Satyam Lotus

Completed

Godhani (Railway), Nagpur 441203 |Promoter: Omsatyam Buildcons Private Limited

Residential / Group HousingRERAP50500018515
12 Nov 2018Registered with MahaRERA
30 Oct 2022Promised completion
1Building
70Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1 BHK, 2BHK70 units in all
Land area for this project
2,272 sq m (24,456 sq ft)
Permissible built-up area
3,811 sq m (41,018 sq ft)
Sanctioned built-up area
3,811 sq m (41,018 sq ft)
Address
4/67/2/B/4, Godhani Main Road, GodhaniPIN 441203
Designated bank account
Union Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.15308, 79.07374
Satyam Lotus is at latitude 21.15308, longitude 79.07374.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Oct 2022

The latest completion date on record passed 4 years ago.

Registered
12 Nov 2018
Promised
30 Oct 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050001851512 Nov 201830 Oct 2022—Omsatyam Buildcons Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Satyam Lotus970

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

70 units registered

1 BHK · 14 units2BHK · 56 units
TypeCarpet areaUnits
1 BHK39.05 sq m · 420 sq ft14
2BHK52.55 sq m · 566 sq ft56

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Satyam Lotus

  • Excavation100%
  • Basement (if any)1%
  • Podiums (if any)0%
  • Plinth1%
  • Stilt Floor1%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER LAYOUT SANCTION100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER LAYOUT SANCTION100%
  • Storm Water DrainsAS PER LAYOUT SANCTION100%
  • Landscaping & Tree Planting050%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAS PER LAYOUT SANCTION25%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER LAYOUT SANCTION25%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements00%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking00%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

2 documents held by Deedo, 24 filings listed on MahaRERA's project page

Registration certificate

Other

Document library

  • Commencement Certificates / NA Order for plotted developmentBuilding Permit 1.pdf · uploaded 31 Oct 2018Source
  • Commencement Certificates / NA Order for plotted developmentBuilding Permit 2.pdf · uploaded 31 Oct 2018Source
  • Commencement Certificates / NA Order for plotted developmentBuilding Permit 3.pdf · uploaded 31 Oct 2018Source
  • Details of encumbrancesSearch report Satyam Lotus-min.pdf · uploaded 3 Nov 2018Source
  • Declaration in FORM BAffidavit 1.pdf · uploaded 3 Nov 2018Source
  • Declaration in FORM BAffidavit 2.pdf · uploaded 3 Nov 2018Source
  • Copy of the legal title reportSearch report Satyam Lotus-min.pdf · uploaded 3 Nov 2018Source
  • Building Plan Approval (IOD)MAP 1.PDF · uploaded 3 Nov 2018Source
  • Building Plan Approval (IOD)MAP 2.PDF · uploaded 3 Nov 2018Source
  • Building Plan Approval (IOD)MAP-3.PDF · uploaded 3 Nov 2018Source
  • Proforma of Allotment letterAGREEMENT TO SELL-LOTUS-STANDARD DRAFT (1).pdf · uploaded 3 Nov 2018Source
  • Copy of Layout Approval (in case of layout)MAP 1.PDF · uploaded 3 Nov 2018Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Engineer Certificate Lotus.pdf · uploaded 30 Sep 2019Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Lotus.pdf · uploaded 30 Sep 2019Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERT lOTUS.pdf · uploaded 30 Sep 2019Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate Lotus.pdf · uploaded 20 May 2023Source

Promoter documents

  • Declaration Form BAffidavit 1.pdf · uploaded 3 Nov 2018Source
  • Declaration Form BAffidavit 2.pdf · uploaded 3 Nov 2018Source
  • Legal Title reportSearch report Satyam Lotus-min.pdf · uploaded 3 Nov 2018Source

Technical documents

  • Building Plan ApprovalMAP 1.PDFSource
  • Building Plan ApprovalMAP 2.PDFSource
  • Building Plan ApprovalMAP-3.PDFSource
  • Layout ApprovalMAP 1.PDFSource

Proforma allotment letter

  • Proforma allotment letterAGREEMENT TO SELL-LOTUS-STANDARD DRAFT (1).pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Godhani (Railway), Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

4/67/2/B/4

As published on MahaRERA's project page

4/67/2/B/4

Boundaries

North
Plot 03
South
Road 12 Mtr
East
Survey No 67-2-A
West
12 Mt Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLokesh Kadu—

Source: MahaRERA project page. Contact details are not shown.