Vishwa Bhuvan

Certificate Signed

Mumbai, Maharashtra 400071 |Promoter: Majestic Royale City Developers

Residential / Group HousingRERAP51800053266
23 Oct 2023Registered with MahaRERA
11 Nov 2026Promised completion
11 Mar 2027Revised completionPushed back 4 months
1Building
20Units registered14 booked (70%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Tenant 2Bhk, Tenant 3Bhk20 units in all
Address
1622, 1622 / 1 to 4, 7TH CROSS ROAD, CHEMBUR EASTPIN 400071
Designated bank account
85
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.05347, 72.89887
Vishwa Bhuvan is at latitude 19.05347, longitude 72.89887.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
23 Oct 2023
Promised
11 Nov 2026
Revised
11 Mar 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180005326623 Oct 202311 Nov 202611 Mar 2027Majestic Royale City DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vishwa Bhuvan1020

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 of 20 units booked (70%), as the promoter reported to MahaRERA

2BHK · 6 units3BHK · 2 unitsTenant 2Bhk · 10 unitsTenant 3Bhk · 2 units
TypeCarpet areaUnitsBooked
2BHK63.92 sq m · 688 sq ft10
2BHK64.95 sq m · 699 sq ft10
2BHK67.85 sq m · 730 sq ft30
2BHK74.32 sq m · 800 sq ft11
3BHK87.19 sq m · 939 sq ft21
Tenant 2Bhk61.64 sq m · 663 sq ft11
Tenant 2Bhk62.67 sq m · 675 sq ft11
Tenant 2Bhk67.85 sq m · 730 sq ft11
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Tenant 2Bhk72.27 sq m · 778 sq ft66
Tenant 2Bhk74.32 sq m · 800 sq ft11
Tenant 3Bhk87.19 sq m · 939 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 94 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardMRCD_PAN CARD.pdf · uploaded 22 Jul 2023Source

Legal

  • Declaration Form BForm B pdf.pdf · uploaded 8 Aug 2023Source
  • Legal Title reportLegal Title.pdf · uploaded 8 Sep 2023Source
  • Legal Title reportLegal Title.pdf · uploaded 8 Sep 2023Source

Migrated

  • 1 PAN CardMRCD_PAN CARD.pdf · uploaded 22 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION IN RERA Allotment ok.pdf · uploaded 25 Jul 2023Source
Show all 96 documentsShow fewer documents

Migrated

  • 1 Deviation Report with respect to model copy of AgreementDEVIATION IN RERA AGREEMENT ok.pdf · uploaded 25 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentVishwabhuvan Fist CC.pdf · uploaded 8 Aug 2023Source
  • 1 Declaration about Commencement CertificateCC Declaration certificate 2.pdf · uploaded 8 Aug 2023Source
  • 1 Declaration in FORM BForm B pdf.pdf · uploaded 8 Aug 2023Source
  • 1 Proforma of Allotment letterProforma Allotment Letter.pdf · uploaded 11 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)20230818 ISSUE DRAWING 1 FSI IOD (2).pdf · uploaded 18 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted development20230818 ISSUE DRAWING 1 FSI IOD (2).pdf · uploaded 18 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Financial.pdf · uploaded 25 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Financial.pdf · uploaded 25 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Details Letter ok.pdf · uploaded 25 Aug 2023Source
  • 1 Copy of the legal title reportLegal Title.pdf · uploaded 8 Sep 2023Source
  • 2 Copy of the legal title reportLegal Title.pdf · uploaded 8 Sep 2023Source
  • 1 CERSAI detailsCersai Certirficate.pdf · uploaded 8 Sep 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 08-09-2023.pdf · uploaded 8 Sep 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 08-09-2023.pdf · uploaded 8 Sep 2023Source
  • 1 Proforma of Agreement for saleRERA- Venkat Nagar 06-09-2023.pdf · uploaded 8 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrances Legal.pdf · uploaded 5 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrances Legal.pdf · uploaded 5 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate.pdf · uploaded 12 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24_.pdf · uploaded 17 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Full CC Drawing.pdf · uploaded 19 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentFull CC Vishwabhuvan.pdf · uploaded 19 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 21 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 21 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 21 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 21 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 21 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 21 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 9 Nov 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 9 Nov 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 9 Nov 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 9 Nov 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 9 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Nov 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 23 Nov 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 23 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 23 Nov 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 23 Nov 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 23 Nov 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 23 Nov 2024Source
  • 2 Copy of Layout Approval (in case of layout)Full CC.pdf · uploaded 30 Dec 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentFull CC Certificate.pdf · uploaded 30 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentFull CC.pdf · uploaded 30 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 December 2024_.pdf · uploaded 30 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 December 2024.pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 December 2024_.pdf · uploaded 30 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 March 2025.pdf · uploaded 16 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2025.pdf · uploaded 16 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2025.pdf · uploaded 16 Apr 2025Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 7 Aug 2026Source
  • Form 2A (FY 2025-2026)Form 2A 25-26.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 1Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 1Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 2Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 2Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 3Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 3Declaration.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 1Declaration Regarding Non-Filing of QPR and APR_.pdf · uploaded 12 Sep 2026Source
  • Withdrawal Update Form 2Declaration Regarding Non-Filing of QPR and APR_.pdf · uploaded 12 Sep 2026Source
  • Withdrawal Update Form 3Declaration Regarding Non-Filing of QPR and APR_.pdf · uploaded 12 Sep 2026Source

Technical

  • Document20230818 ISSUE DRAWING 1 FSI IOD (2).pdf · uploaded 18 Aug 2023Source
  • Document20230818 ISSUE DRAWING 1 FSI IOD (2).pdf · uploaded 18 Aug 2023Source
  • DocumentFull CC Drawing.pdf · uploaded 19 Oct 2024Source
  • DocumentFull CC.pdf · uploaded 30 Dec 2024Source
  • DocumentFull CC.pdf · uploaded 30 Dec 2024Source
  • DocumentFull OC Plan.pdf · uploaded 12 Sep 2026Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 21 Oct 2024Source
  • Documentform 1.pdf · uploaded 21 Oct 2024Source
  • Documentform 1.pdf · uploaded 9 Nov 2024Source
  • Documentform 1.pdf · uploaded 9 Nov 2024Source
  • Documentform 1.pdf · uploaded 9 Nov 2024Source
  • Documentform 1.pdf · uploaded 9 Nov 2024Source
  • Documentform 1.pdf · uploaded 9 Nov 2024Source
  • DocumentForm 1 December 2024_.pdf · uploaded 30 Jan 2025Source
  • DocumentForm 1 March 2025.pdf · uploaded 16 Apr 2025Source
  • DocumentDeclaration Regarding Non-Filing of QPR and APR_.pdf · uploaded 12 Sep 2026Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 21 Oct 2024Source
  • Documentform 2.pdf · uploaded 21 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 23 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 23 Nov 2024Source
  • Documentform 2.pdf · uploaded 23 Nov 2024Source
  • Documentform 2.pdf · uploaded 23 Nov 2024Source
  • DocumentForm 2 December 2024_.pdf · uploaded 30 Jan 2025Source
  • DocumentForm 2 March 2025.pdf · uploaded 16 Apr 2025Source
  • DocumentDeclaration Regarding Non-Filing of QPR and APR_.pdf · uploaded 12 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Greater Mumbai (M Corp.) (Part) (802794), Mumbai taluka

Survey, CTS, gat or plot numbers

16221622 / 1 to 4

Boundaries

North
7th Cross Road
South
Majica Chsl
East
Vasudha Chsl
West
Sangeeta Chsl

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAditi Dilip Yadav—
Chartered accountantRavi Kumar Mehata—
EngineerVikas Vinayak Gokhale—
EngineerVinayak Chopdekar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology