Kolekalyan, Mumbai Suburban 400098 |Promoter: Transcon Bellaviu Private Limited

15 Feb 2024Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
289Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Existing Member 1BHK, Existing Member 2BHK, ExIsting Member 2BHK, Multipurpose Room, Office space, Shop289 units in all
Address
4947/B (pt), CST Road, KalinaPIN 400098
Designated bank account
76
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
15 Feb 2024
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180005486515 Feb 202431 Dec 202730 Apr 2028Transcon Bellaviu Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Kalina Business Centre15289

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 289 units booked (0%), as the promoter reported to MahaRERA

Existing Member 1BHK · 19 unitsExisting Member 2BHK · 13 unitsExIsting Member 2BHK · 8 unitsMultipurpose Room · 89 unitsOffice space · 144 unitsShop · 16 units
TypeCarpet areaUnitsBooked
Existing Member 1BHK36.18 sq m · 389 sq ft190
Existing Member 2BHK71.95 sq m · 774 sq ft130
ExIsting Member 2BHK71.76 sq m · 772 sq ft80
Multipurpose Room27.89 sq m · 300 sq ft100
Multipurpose Room27.9 sq m · 300 sq ft120
Multipurpose Room27.95 sq m · 301 sq ft40
Multipurpose Room27.96 sq m · 301 sq ft240
Multipurpose Room27.99 sq m · 301 sq ft60
Show all 53 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Multipurpose Room28.01 sq m · 301 sq ft40
Multipurpose Room28.02 sq m · 302 sq ft70
Multipurpose Room28.05 sq m · 302 sq ft50
Multipurpose Room28.13 sq m · 303 sq ft100
Multipurpose Room28.23 sq m · 304 sq ft70
Office space35.11 sq m · 378 sq ft140
Office space38.01 sq m · 409 sq ft70
Office space39.65 sq m · 427 sq ft20
Office space39.7 sq m · 427 sq ft70
Office space40.06 sq m · 431 sq ft70
Office space40.32 sq m · 434 sq ft70
Office space46.87 sq m · 505 sq ft70
Office space48.94 sq m · 527 sq ft60
Office space51.69 sq m · 556 sq ft70
Office space51.7 sq m · 556 sq ft10
Office space56.81 sq m · 611 sq ft60
Office space58.99 sq m · 635 sq ft70
Office space60.26 sq m · 649 sq ft70
Office space60.66 sq m · 653 sq ft70
Office space63.44 sq m · 683 sq ft70
Office space66.54 sq m · 716 sq ft10
Office space74.69 sq m · 804 sq ft70
Office space75.71 sq m · 815 sq ft70
Office space92.75 sq m · 998 sq ft70
Office space97.66 sq m · 1,051 sq ft70
Office space100.15 sq m · 1,078 sq ft10
Office space105.31 sq m · 1,134 sq ft70
Office space108.59 sq m · 1,169 sq ft10
Office space113.31 sq m · 1,220 sq ft70
Shop42.73 sq m · 460 sq ft10
Shop43.87 sq m · 472 sq ft10
Shop50.4 sq m · 543 sq ft10
Shop50.65 sq m · 545 sq ft10
Shop52.87 sq m · 569 sq ft10
Shop57.22 sq m · 616 sq ft10
Shop57.43 sq m · 618 sq ft10
Shop60.73 sq m · 654 sq ft10
Shop66.38 sq m · 715 sq ft10
Shop67.25 sq m · 724 sq ft10
Shop79.71 sq m · 858 sq ft10
Shop80.03 sq m · 861 sq ft10
Shop83.28 sq m · 896 sq ft10
Shop100.8 sq m · 1,085 sq ft10
Shop106.43 sq m · 1,146 sq ft10
Shop139.7 sq m · 1,504 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 75 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1_PAN.pdf · uploaded 12 Jan 2024Source

Legal

  • Legal Title report2_TC.pdf · uploaded 12 Jan 2024Source
  • Declaration Form B8_Form-B_Transcon.pdf · uploaded 13 Jan 2024Source

Migrated

  • 1 PAN Card1_PAN.pdf · uploaded 12 Jan 2024Source
  • 1 Copy of the legal title report2_TC.pdf · uploaded 12 Jan 2024Source
  • 1 a Details of encumbrances concerned to Finance3B_Legal Encumbrances Declaration.pdf · uploaded 12 Jan 2024Source
  • 1 b Details of encumbrances concerned to Legal3B_Legal Encumbrances Declaration.pdf · uploaded 12 Jan 2024Source
Show all 76 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted development6_CC.pdf · uploaded 12 Jan 2024Source
  • 1 Declaration about Commencement Certificate7_CC declaration.pdf · uploaded 12 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)10_Er.pdf · uploaded 12 Jan 2024Source
  • 1 CERSAI details12_CERSAI Revised.pdf · uploaded 12 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)11_CA_Revised_06022024.pdf · uploaded 12 Jan 2024Source
  • 1 Declaration in FORM B8_Form-B_Transcon.pdf · uploaded 13 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsKalina-OREO Signed.pdf · uploaded 13 Jan 2024Source
  • 1 Proforma of Allotment letter13_Allotment Letter.pdf · uploaded 13 Jan 2024Source
  • 1 Proforma of Agreement for sale14_AfS.pdf · uploaded 13 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same18_Bank Declaration.pdf · uploaded 13 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letter13A_Allotment Deviation.pdf · uploaded 13 Jan 2024Source
  • 1 Deviation Report with respect to model copy of Agreement14A_Deviation.pdf · uploaded 13 Jan 2024Source
  • 2 a Details of encumbrances concerned to Finance3A_Finance Encumbrance.pdf · uploaded 24 Jan 2024Source
  • 2 b Details of encumbrances concerned to Legal3A_Finance Encumbrance.pdf · uploaded 24 Jan 2024Source
  • 2 Disclosure of Interest in Other Real Estate Organizations17_DM_OREO.pdf · uploaded 24 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)4_1_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • 2 Copy of Layout Approval (in case of layout)4_2_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • 3 Copy of Layout Approval (in case of layout)4_3_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • 4 Copy of Layout Approval (in case of layout)4_4_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted development5_IOA Letter-1.pdf · uploaded 25 Jan 2024Source
  • 1 Other – TechnicalCC Verification.pdf · uploaded 7 Feb 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Kalina- Architect Certificate March 2024.pdf · uploaded 26 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Kalina- Engineer's Certificate March 2024.pdf · uploaded 26 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Kalina- CA Certificate March 2024.pdf · uploaded 26 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A jan to march 24.pdf · uploaded 13 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure for Inventory.pdf · uploaded 16 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Kalina- CA certificate.pdf · uploaded 16 Jul 2024Source
  • 2 Proforma of Allotment letterProforma of Allotment letter UNO.pdf · uploaded 13 Aug 2024Source
  • 2 Proforma of Agreement for saleAFS UNO Final.pdf · uploaded 14 Aug 2024Source
  • 1 Copy of Layout Approval (in case of layout)Loi plans.pdf · uploaded 16 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentKalina Clubbing LOI.pdf · uploaded 16 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UNO Jun 24_CA.pdf · uploaded 5 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)UNO Sep 24_CA.pdf · uploaded 5 Apr 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)UNO Dec 24_CA.pdf · uploaded 5 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)UNO Engg Certificate Jun 24.pdf · uploaded 5 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)UNO Engg Certificate Sept 24.pdf · uploaded 5 Apr 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)UNO Engg Certificate Dec 24.pdf · uploaded 5 Apr 2025Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate UNO.pdf · uploaded 15 Apr 2025Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Certificate UNO.pdf · uploaded 15 Apr 2025Source
  • 1 CERSAI detailsCERSAI_MOE_UNO Prop_SI_400090237996.pdf · uploaded 29 Apr 2025Source
  • Withdrawal Update Form 1UNO form 1 (architect certificate) - June 25.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 2TBPL- Form 2 Aug 2025.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 3Kalina- CA certificate.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 1UNO form 1 (architect certificate) - Sept 25.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2Form 2-TBPL UNO Sep25.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3Form 3-TBPL UNO Sep 25.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1Form 1- Mar 26 UNO.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1Form 1- Mar 26 UNO.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2UNO- Form 2 Mar 26.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2UNO- Form 2 Mar 26.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3UNO Mar 26_11zon.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3UNO Mar 26_11zon.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1UNO Form 1 Jun26.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 2UNO Form 2 Jun26.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 3UNO June 26 Form 3 (1).pdf · uploaded 14 Aug 2026Source

Technical

  • Document4_1_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • Document4_2_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • Document4_3_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • Document4_4_IoA Drawing.pdf · uploaded 25 Jan 2024Source
  • Document5_IOA Letter-1.pdf · uploaded 25 Jan 2024Source
  • Other – TechnicalCC Verification.pdf · uploaded 7 Feb 2024Source
  • DocumentLoi plans.pdf · uploaded 16 Dec 2024Source
  • DocumentKalina Clubbing LOI.pdf · uploaded 16 Dec 2024Source

Technical (Architect)

  • DocumentUNO Form 1 Jun26.pdf · uploaded 13 Aug 2026Source

Technical (Engineer)

  • DocumentUNO Engg Certificate Jun 24.pdf · uploaded 5 Apr 2025Source
  • DocumentUNO Engg Certificate Sept 24.pdf · uploaded 5 Apr 2025Source
  • DocumentUNO Engg Certificate Dec 24.pdf · uploaded 5 Apr 2025Source
  • DocumentUNO Form 2 Jun26.pdf · uploaded 13 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kolekalyan, Andheri taluka

Survey, CTS, gat or plot numbers

4947/B (pt)

Boundaries

North
Parkbay CHSL
South
CST Road
East
Saba Building
West
Akash Darshan CHSL

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArchpro India—
Chartered accountantMalvika & Associates—
EngineerVenturx Project Services LLP—

Source: MahaRERA project page. Contact details are not shown.