Skip to content

Ashtha Pushp · Ashtha Pushp Andheri East

Chakala · RERA P51800078676

IDBLD_0589087 floorsExtended 4 mo
7Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51800078676 · registered 1 Jan 2025
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
7
ProjectId
53,191
ProjectName
Ashtha Pushp Andheri East
TotalUnitCount
17
ProjectBuildingId
1,13,728
BuildingNameNumber
Ashtha Pushp
FsiWithSanctionSqmts
6TH PART UPPER FLOORS
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
15
ProjectRegistartionNo
P51800078676
ProjectBuildingWingsId
1,17,105
BuildingWingsNameNumber
NA
NonResidentialUnitCount
2
AdvertisedBuildingNameNumber
Ashtha Pushp
NoOfBuildingWingFloorProposed
7
NoOfBuildingWingFloorHabitable
7
NoOfBuildingWingFloorSanctioned
7

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——17not published
Total17
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology