BLD_009281Completed4 floors
Duplex Home 8 DH 13 and DH 14 · Bloomdale Duplex 08 13 to 14
Khapari · RERA P50500017236
4Sanctioned habitable floorsregistration certificate
27 Feb 2022Revised completionpromised 28 Feb 2020
Floors
4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P50500017236 · registered 24 Jul 2018
- Promised completion
- 28 Feb 2020
- Revised completion
- 27 Feb 2022
- Sanctioned habitable floors
- 4
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4 BHK | 148.9 m² (1,603 sq.ft) | 1 | not published |
| 4 BHK | 155.5 m² (1,674 sq.ft) | 2 | not published |
| 4 BHK | 158.3 m² (1,704 sq.ft) | 2 | not published |
| 4 BHK | 162.9 m² (1,753 sq.ft) | 2 | not published |
| 4 BHK | 163.6 m² (1,761 sq.ft) | 1 | not published |
| Total | 8 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 12 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor0%
- Slabs of Super Structure65%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
- Sanitary Fittings within the flats / premises10%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%