Gangotri Ram Nagar

Certificate Signed

Belgaon, Nagpur 441203 |Promoter: Gangotri Real Estate

23 Jul 2024Registered with MahaRERA
28 Feb 2026Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
Sur No 35/3 Part P.H.No. 45, Umred Road, Mouza: BelgaonPIN 441203
Designated bank account
196
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.23879, 76.79712
Gangotri Ram Nagar is at latitude 20.23879, longitude 76.79712.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 28 Feb 2026

The latest completion date on record passed 8 months ago.

Registered
23 Jul 2024
Promised
28 Feb 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050007708823 Jul 202428 Feb 202628 Feb 2026Gangotri Real EstateProject page

Documents

1 document held by Deedo, 76 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Declaration Form BForm B.pdf · uploaded 20 Mar 2024Source
  • Legal Title reportTitle Report.pdf · uploaded 24 Jun 2024Source

Migrated

  • 1 PAN CardGangotri Pan Card.pdf · uploaded 19 Mar 2024Source
  • 1 a Details of encumbrances concerned to FinanceFinance.pdf · uploaded 19 Mar 2024Source
  • 2 a Details of encumbrances concerned to FinanceLegal.pdf · uploaded 19 Mar 2024Source
  • 1 b Details of encumbrances concerned to LegalFinance.pdf · uploaded 19 Mar 2024Source
  • 2 b Details of encumbrances concerned to LegalLegal.pdf · uploaded 19 Mar 2024Source
Show all 77 documentsShow fewer documents

Migrated

  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexture A.pdf · uploaded 19 Mar 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 19 Mar 2024Source
  • 1 Proforma of Allotment letterAL.pdf · uploaded 19 Mar 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of SBA.pdf · uploaded 19 Mar 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation of AL.pdf · uploaded 19 Mar 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation of AFS.pdf · uploaded 19 Mar 2024Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 20 Mar 2024Source
  • 1 Copy of Layout Approval (in case of layout)Sansion Map.pdf · uploaded 1 Apr 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSansion Map.pdf · uploaded 1 Apr 2024Source
  • 1 CERSAI detailsCersai Serch Concern.pdf · uploaded 2 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Jun 2024Source
  • 1 Other – TechnicalOrder No 50 Annexure A.pdf · uploaded 14 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevise NA Order.pdf · uploaded 18 Jun 2024Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 24 Jun 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCovering Letter 1.pdf · uploaded 1 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Jul 2024Source
  • 2 Other – TechnicalCovering Letter 1.pdf · uploaded 1 Jul 2024Source
  • 3 Other – TechnicalNew Revise Plan 1.pdf · uploaded 1 Jul 2024Source
  • 4 Other – TechnicalRevise NA Order.pdf · uploaded 1 Jul 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 2 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryQ-July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryQ-Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryQ-Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • Form 1Form 1 July to Sep 2024.pdf · uploaded 24 May 2025Source
  • Form 2Form 2 July to Sep 2024.pdf · uploaded 24 May 2025Source
  • Form 3Form 3 July to Sep 2024.pdf · uploaded 24 May 2025Source
  • Disclosure of Sold and Booked InventoryQ-July to Sep 2024.pdf · uploaded 24 May 2025Source
  • Form 1Form 1 Oct to Dec 2024.pdf · uploaded 24 May 2025Source
  • Form 2Form 2 Oct to Dec 2024.pdf · uploaded 24 May 2025Source
  • Form 3Form 3 Oct to Dec 2024.pdf · uploaded 24 May 2025Source
  • Disclosure of Sold and Booked InventoryQ-Oct to Dec 2024.pdf · uploaded 24 May 2025Source
  • Form 1Form 1 Jan to Mar 2025.pdf · uploaded 24 May 2025Source
  • Form 2Form 2 Jan to Mar 2025.pdf · uploaded 24 May 2025Source
  • Form 3Form 3 Jan to Mar 2025.pdf · uploaded 24 May 2025Source
  • Disclosure of Sold and Booked InventoryQ-Jan to Mar 2025.pdf · uploaded 24 May 2025Source
  • Form 5 (FY 2024-2025)Form 5 2024-25.pdf · uploaded 4 Aug 2025Source
  • Form 2A (FY 2024-2025)Form 2A 2024-25.pdf · uploaded 18 Aug 2025Source
  • Withdrawal Update Form 1Form 1 Apr to Jun 2025.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 1Form 1 July to Sep 2025.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Apr to Jun 2025.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 2Form 2 July to Sep 2025.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 3Form 3 Apr to Jun 2025.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 3Form 3 July to Sep 2025.pdf · uploaded 12 Dec 2025Source
  • Completion CertificateCompletion Certificate.pdf · uploaded 13 Jan 2026Source
  • Completion CertificateEmail Verification Date 06-01-2026.pdf · uploaded 13 Jan 2026Source

Technical

  • DocumentSansion Map.pdf · uploaded 1 Apr 2024Source
  • DocumentSansion Map.pdf · uploaded 1 Apr 2024Source
  • Other – TechnicalOrder No 50 Annexure A.pdf · uploaded 14 Jun 2024Source
  • Other – TechnicalCovering Letter 1.pdf · uploaded 1 Jul 2024Source
  • Other – TechnicalNew Revise Plan 1.pdf · uploaded 1 Jul 2024Source
  • Other – TechnicalRevise NA Order.pdf · uploaded 1 Jul 2024Source

Technical (Architect)

  • DocumentForm 1 July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 1 Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 1 Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • DocumentForm 1 July to Sep 2025.pdf · uploaded 12 Dec 2025Source

Technical (Engineer)

  • DocumentForm 2 July to Sep 2024.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 2 Oct to Dec 2024.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 2 Jan to Mar 2025.pdf · uploaded 21 Apr 2025Source
  • DocumentForm 2 July to Sep 2025.pdf · uploaded 12 Dec 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Belgaon, Umred taluka

Survey, CTS, gat or plot numbers

Sur No 35/3 Part P.H.No. 45

Boundaries

North
Sur No 11 and 13 and road
South
Remining Space of Sur No 35-1
East
Sur No 33
West
Sur No 36-1 and 47-1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectTushar Wandile—
Chartered accountantRavindra Lashkare—
Chartered accountantRishi Lashkare—
Chartered accountantVikas Atkar—
EngineerTushar Wandile—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology