Skip to content

Bimal Apartments Chsl · Bimal Apartment Chsl

Mulund · RERA P51800046666

IDBLD_07853019 floorsExtended 4 mo
19Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
34 of 49Units bookedMahaRERA project page

Floors

19 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51800046666 · registered 26 Aug 2022
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
19
ProjectId
39,211
ProjectName
BIMAL APARTMENT CHSL
TotalUnitCount
49
ProjectBuildingId
1,55,017
BuildingNameNumber
BIMAL APARTMENTS CHSL
FsiWithSanctionSqmts
22
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
48
ProjectRegistartionNo
P51800046666
ProjectBuildingWingsId
1,58,442
BuildingWingsNameNumber
NA
NonResidentialUnitCount
1
AdvertisedBuildingNameNumber
BIMAL APARTMENTS CHSL
NoOfBuildingWingFloorProposed
22
NoOfBuildingWingFloorHabitable
19
NoOfBuildingWingFloorSanctioned
22

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK66.3 m² (714 sq.ft)11
2BHK66.6 m² (717 sq.ft)11
2BHK66.7 m² (718 sq.ft)1613
2BHK66.8 m² (719 sq.ft)2416
2BHK77.5 m² (834 sq.ft)11
3BHK97.2 m² (1,046 sq.ft)51
Shop59.3 m² (638 sq.ft)11
Total4934
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology