
1
Unit types
3BHK, 4BHK, Shop 01 lg, Shop 01 ug, Shop 02 lg, Shop 02 ug, Shop 03 lg, Shop 03 ug, Shop 04 lg, Shop 04 ug, Shop 05 lg, Shop 05 ug, Shop 06 lg, Shop 06 ug, Shop 07 lg, Shop 07 ug, Shop 08 lg, Shop 08 ug, Shop 09 lg, Shop 09 ug, Shop 10 lg, Shop 10 ug, Shop 11 lg, Shop 11 ug86 units in all
Land area for this project
6,024 sq m (64,837 sq ft)
Permissible built-up area
12,047 sq m (1,29,675 sq ft)
Sanctioned built-up area
12,047 sq m (1,29,675 sq ft)
Address
3, Cs No. 488, Khasara No. 38/1PIN 440015
Designated bank account
Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.10524, 79.06937
Enrico Heights is at latitude 21.10524, longitude 79.06937.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 4 months

The latest completion date on record passed 6 years ago.

Registered
7 Aug 2017
Promised
30 Jun 2018
Revised
30 Oct 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000040227 Aug 201730 Jun 201830 Oct 2020Universal Drinks Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Enrico Heights1886

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

86 units registered

3BHK · 44 units4BHK · 20 unitsShop 01 lg · 1 unitShop 01 ug · 1 unitShop 02 lg · 1 unitShop 02 ug · 1 unitShop 03 lg · 1 unitShop 03 ug · 1 unitShop 04 lg · 1 unitShop 04 ug · 1 unitShop 05 lg · 1 unitShop 05 ug · 1 unitShop 06 lg · 1 unitShop 06 ug · 1 unitShop 07 lg · 1 unitShop 07 ug · 1 unitShop 08 lg · 1 unitShop 08 ug · 1 unitShop 09 lg · 1 unitShop 09 ug · 1 unitShop 10 lg · 1 unitShop 10 ug · 1 unitShop 11 lg · 1 unitShop 11 ug · 1 unit
TypeCarpet areaUnits
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK143.79 sq m · 1,548 sq ft4
3BHK144.38 sq m · 1,554 sq ft4
3BHK144.38 sq m · 1,554 sq ft4
3BHK147.23 sq m · 1,585 sq ft2
3BHK151.05 sq m · 1,626 sq ft2
3BHK161.23 sq m · 1,735 sq ft4
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK173.47 sq m · 1,867 sq ft2
4BHK174.17 sq m · 1,875 sq ft2
4BHK174.17 sq m · 1,875 sq ft2
4BHK182.22 sq m · 1,961 sq ft2
Shop 01 lg169.94 sq m · 1,829 sq ft1
Shop 01 ug181.17 sq m · 1,950 sq ft1
Shop 02 lg92.42 sq m · 995 sq ft1
Shop 02 ug98.53 sq m · 1,061 sq ft1
Shop 03 lg158.36 sq m · 1,705 sq ft1
Shop 03 ug168.82 sq m · 1,817 sq ft1
Shop 04 lg184.89 sq m · 1,990 sq ft1
Shop 04 ug197.11 sq m · 2,122 sq ft1
Shop 05 lg83.39 sq m · 898 sq ft1
Shop 05 ug88.9 sq m · 957 sq ft1
Shop 06 lg90.18 sq m · 971 sq ft1
Shop 06 ug96.14 sq m · 1,035 sq ft1
Shop 07 lg64.48 sq m · 694 sq ft1
Shop 07 ug66.51 sq m · 716 sq ft1
Shop 08 lg42.17 sq m · 454 sq ft1
Shop 08 ug44.96 sq m · 484 sq ft1
Shop 09 lg42.17 sq m · 454 sq ft1
Shop 09 ug44.97 sq m · 484 sq ft1
Shop 10 lg43.05 sq m · 463 sq ft1
Shop 10 ug45.89 sq m · 494 sq ft1
Shop 11 lg63.2 sq m · 680 sq ft1
Shop 11 ug67.38 sq m · 725 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000046
Open Space000072

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Enrico Heights

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETED100%
  • Storm Water DrainsCOMPLETED100%
  • Landscaping & Tree PlantingFRONT LANDSCAPING75%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterSYSTEM TO BE ORDERED95%
  • Solid Waste Management And DisposalPLANNED100%
  • Water conservation /Rain water harvestingUNDER PROGRESS0%
  • Energy managemcntTO BE ORDERED0%
  • Fire protection and fire safety requirementsCOMPLETED100%
  • Electrical meter room, sub-station, receiving stationCOMPLETED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCOMPLETED100%
  • PODIUM GARDENCOMPLETED100%
  • SWIMMING POOLPOOL UNDER CONSTRUCTION90%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

25 documents held by Deedo, 27 filings listed on MahaRERA's project page

Title

Commencement certificate

Encumbrances

Form 1

Form 2

Form b

Registration certificate

Form 5s

Completions

Extension certificate

Others

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reportCopy of the legal title report.PDF · uploaded 25 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.PDF · uploaded 25 Jul 2017View
  • Proforma of Allotment letterAllotment Letter format 1.pdf · uploaded 25 Jul 2017View
  • Details of encumbrancesDetails of encumbrances.PDF · uploaded 26 Jul 2017View
  • Building Plan Approval (IOD)BP.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect cert.pdf · uploaded 28 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer cert (1).pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)scan892.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM Bform b affidavit.PDF · uploaded 31 Jul 2017View
  • Certificates of CA (Form 5)udpl form 5.pdf · uploaded 28 Feb 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentudpl architect certificate of completion.pdf · uploaded 21 Sep 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentpart occupancy certificate.pdf · uploaded 18 Oct 2021View
  • OtherEXTENTION LETTER.pdf · uploaded 18 Oct 2021View
  • OtherENRICO DOD FINAL.pdf · uploaded 18 Oct 2021View
  • Certificates of CA (Form 5)Form 5 (1).pdf · uploaded 28 Dec 2021View
  • Other – Financesociety registration certificate.pdf · uploaded 10 Apr 2024View
  • Other – TechnicalForm 4 Architect Certificate.pdf · uploaded 10 Apr 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameCert_RB_325889_383OKuSsSign.pdf · uploaded 10 Apr 2024View
  • Foreclosure of the ProjectFULL OCCUPANCY CERTIFICATE UDPL.pdf · uploaded 10 Apr 2024View

Promoter documents

  • Legal Title reportCopy of the legal title report.PDF · uploaded 25 Jul 2017View
  • Declaration Form Bform b affidavit.PDF · uploaded 31 Jul 2017View

Technical documents

  • Building Plan ApprovalBP.pdfView
  • Layout Approvalscan892.pdfView

Other legal documents

  • OtherEXTENTION LETTER.pdfView
  • OtherENRICO DOD FINAL.pdfView

Financial documents

  • Other – Financesociety registration certificate.pdf · uploaded 10 Apr 2024View

Proforma allotment letter

  • Proforma allotment letterAllotment Letter format 1.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

3CS NO. 488KHASARA NO. 38/1

As published on MahaRERA's project page

3, CS NO. 488, KHASARA NO. 38/1

Boundaries

North
Hotel Radisson
South
36 M Road
East
12 M Road
West
Plot 1 And 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVirendra Khare—
Chartered accountantSv Ramana & Co—
EngineerKamath & Co—
OtherLaxmi Keshav Constructions—
OtherVka Infra Services Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology