Siennaa
Completion due Dec 2027Poisar, Mumbai Suburban 400101 |Promoter: S D Corporation Private Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 6
- Phases
- 6
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 3 months
P51800019624The latest completion date on record passed 2 years and 7 months ago.
- Registered
- 14 Feb 2019
- Promised
- 30 Dec 2023
- Revised
- 31 Mar 2024
Completion promised for 30 Dec 2027
P51800019677- Registered
- 20 Feb 2019
- Promised
- 30 Dec 2027
Completion promised for 30 Jun 2027
P51800019643- Registered
- 20 Feb 2019
- Promised
- 30 Jun 2027
Completion pushed back 3 months
P51800019658The latest completion date on record passed 2 years and 7 months ago.
- Registered
- 20 Feb 2019
- Promised
- 30 Dec 2023
- Revised
- 31 Mar 2024
Show 2 more registrations
Completion pushed back 3 months
P51800019659The latest completion date on record passed 2 years and 7 months ago.
- Registered
- 20 Feb 2019
- Promised
- 30 Dec 2023
- Revised
- 31 Mar 2024
Completion pushed back 3 years
P51800019693- Registered
- 22 Feb 2019
- Promised
- 30 Dec 2024
- Revised
- 30 Dec 2027
6 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800019624 | 14 Feb 2019 | 30 Dec 2023 | 31 Mar 2024 | S D Corporation Private Limited | Project page |
| P51800019677 | 20 Feb 2019 | 30 Dec 2027 | 30 Dec 2027 | S D Corporation Private Limited | Project page |
| P51800019643 | 20 Feb 2019 | 30 Jun 2027 | — | S D Corporation Private Limited | Project page |
| P51800019658 | 20 Feb 2019 | 30 Dec 2023 | 31 Mar 2024 | S D Corporation Private Limited | Project page |
| P51800019659 | 20 Feb 2019 | 30 Dec 2023 | 31 Mar 2024 | S D Corporation Private Limited | Project page |
| P51800019693 | 22 Feb 2019 | 30 Dec 2024 | 30 Dec 2027 | S D Corporation Private Limited | Project page |
Documents
12 documents held by Deedo
Registration certificates
- Registration certificateP51800019693 · 9 Sep 2021ViewSource
- Registration certificateP51800019624 · 9 Sep 2021ViewSource
- Registration certificateP51800019658 · 9 Sep 2021ViewSource
- Registration certificateP51800019659 · 9 Sep 2021ViewSource
- Registration certificateP51800019643 · 22 Sep 2026ViewSource
- Registration certificateP51800019677 · 7 Oct 2026ViewSource
Extension certificates
- Extension certificateP51800019659 · 28 Nov 2023ViewSource
- Extension certificateP51800019624 · 3 Jan 2024ViewSource
- Extension certificateP51800019658 · 3 Jan 2024ViewSource
- Extension certificateP51800019677 · 16 Oct 2025ViewSource
- Extension certificateP51800019693 · 16 Oct 2025ViewSource
- Extension certificateP51800019643 · 18 Aug 2026ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order14 Oct 2025Matched by RERA number
Regulatory order: PROJECT NAME: SIENNAA WING F (Regulatory Case No. 409 OF 2025) dated 14 Sept, 2025.
- Regulatory order14 Oct 2025Matched by RERA number
Regulatory order: PROJECT NAME: SIENNAA WING E (Regulatory Case No. 410 OF 2025) dated 14 Sept, 2025.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Borivali
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.