S3 · Godrej Prime
Kurla · RERA P51800000519
IDBLD_06519018 floorsPromised date passed
18Sanctioned habitable floorsregistration certificate
30 May 2023Revised completionpromised 30 May 2023
59 of 59Units bookedMahaRERA project page
Floors
18 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51800000519 · registered 18 Jul 2017
- Promised completion
- 30 May 2023
- Revised completion
- 30 May 2023
- Sanctioned habitable floors
- 18
- ProjectId
- 3,640
- ProjectName
- Godrej Prime
- TotalUnitCount
- 0
- ProjectBuildingId
- 675
- BuildingNameNumber
- S3
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P51800000519
- ProjectBuildingWingsId
- 675
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- S3
- NoOfBuildingWingFloorProposed
- 18
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 18
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 51.4 m² (553 sq.ft) | 1 | 1 |
| 2 BHK | 65.5 m² (705 sq.ft) | 14 | 14 |
| 2 BHK | 65.5 m² (705 sq.ft) | 14 | 14 |
| 2 BHK | 68.9 m² (742 sq.ft) | 30 | 30 |
| Total | 59 | 59 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology