Balkrishna Apartment

Completed

Nagpur (M Corp.), Nagpur 440013 |Promoter: Venkat Balkrishnarao Bhatgare

Residential / Group HousingRERAP50500010628
31 Aug 2017Registered with MahaRERA
28 Feb 2019Promised completion
28 Feb 2020Revised completionPushed back 1 year
1Building
1Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
Residancial1 unit in all
Land area for this project
1,115 sq m (11,999 sq ft)
Permissible built-up area
2,056 sq m (22,131 sq ft)
Sanctioned built-up area
2,056 sq m (22,131 sq ft)
Address
11PIN 440013
Designated bank account
Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.18372, 79.05023
Balkrishna Apartment is at latitude 21.18372, longitude 79.05023.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 6 years and 8 months ago.

Registered
31 Aug 2017
Promised
28 Feb 2019
Revised
28 Feb 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050001062831 Aug 201728 Feb 201928 Feb 2020Venkat Balkrishnarao BhatgareProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Balkrishna Apartment71

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

1 unit registered

Residancial · 1 unit
TypeCarpet areaUnits
Residancial2,056 sq m · 22,131 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space000012

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Balkrishna Apartment

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure7%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply----------100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water Drains-----------100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements------------80%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 19 filings listed on MahaRERA's project page

Form 1

Title report

Form B

Encumbrance details

Form 2

Allotment letter (2)

Registration certificate

Show all 34 documentsShow fewer documents

Form 5

Form 4

Extension certificate

Other (2)

Layout plan

Building plan

Document library

  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architech certificate.pdf · uploaded 12 Aug 2017View
  • Declaration in FORM Bowner decleration 003.pdf · uploaded 15 Aug 2017View
  • Copy of the legal title reportsale deed002-min.pdf · uploaded 15 Aug 2017View
  • Copy of Layout Approval (in case of layout)layout map and rl001-min.pdf · uploaded 15 Aug 2017View
  • Proforma of Allotment letterProforma of the allotment letter and agreement for sale .pdf · uploaded 15 Aug 2017View
  • Building Plan Approval (IOD)Building Plan Approval (1).pdf · uploaded 15 Aug 2017View
  • Details of encumbrancesBank Letter regarding mortgage001.pdf · uploaded 16 Aug 2017View
  • Proforma of Allotment letterAGREEMENT TO SALE- -Bhatgare Draft (Rera).pdf · uploaded 16 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)cretificate of engg.pdf · uploaded 16 Aug 2017View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 venkat bhatgare.pdf · uploaded 23 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 venkat bhatgare.pdf · uploaded 23 Dec 2019View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4 .pdf · uploaded 27 Dec 2019View
  • OtherCredia certificate.pdf · uploaded 1 Jan 2020View

Promoter documents

  • Declaration Form Bowner decleration 003.pdf · uploaded 15 Aug 2017View
  • Legal Title reportsale deed002-min.pdf · uploaded 15 Aug 2017View

Technical documents

  • Layout Approvallayout map and rl001-min.pdfView
  • Building Plan ApprovalBuilding Plan Approval (1).pdfView

Other legal documents

  • OtherCredia certificate.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of the allotment letter and agreement for sale .pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

11

As published on MahaRERA's project page

11

Boundaries

North
Plot No 12
South
Road
East
Plot No 3
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVikas Padole—
EngineerAaj Engineering—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology