BLD_009281Completed4 floors

Duplex Home 8 DH 13 and DH 14 · Bloomdale Duplex 08 13 to 14

Khapari · RERA P50500017236

4Sanctioned habitable floorsregistration certificate
27 Feb 2022Revised completionpromised 28 Feb 2020

Floors

4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500017236 · registered 24 Jul 2018
Promised completion
28 Feb 2020
Revised completion
27 Feb 2022
Sanctioned habitable floors
4

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
4 BHK148.9 m² (1,603 sq.ft)1not published
4 BHK155.5 m² (1,674 sq.ft)2not published
4 BHK158.3 m² (1,704 sq.ft)2not published
4 BHK162.9 m² (1,753 sq.ft)2not published
4 BHK163.6 m² (1,761 sq.ft)1not published
Total8

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0000
Open Space00012

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure65%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology