Skip to content

Row houses · Construction of 24 flats and 9 row houses at mauza Digdoh, Nagpur

Digdoh (Devi) · RERA P50500028482

2Sanctioned habitable floorsregistration certificate
31 Dec 2023Revised completionpromised 30 Sep 2022
0 of 9Units bookedMahaRERA project page

Floors

2 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500028482 · registered 8 Mar 2021
Promised completion
30 Sep 2022
Revised completion
31 Dec 2023
Sanctioned habitable floors
2
ProjectId
22,878
ProjectName
Construction of 24 flats and 9 row houses at mauza Digdoh, Nagpur
TotalUnitCount
0
ProjectBuildingId
71,517
BuildingNameNumber
Row houses
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P50500028482
ProjectBuildingWingsId
71,517
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Row houses
NoOfBuildingWingFloorProposed
2
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
2

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK68.2 m² (734 sq.ft)90
Total90
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology