Skip to content

Sovrano

Certificate Signed

Oshiwara, Mumbai Suburban 400102 |Promoter: Lodha Developers Limited

15 Dec 2025Registered with MahaRERAFirst of 2 registrations
31 Mar 2031Promised completionLatest across registrations
30 Apr 2031Revised completion1 of 2 registrations pushed back, by up to 4 months
2Buildings2 phases
240Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
RERA registrations
2
Phases
2
Buildings
2
Unit types
—240 units in all
Address
Jogeshwari (W), JogeshwariPIN 400102
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.14070, 72.84903
Sovrano is at latitude 19.14070, longitude 72.84903.

Also registered as

Sovrano Tower-ASovrano Tower C

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2031

PR1180002501771
Registered
15 Dec 2025
Promised
31 Mar 2031

Completion pushed back 4 months

PR1180002501764
Registered
15 Dec 2025
Promised
31 Dec 2030
Revised
30 Apr 2031

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR118000250177115 Dec 202531 Mar 203131 Mar 2031Lodha Developers LimitedProject page
PR118000250176415 Dec 202531 Dec 203030 Apr 2031Lodha Developers LimitedProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Wing -3 (Tower -C)320120
Wing -5(Tower - A )320120

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

240 units registered

— · 240 units
RERABuildingTypeCarpet areaUnits
PR1180002501764Wing -3 (Tower -C)——120
PR1180002501771Wing -5(Tower - A )——120

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

3 documents held by Deedo, 67 filings listed on MahaRERA's project page

Extension certificate

  • Extension certificatePR1180002501771 · 4 Jun 2026ViewSource

Registration certificate (2)

  • Registration certificatePR1180002501764 · 19 Jun 2026ViewSource
  • Registration certificatePR1180002501771 · 24 Jun 2026ViewSource

Finance

  • PAN CardPR1180002501764 · LDL PAN.pdf · uploaded 4 Dec 2025Source
  • OthersPR1180002501764 · Finance Declaration.pdf · uploaded 4 Dec 2025Source
  • OthersPR1180002501771 · Viability.pdf · uploaded 4 Dec 2025Source
  • PAN CardPR1180002501771 · LDL PAN.pdf · uploaded 4 Dec 2025Source

Legal

  • Declaration Form BPR1180002501771 · Legal Title Report-Jogeshwari.pdf · uploaded 2 Dec 2025Source
Show all 70 documentsShow fewer documents

Legal

  • Declaration Form BPR1180002501771 · Form B -Sovrano Tower A.pdf · uploaded 2 Dec 2025Source
  • Declaration Form BPR1180002501771 · 1_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of Reg No19004-2025.pdf · uploaded 3 Dec 2025Source
  • Declaration Form BPR1180002501771 · 2_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of RegNo19004-2025.pdf · uploaded 3 Dec 2025Source
  • OthersPR1180002501764 · Interest Disclosure Lodha_removed.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BPR1180002501764 · Legal Title Report.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BPR1180002501764 · Form B -Sovrano Tower C.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BPR1180002501764 · 1_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of Reg No19004-2025.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BPR1180002501764 · 2_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of RegNo19004-2025.pdf · uploaded 4 Dec 2025Source
  • OthersPR1180002501771 · Interest Disclosure Lodha_removed.pdf · uploaded 4 Dec 2025Source

Migrated

  • Withdrawal Update Form 1PR1180002501764 · Form-1 Sovarno C Dec-25.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 2PR1180002501764 · Sovrano Tower C Form 2.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 3PR1180002501764 · Form 3 - Sovrano Tower C.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 1PR1180002501771 · Form-1 Sovarno A Dec-25.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 2PR1180002501771 · Sovrano Tower A Form 2.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 3PR1180002501771 · fORM-3 a-.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 1PR1180002501764 · Form1 - Sovrano Tower C - PR1180002501764-ok.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2PR1180002501764 · Sovrano C Form 2.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3PR1180002501764 · Form- 3 regg- Sovarno C-F.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1PR1180002501771 · Form1 -Sovrano Tower A - PR1180002501771- Mar-26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2PR1180002501771 · Sovrano A Form 2.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3PR1180002501771 · Form- 3 regg-_merged Sovarno A.pdf · uploaded 20 Apr 2026Source
  • Form 2A (FY 2025-2026)PR1180002501764 · Form 2A - Sovrano Tower C - PR1180002501764.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)PR1180002501771 · Form 2A - Sovrano Tower-A - PR1180002501771.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 1PR1180002501764 · Form1 - June 26.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2PR1180002501764 · Sovrano C Form 2 June 26.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3PR1180002501764 · Sovrano C Form-3 June 26.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 1PR1180002501771 · Form1 - June 26.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2PR1180002501771 · Form 2 June 26.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3PR1180002501771 · Form-3 June 26.pdf · uploaded 17 Jul 2026Source
  • Form 5 (FY 2025-2026)PR1180002501764 · Sovrano Tower C.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)PR1180002501771 · Sovrano Tower A.pdf · uploaded 29 Sep 2026Source

Planning Authority

  • DocumentPR1180002501764 · MCGM_2504229_IOD_signed.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501764 · MCGM_2505757_FirstCC_signed.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501764 · MCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501764 · MCGM_051701070215249599116.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501764 · MCGM_052103070215250547616.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501764 · MCGM_051803070215250547716.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_2504229_IOD_signed.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_2505757_FirstCC_signed.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_051701070215249599116.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_052103070215250547616.pdf · uploaded 10 Dec 2025Source
  • DocumentPR1180002501771 · MCGM_051803070215250547716.pdf · uploaded 10 Dec 2025Source

Technical

  • DocumentPR1180002501764 · 20251203 For RERA Submission Wing No3 - converted.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501764 · Building Plan Wing 3.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501764 · Order 50.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501764 · Sheet 2.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501771 · 20251203 For RERA Submission Wing No 5 - converted (2).pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501771 · Drawing_02.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501771 · Building Plan_1.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501771 · Building Plan_2.pdf · uploaded 4 Dec 2025Source
  • DocumentPR1180002501771 · Order 50 -Sovrano Tower-A.pdf · uploaded 4 Dec 2025Source
  • OthersPR1180002501764 · land area declartion-Final tower C F.pdf · uploaded 10 Dec 2025Source
  • OthersPR1180002501764 · land area declartion-Final tower C - Exact ok.pdf · uploaded 10 Dec 2025Source
  • OthersPR1180002501764 · Ack Wing 3.pdf · uploaded 10 Dec 2025Source
  • OthersPR1180002501771 · Tower A - Final (2).pdf · uploaded 10 Dec 2025Source
  • OthersPR1180002501771 · land area declartion-Final tower A - Excact- F.pdf · uploaded 10 Dec 2025Source
  • OthersPR1180002501771 · Acknowlgement.pdf · uploaded 10 Dec 2025Source

Technical (Architect)

  • DocumentPR1180002501764 · Form1 - June 26.pdf · uploaded 17 Jul 2026Source
  • DocumentPR1180002501771 · Form1 - June 26.pdf · uploaded 17 Jul 2026Source

Technical (Engineer)

  • DocumentPR1180002501764 · Sovrano C Form 2 June 26.pdf · uploaded 17 Jul 2026Source
  • DocumentPR1180002501771 · Form 2 June 26.pdf · uploaded 17 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Oshiwara, Andheri taluka

Survey, CTS, gat or plot numbers

510

Boundaries

North
CTS No 510(pt)
South
CTS No 1 (pt)
East
9.00 Mt Driveway
West
9.00 Mt Driveway

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPradeep M Kamble—PR1180002501764
ArchitectPradeep M Kamble—PR1180002501771
ArchitectVini Vilas Desai—PR1180002501764
ArchitectVini Vilas Desai—PR1180002501771
Chartered accountantChirag Bharat Sarvaiya—PR1180002501771
Chartered accountantChirag Bharat Sarvaiya—PR1180002501764
EngineerMehul Kaivant Shah—PR1180002501764
EngineerMehul Kaivant Shah—PR1180002501771
EngineerTushar hodbe—PR1180002501764
EngineerTushar Hodbe—PR1180002501771

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology