Paradise Palace A Wing · Paradise Palace

Kolekalyan · RERA P51800054368

IDBLD_0135332 floorsNot yet due
2Sanctioned habitable floorsregistration certificate
31 Dec 2026Promised completion

Floors

2 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51800054368 · registered 17 Jan 2024
Promised completion
31 Dec 2026
Sanctioned habitable floors
2

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK28.9 m² (311 sq.ft)1not published
1BHK29.8 m² (320 sq.ft)1not published
1BHK32.8 m² (353 sq.ft)2not published
1BHK35.9 m² (387 sq.ft)2not published
1BHKRehab35.8 m² (385 sq.ft)1not published
2BHK35.5 m² (382 sq.ft)1not published
2BHK35.8 m² (385 sq.ft)1not published
2BHK44.9 m² (483 sq.ft)2not published
2BHK45 m² (484 sq.ft)2not published
Shop18 m² (193 sq.ft)1not published
Show all 13 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
Shop20.9 m² (225 sq.ft)1not published
Shop Rehab17.4 m² (187 sq.ft)1not published
Shop Rehab17.9 m² (193 sq.ft)1not published
Total17

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00023
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology