Completion due Dec 2032

Hariyali, Mumbai Suburban 400083 |Promoter: Mumbai Housing And Area Development Board

25 Mar 2026Registered with MahaRERA
31 Dec 2032Promised completion
1Building
70Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

Buildings
1

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.11984, 72.94158
Construction of 70 LIG TS S. No.113(Pt) CTS 356A/2pt Pocket V kanamwar Nagar Mumbai is at latitude 19.11984, longitude 72.94158.
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2032

Registered
25 Mar 2026
Promised
31 Dec 2032

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR118101250304725 Mar 202631 Dec 2032—Mumbai Housing And Area Development BoardProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Development of181970

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo

Registration certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hariyali

Survey, CTS, gat or plot numbers

survey no. 113(pt.) C.T.S. 365A/2(pt.) of

Source: registration certificates, as stated there.