Wing B · Uttara Heights

Hingna · RERA P50500053245

IDBLD_0510587 floorsExtended 4 mo
7Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500053245 · registered 23 Oct 2023
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
7
ProjectId
39,502
ProjectName
Uttara Heights
TotalUnitCount
26
ProjectBuildingId
1,68,855
BuildingNameNumber
Wing B
FsiWithSanctionSqmts
8
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
26
ProjectRegistartionNo
P50500053245
ProjectBuildingWingsId
1,72,312
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Wing B
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
7
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——26not published
Total26
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology