Completed

Nagpur (M Corp.), Nagpur 440013 |Promoter: Impressa Laxmi

Residential / Group HousingRERAP50500013844
27 Oct 2017Registered with MahaRERA
30 Sep 2020Promised completion
1Building
78Units registered
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
Residential78 units in all
Land area for this project
3,001 sq m (32,298 sq ft)
Permissible built-up area
4,348 sq m (46,800 sq ft)
Sanctioned built-up area
4,348 sq m (46,800 sq ft)
Address
Plot No 2, Nagpur, NagpurPIN 440013
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.17540, 79.08176
Aasra is at latitude 21.17540, longitude 79.08176.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2020

The latest completion date on record passed 6 years and 1 month ago.

Registered
27 Oct 2017
Promised
30 Sep 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050001384427 Oct 201730 Sep 2020—Impressa LaxmiProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Aasra1978

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

78 units registered

Residential · 78 units
TypeCarpet areaUnits
Residential42.73 sq m · 460 sq ft13
Residential50.48 sq m · 543 sq ft13
Residential52.48 sq m · 565 sq ft13
Residential54.26 sq m · 584 sq ft13
Residential54.83 sq m · 590 sq ft13
Residential56.44 sq m · 608 sq ft13

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000033
Open Space0000201

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Aasra

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMLETED100%
  • Storm Water DrainsCOMPLETED100%
  • Landscaping & Tree PlantingCOMPLETED100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsCOMPLETED100%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCOMPLETED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 40 filings listed on MahaRERA's project page

Encumbrances

Title

Building plans

Form bs

Form 1s

Registration certificate

Others

Layout plan

Document library

  • Copy of Layout Approval (in case of layout)Subdivision Layout.pdf · uploaded 11 Sep 2017View
  • Proforma of Allotment letterLETTER OF ALLOTMENT.pdf · uploaded 11 Sep 2017Source
  • Details of encumbrancesDECLARATION 2.pdf · uploaded 12 Sep 2017View
  • OtherDECLARATION.pdf · uploaded 12 Sep 2017Source
  • Proforma of Allotment letterCHITNAVIS-IMPRESSA LAXMI-AGREEMENT _AASRA_-RERA.pdf · uploaded 16 Sep 2017Source
  • Copy of the legal title reportTitle Report.pdf · uploaded 22 Sep 2017View
  • Declaration in FORM BForm B.pdf · uploaded 22 Sep 2017View
  • Building Plan Approval (IOD)commencement certificate.pdf · uploaded 22 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentdownload (5).pdf · uploaded 24 Mar 2018View
  • Declaration in FORM BForm B.pdf · uploaded 30 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch certificate.pdf · uploaded 30 Mar 2018View
  • OtherDeclaration.pdf · uploaded 30 Mar 2018Source
  • Details of encumbrancesCredit sanction advice.pdf · uploaded 2 Aug 2018View
  • Declaration in FORM B01 form b.pdf · uploaded 2 Aug 2018View
  • Other02 self declaration.pdf · uploaded 2 Aug 2018Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)05 Engineer Certificate.pdf · uploaded 2 Aug 2018Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)04 Architect Certificate.pdf · uploaded 2 Aug 2018View
  • Certificates of CA (Form 5)AASRA.pdf · uploaded 29 Sep 2018Source
  • Form 2AFORM 2 A_compressed.pdf · uploaded 24 Apr 2019Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Certificate.pdf · uploaded 24 Apr 2019View
  • Building Plan Approval (IOD)PERMIT 2019.pdf · uploaded 19 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentPERMIT 2019.pdf · uploaded 19 Nov 2019View
  • OtherDECLARATION.pdf · uploaded 20 Nov 2019Source
  • Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 6 Nov 2020Source
  • Otheroc application receipt.pdf · uploaded 6 Nov 2020Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY CERTIFICATE.pdf · uploaded 16 Nov 2020Source
  • Status of Formation of Legal Entity (Society/Co Op etc.)ASSOCIATION PAN AASRA.pdf · uploaded 21 Jun 2021Source

Promoter documents

  • Legal Title reportTitle Report.pdf · uploaded 22 Sep 2017View
  • Declaration Form BForm B.pdf · uploaded 22 Sep 2017View
  • Declaration Form BForm B.pdf · uploaded 30 Mar 2018View
  • Declaration Form B01 form b.pdf · uploaded 2 Aug 2018View

Technical documents

  • Layout ApprovalSubdivision Layout.pdfView
  • Building Plan Approvalcommencement certificate.pdfView
  • Building Plan ApprovalPERMIT 2019.pdfView

Other legal documents

Proforma allotment letter

  • Proforma allotment letterLETTER OF ALLOTMENT.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

2PLOT NO 2

As published on MahaRERA's project page

PLOT NO 2

Boundaries

North
Remaining Portion Of Plot No 2
South
Remaining Portion Of Plot No 2
East
Plot No 3 And 4
West
Swami Samarth Apartments

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRajesh Jaiswal—
ArchitectRajesh Jaiswal—
ArchitectRajesh Jaiswal—
ArchitectRajesh Jaiswal—
EngineerKamath & Company—
EngineerKamath & Company—
EngineerKamath & Company—
EngineerKamath & Company—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology