Skip to content
Deedo home
Menu

Sheetal Sky

Completion due Dec 2030

Oshiwara, Mumbai Suburban 400053 |Promoter: D.G.S. Land Developers (India) Pvt Ltd

24 Jun 2025Registered with MahaRERAFirst of 2 registrations
31 Dec 2030Promised completionLatest across registrations
1Building2 phases
143Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2
Buildings
1

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.14835, 72.84047
Sheetal Sky is at latitude 19.14835, longitude 72.84047.

Also registered as

Sheetal Sky Tower B
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2030

PM1180002500121
Registered
24 Jun 2025
Promised
31 Dec 2030

Completion promised for 31 Dec 2030

PM1180002500823
Registered
17 Sep 2025
Promised
31 Dec 2030

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM118000250012124 Jun 202531 Dec 2030—D.G.S. Land Developers (India) Pvt LtdProject page
PM118000250082317 Sep 202531 Dec 2030—D.G.S. Land Developers (India) Pvt LtdProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Sheetal Sky Tower B2627143

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificatePM1180002500121 · 24 Jun 2025ViewSource
  • Registration certificatePM1180002500823 · 17 Sep 2025ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Oshiwara

Survey, CTS, gat or plot numbers

1/1391/140

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology