Skip to content

Tower B · Aveza

Kurla · RERA P51900007527

IDBLD_08920041 floorsExtended 12 mo
41Sanctioned habitable floorsregistration certificate
29 Dec 2024Revised completionpromised 30 Dec 2023
0 of 129Units bookedMahaRERA project page

Floors

41 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51900007527 · registered 17 Aug 2017
Promised completion
30 Dec 2023
Revised completion
29 Dec 2024
Sanctioned habitable floors
41
ProjectId
10,786
ProjectName
Aveza Phase 1
TotalUnitCount
0
ProjectBuildingId
7,343
BuildingNameNumber
Tower B
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P51900007527
ProjectBuildingWingsId
7,343
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Tower B
NoOfBuildingWingFloorProposed
41
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
41

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK85.4 m² (919 sq.ft)30
3BHK107.1 m² (1,152 sq.ft)1240
3BHK G1107.1 m² (1,152 sq.ft)10
3BHK G2107.1 m² (1,152 sq.ft)10
Total1290
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology