Babji Enclave

Completed

Beltarodi, Nagpur 440034 |Promoter: Fakhri Infraventures

Residential / Group HousingRERAP50500001888
29 Jul 2017Registered with MahaRERA
30 Dec 2021Promised completion
1Building
34Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK, Falt, Flat, Shop34 units in all
Land area for this project
1,500 sq m (16,146 sq ft)
Permissible built-up area
2,700 sq m (29,063 sq ft)
Sanctioned built-up area
1,945 sq m (20,936 sq ft)
Address
KH NO 10, 11 PLOT NO. R-2, Beltarodi road, Near Beltarodi Bus stopPIN 440034
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.07521, 79.07722
Babji Enclave is at latitude 21.07521, longitude 79.07722.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2021

The latest completion date on record passed 4 years and 10 months ago.

Registered
29 Jul 2017
Promised
30 Dec 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050000188829 Jul 201730 Dec 2021—Fakhri InfraventuresProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Babji Enclave834

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

34 units registered

2BHK · 5 unitsFalt · 1 unitFlat · 24 unitsShop · 4 units
TypeCarpet areaUnits
2BHK46.45 sq m · 500 sq ft1
2BHK47.46 sq m · 511 sq ft2
2BHK47.86 sq m · 515 sq ft2
Falt43.59 sq m · 469 sq ft1
Flat45.61 sq m · 491 sq ft4
Flat48.45 sq m · 522 sq ft4
Flat49.67 sq m · 535 sq ft3
Flat52.53 sq m · 565 sq ft1
Flat54.84 sq m · 590 sq ft6
Flat58.83 sq m · 633 sq ft3
Flat65.05 sq m · 700 sq ft3
Shop24.98 sq m · 269 sq ft1
Shop26.28 sq m · 283 sq ft1
Shop28.48 sq m · 307 sq ft1
Shop35.85 sq m · 386 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Babji Enclave

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOAR-WELL DONE/MJPD NAGPUR100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)CHAMBER100%
  • Storm Water DrainsCHAMBER100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalDUSTBIN100%
  • Water conservation /Rain water harvestingAS PER NORMS100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFIRE EQUIPMENT0%
  • Electrical meter room, sub-station, receiving stationPANEL BOARD100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

18 documents held by Deedo, 23 filings listed on MahaRERA's project page

Form 1

Form 2

Title

Form b

Allotment letters

Form 5s

Completion

Form 4s

Others

Registration certificate

Layout plan

Building plan

Document library

  • Copy of the legal title reportTitle Report.pdf · uploaded 26 Jul 2017View
  • Details of encumbrancesTitle Report.pdf · uploaded 26 Jul 2017View
  • Copy of Layout Approval (in case of layout)Building Permit.pdf · uploaded 26 Jul 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 26 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentBuilding Permit.pdf · uploaded 26 Jul 2017View
  • Building Plan Approval (IOD)Sanctioned Plan.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's Certificate.pdf · uploaded 26 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM BForm B.pdf · uploaded 28 Jul 2017View
  • Proforma of Allotment letterAGREEMENT-AS PER RERA-BABJI ENCLAVE.pdf · uploaded 28 Jul 2017View
  • Certificates of CA (Form 5)Form 5 2017-18.pdf · uploaded 28 Sep 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 18-19.pdf · uploaded 29 Nov 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY CERTIFICATE.pdf · uploaded 17 Dec 2019View
  • Architect’s Certificate on Completion of Project (Form 4)COMPLETION CERTIFICATE.pdf · uploaded 17 Dec 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation.pdf · uploaded 13 Feb 2020View
  • Architect’s Certificate on Completion of Project (Form 4)ARCHITECT_CERTIFICATE.pdf · uploaded 31 Aug 2020View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Babji Society.pdf · uploaded 24 Jun 2021View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Babji Enclave Society.pdf · uploaded 25 Jun 2021View

Promoter documents

  • Legal Title reportTitle Report.pdf · uploaded 26 Jul 2017View
  • Declaration Form BForm B.pdf · uploaded 28 Jul 2017View

Technical documents

  • Layout ApprovalBuilding Permit.pdfView
  • Building Plan ApprovalSanctioned Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Beltarodi, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

11 PLOT NO.R2KH NO 10

As published on MahaRERA's project page

KH NO 10, 11 PLOT NO. R-2

Boundaries

North
Plot No R-1
South
Plot No R-4
East
Road
West
Plot No R-3

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAlok Lunia—
EngineerR & G Associates—
OtherDevendra Gautam—

Source: MahaRERA project page. Contact details are not shown.