Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 2BHK, 3BHK, 4BHK, Rehab Flat, Rehab Shop101 units in all
- Address
- 2466, 2466 / (1 to 4), S. V. P. Road, Borivali WestPIN 400092
- Designated bank account
- 109
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 20 Jun 2024
- Promised
- 30 Jun 2028
- Revised
- 30 Oct 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800076677 | 20 Jun 2024 | 30 Jun 2028 | 30 Oct 2028 | K Mehta And Company | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Wing A and B | 16 | 101 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
20 of 101 units booked (20%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 67.59 sq m · 728 sq ft | 2 | 0 |
| 3BHK | 99.45 sq m · 1,070 sq ft | 1 | 0 |
| 3BHK | 104.87 sq m · 1,129 sq ft | 10 | 5 |
| 3BHK | 121.49 sq m · 1,308 sq ft | 12 | 5 |
| 3BHK | 126.29 sq m · 1,359 sq ft | 1 | 0 |
| 4BHK | 134.56 sq m · 1,448 sq ft | 15 | 6 |
| 4BHK | 145.18 sq m · 1,563 sq ft | 4 | 3 |
| 4BHK | 153.26 sq m · 1,650 sq ft | 1 | 1 |
Show all 28 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Rehab Flat | 41.96 sq m · 452 sq ft | 4 | 0 |
| Rehab Flat | 48.95 sq m · 527 sq ft | 1 | 0 |
| Rehab Flat | 61.52 sq m · 662 sq ft | 10 | 0 |
| Rehab Flat | 67.59 sq m · 728 sq ft | 12 | 0 |
| Rehab Flat | 79.2 sq m · 853 sq ft | 1 | 0 |
| Rehab Flat | 89.55 sq m · 964 sq ft | 2 | 0 |
| Rehab Flat | 90.79 sq m · 977 sq ft | 3 | 0 |
| Rehab Flat | 100.97 sq m · 1,087 sq ft | 5 | 0 |
| Rehab Flat | 104.87 sq m · 1,129 sq ft | 3 | 0 |
| Rehab Flat | 121.49 sq m · 1,308 sq ft | 1 | 0 |
| Rehab Flat | 134.56 sq m · 1,448 sq ft | 1 | 0 |
| Rehab Flat | 147.4 sq m · 1,587 sq ft | 2 | 0 |
| Rehab Shop | 25.37 sq m · 273 sq ft | 1 | 0 |
| Rehab Shop | 29.97 sq m · 323 sq ft | 2 | 0 |
| Rehab Shop | 32.33 sq m · 348 sq ft | 1 | 0 |
| Rehab Shop | 32.48 sq m · 350 sq ft | 1 | 0 |
| Rehab Shop | 35.38 sq m · 381 sq ft | 1 | 0 |
| Rehab Shop | 35.49 sq m · 382 sq ft | 1 | 0 |
| Rehab Shop | 36.49 sq m · 393 sq ft | 2 | 0 |
| Rehab Shop | 192.43 sq m · 2,071 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 67 filings listed on MahaRERA's project page
Finance
- PAN Card1 PAN Card.pdf · uploaded 22 May 2024Source
Legal
Migrated
- 1 PAN Card1 PAN Card.pdf · uploaded 22 May 2024Source
- 1 Copy of the legal title report2 Copy of the legal title report.pdf · uploaded 22 May 2024Source
- 1 a Details of encumbrances concerned to Finance4 b Details of encumbrances concerned to Legal (1).pdf · uploaded 22 May 2024Source
- 1 b Details of encumbrances concerned to Legal4 b Details of encumbrances concerned to Legal (1).pdf · uploaded 22 May 2024Source
Show all 68 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LP.pdf · uploaded 22 May 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBP 1.pdf · uploaded 22 May 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBP 2.pdf · uploaded 22 May 2024Source
- 1 Commencement Certificates / NA Order for plotted development7 Commencement Certificates _ NA Order for plotted development.pdf · uploaded 22 May 2024Source
- 1 Declaration about Commencement Certificate8 Declaration about Commencement Certificate.pdf · uploaded 22 May 2024Source
- 1 Declaration in FORM B9 Declaration in FORM B.pdf · uploaded 22 May 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations21 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 22 May 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations22 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 22 May 2024Source
- 1 Proforma of Agreement for sale30 Proforma of Agreement for sale.pdf · uploaded 22 May 2024Source
- 1 Proforma of Allotment letter31 Proforma of Allotment letter.pdf · uploaded 22 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same40 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 22 May 2024Source
- 1 Deviation Report with respect to Allotment letter41 Deviation Report with respect to Allotment letter.pdf · uploaded 22 May 2024Source
- 1 Deviation Report with respect to model copy of Agreement42 Deviation Report with respect to model copy of Agreement.pdf · uploaded 22 May 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance Finance 28th May.pdf · uploaded 6 Jun 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance Finance 28th May.pdf · uploaded 6 Jun 2024Source
- 1 CERSAI detailsCersai 28th May.pdf · uploaded 6 Jun 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 29th May.pdf · uploaded 6 Jun 2024Source
- 1 Other – TechnicalAnnexure A 28th May.pdf · uploaded 6 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Shreeji leela_RERA_Architect form 1_compressed.pdf · uploaded 22 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate.pdf · uploaded 22 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 _ Shreeji Leela Signed_compressed.pdf · uploaded 22 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)SHREEJI LEELA_Form 1.pdf · uploaded 6 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA CERTIFICATE_Shreeji Leela.pdf · uploaded 6 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Sanjay.pdf · uploaded 6 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)SHREEJI LEELA_Form 1.pdf · uploaded 18 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3_CA Certificate_Shreeji Leela.pdf · uploaded 18 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Engineer Certificate.pdf · uploaded 18 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Architect Certificate.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA Certificate_Sanjay - Signed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Engineer Certificate.pdf · uploaded 19 Apr 2025Source
- Form 5 (FY 2024-2025)Form 5-Signed (2).pdf · uploaded 26 Sep 2025Source
- Withdrawal Update Form 1SHREEJI LEELA_Form 1.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 1SHREEJI LEELA_Form 1.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 2Form2_Sign.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 2Form2_Sign.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3 -Signed.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3 -Signed.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 1SHREEJI LEELA_Form 1_Sign.pdf · uploaded 14 Jan 2026Source
- Withdrawal Update Form 2Form_2 Engineer Certificate.pdf · uploaded 14 Jan 2026Source
- Withdrawal Update Form 3Form 3_CA Certificate.pdf · uploaded 14 Jan 2026Source
- Withdrawal Update Form 1Form 1_Architect Certificate_Sign.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3-Signed.pdf · uploaded 20 Apr 2026Source
- Form 5 (FY 2025-2026)Form5_2025-26-signed.pdf · uploaded 21 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A_Quality Assurance.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 1Form 1_Architect Certificate_Shreeji Leela.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2_Engineer Certificate_Shreeji Leela.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3_CA Certificate_Shreeji Leela.pdf · uploaded 20 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Borivali, Borivali taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Shreeji Tower Jai Shrinath CHSL CTS No 2467 A
- South
- Saddicha CTS No 2465 B
- East
- Sahjeevan CHSL CTS No 2474 A and 2475
- West
- Mandpeshwar Road S V P Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Harish Gandhi | — |
| Chartered accountant | Darshan Shah | — |
| Chartered accountant | Shah & Vejani | — |
| Engineer | Bindesh Chitalia | — |
| Engineer | Mr Hiren M Tanna | — |
Source: MahaRERA project page. Contact details are not shown.