7 Feb 2023Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
59Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Handed over to MCGM, Hnaded over to MCGM, Shop59 units in all
Address
572, Borivali Tps No. III Of Village Shimpoli, Borivali WestPIN 400092
Designated bank account
17
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 Feb 2023
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000493667 Feb 202331 Dec 202730 Apr 2028Ans Lifestyle Realtors LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
The Capital1059

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 59 units booked (0%), as the promoter reported to MahaRERA

1BHK · 37 units2BHK · 9 unitsHanded over to MCGM · 10 unitsHnaded over to MCGM · 2 unitsShop · 1 unit
TypeCarpet areaUnitsBooked
1BHK30.7 sq m · 330 sq ft80
1BHK30.71 sq m · 331 sq ft10
1BHK34.9 sq m · 376 sq ft90
1BHK40.42 sq m · 435 sq ft20
1BHK43.24 sq m · 465 sq ft80
1BHK46.26 sq m · 498 sq ft90
2BHK57.05 sq m · 614 sq ft10
2BHK69.14 sq m · 744 sq ft80
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Handed over to MCGM27.93 sq m · 301 sq ft20
Handed over to MCGM28.01 sq m · 301 sq ft20
Handed over to MCGM28.1 sq m · 302 sq ft20
Handed over to MCGM28.78 sq m · 310 sq ft20
Handed over to MCGM28.99 sq m · 312 sq ft20
Hnaded over to MCGM27.99 sq m · 301 sq ft20
Shop357.19 sq m · 3,845 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 66 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 26 Dec 2022Source

Legal

  • Legal Title reportlegal title report ANS_compressed.pdf · uploaded 26 Dec 2022Source
  • Declaration Form BFORM B.pdf · uploaded 26 Dec 2022Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 26 Dec 2022Source
  • 1 Copy of the legal title reportlegal title report ANS_compressed.pdf · uploaded 26 Dec 2022Source
  • 1 Copy of Layout Approval (in case of layout)plan_1-1.pdf · uploaded 26 Dec 2022Source
Show all 68 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 26 Dec 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentplan_2-2.pdf · uploaded 26 Dec 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentplan_3-end.pdf · uploaded 26 Dec 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentFIRST CC.pdf · uploaded 26 Dec 2022Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 26 Dec 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE .pdf · uploaded 26 Dec 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE.pdf · uploaded 26 Dec 2022Source
  • 1 Proforma of Allotment letterALLOTMENT DRAFT.pdf · uploaded 26 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation for allotment.pdf · uploaded 26 Dec 2022Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation of agreement.pdf · uploaded 26 Dec 2022Source
  • 1 CERSAI detailsEVERGRAND ETHOS.pdf · uploaded 28 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameseprate bank account.pdf · uploaded 29 Dec 2022Source
  • 1 a Details of encumbrances concerned to Financelegal fiNance.pdf · uploaded 30 Dec 2022Source
  • 1 b Details of encumbrances concerned to Legallegal fiNance.pdf · uploaded 30 Dec 2022Source
  • 1 Declaration about Commencement Certificatedeclaration to CC.pdf · uploaded 30 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest.pdf · uploaded 6 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 17 Jan 2023Source
  • 1 Proforma of Agreement for saleFINAL AGREEMENT FOR SALE.pdf · uploaded 2 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Anant Darshan.pdf · uploaded 2 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)K C shah.pdf · uploaded 2 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA ANS.pdf · uploaded 2 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTURE.pdf · uploaded 6 Sep 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER.pdf · uploaded 6 Sep 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA ETHOS.pdf · uploaded 6 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 2022-23.pdf · uploaded 12 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)EVERGRAND ETHOS FORM 2A.pdf · uploaded 2 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)EVERGRAND ETHOS - FORM 5.pdf · uploaded 2 Dec 2024Source
  • 2 Disclosure of sold/ booked inventoryRERA DISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf · uploaded 20 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 4 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 4 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Inventory.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 11 Feb 2025Source
  • Withdrawal Update Form 1Withdrawal Application Form1 (1).pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 220251216_Withdrawal Application Form2-1.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 3Signed Withdrawal Application Form3 for June 25 (1).pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 1Architect Certf July to Sept 05 01 2026.pdf · uploaded 10 Jan 2026Source
  • Withdrawal Update Form 2Form 2 (2).pdf · uploaded 10 Jan 2026Source
  • Withdrawal Update Form 3Form 3 July to September 2025.pdf · uploaded 10 Jan 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 12 Jun 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 12 Jun 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 12 Jun 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 6 Aug 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 6 Aug 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 6 Aug 2026Source

Technical

  • Documentplan_1-1.pdf · uploaded 26 Dec 2022Source
  • DocumentIOD.pdf · uploaded 26 Dec 2022Source
  • Documentplan_2-2.pdf · uploaded 26 Dec 2022Source
  • Documentplan_3-end.pdf · uploaded 26 Dec 2022Source
  • Document10011 Amended Drawing.pdf · uploaded 13 Jun 2026Source
  • DocumentDrawing highlighted.pdf · uploaded 14 Aug 2026Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 4 Feb 2025Source
  • Documentform 1.pdf · uploaded 6 Aug 2026Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 4 Feb 2025Source
  • Documentform 2.pdf · uploaded 6 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shimpoli, Borivali taluka

Survey, CTS, gat or plot numbers

572

Boundaries

North
Kora Kendra Road
South
F P No 571 Tps No Borivali III
East
Shimpoli Chickuwadi Road
West
F P No 565 569 570 Tps No Borivali III

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnant Darshan—
ArchitectAnkit Shah—
Chartered accountantApkg & Co—
Chartered accountantVirag—
EngineerK C Shah Consultants—
EngineerMohan G Manekar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology