Skip to content

99 Rajgir

Certificate Signed

Poisar, Mumbai Suburban 400067 |Promoter: Sg Abodes

25 Jan 2024Registered with MahaRERA
31 Dec 2028Promised completion
30 Apr 2029Revised completionPushed back 4 months
1Building
92Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—92 units in all
Address
12-B, Poisar, Kandivali WestPIN 400067
Designated bank account
88
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
25 Jan 2024
Promised
31 Dec 2028
Revised
30 Apr 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180005449325 Jan 202431 Dec 202830 Apr 2029Sg AbodesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
99 Rajgir492

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

92 units registered

— · 92 units
TypeCarpet areaUnits
——92

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 45 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCompany pan card.PDF · uploaded 22 Dec 2023Source

Legal

  • Declaration Form BForm B.pdf · uploaded 22 Dec 2023Source
  • Legal Title reportTitle report.pdf · uploaded 11 Jan 2024Source

Migrated

  • 1 PAN CardCompany pan card.PDF · uploaded 22 Dec 2023Source
  • 1 a Details of encumbrances concerned to FinanceNo encumbrance self-declaration.PDF · uploaded 22 Dec 2023Source
  • 1 b Details of encumbrances concerned to LegalNo encumbrance self-declaration.PDF · uploaded 22 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)zero fsi iod Drawing.pdf · uploaded 22 Dec 2023Source
Show all 46 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentzero_IOD_signed.pdf · uploaded 22 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted development2375302_FirstCC_signed (1).pdf · uploaded 22 Dec 2023Source
  • 1 Declaration about Commencement CertificateFormat -D.PDF · uploaded 22 Dec 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 22 Dec 2023Source
  • 1 CERSAI detailsCersai declaration.PDF · uploaded 22 Dec 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed CA Certificate-s g abodes (1).pdf · uploaded 22 Dec 2023Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER FINAL.pdf · uploaded 22 Dec 2023Source
  • 1 Proforma of Agreement for salemaharera agreement.pdf · uploaded 22 Dec 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.PDF · uploaded 22 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterNo Devication Report on Allotment.PDF · uploaded 22 Dec 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Devication Report on Agreement for Sale.PDF · uploaded 22 Dec 2023Source
  • 1 Copy of the legal title reportTitle report.pdf · uploaded 11 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A DOI.pdf · uploaded 11 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 (architect certificate) (1).pdf · uploaded 21 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed_CA Certificate-s g abodes_Dec 24.pdf · uploaded 21 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_9RAJGIR _.pdf · uploaded 21 Feb 2025Source
  • Form 5 (FY 2024-2025)99 RAJGIR FORM 5 24-25.pdf · uploaded 14 Nov 2025Source
  • Form 1FORM1 FINAL.pdf · uploaded 21 Nov 2025Source
  • Form 2form 2 FINAL.pdf · uploaded 21 Nov 2025Source
  • Form 3form 3.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked Inventoryinventory disclosure format.PDF · uploaded 21 Nov 2025Source
  • Withdrawal Update Form 1Form 1 june 25_compressed.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 2FORM 2 engineer_compressed.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 3Signed CA Certificate-s g abodes June 25 (1).pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 1form 1 final.pdf · uploaded 12 Jan 2026Source
  • Withdrawal Update Form 2form 2 final.pdf · uploaded 12 Jan 2026Source
  • Withdrawal Update Form 3Signed CA Certificate-s g abodes Sept 25.pdf · uploaded 12 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 (6).pdf · uploaded 11 Sep 2026Source
  • Withdrawal Update Form 1FORM 1 (7).pdf · uploaded 11 Sep 2026Source
  • Withdrawal Update Form 2FORM 2 (2).pdf · uploaded 11 Sep 2026Source
  • Withdrawal Update Form 2FORM 2 (3).pdf · uploaded 11 Sep 2026Source
  • Withdrawal Update Form 3Signed CA Certificate-s g abodes dec25.pdf · uploaded 11 Sep 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 11 Sep 2026Source
  • Form 5 (FY 2025-2026)Form 5- 25-26 SG abodes-signed.pdf · uploaded 30 Sep 2026Source

Technical

  • Documentzero_IOD_signed.pdf · uploaded 22 Dec 2023Source
  • Documentzero fsi iod Drawing.pdf · uploaded 22 Dec 2023Source

Technical (Architect)

  • DocumentFORM 1 (7).pdf · uploaded 11 Sep 2026Source

Technical (Engineer)

  • DocumentFORM 2 (3).pdf · uploaded 11 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Poisar, Borivali taluka

Survey, CTS, gat or plot numbers

12B

Boundaries

North
By Municipal Road
South
By Plot Bearing S No 95pt
East
By Plot Bearing S No 95 H No 1a
West
By Plot Bearing S No 94 H No 19

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHarish Gandhi Building Consultants LLP—
Chartered accountantCa Nehali & Co—
Chartered accountantjimit shah—
Chartered accountantsanjay makhija—
EngineerAbhijit V Phatarpekar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology