Royal Pristo

Certificate Signed

Borivali, Mumbai Suburban 400097 |Promoter: Royal Realtors

Residential / Group HousingRERAP51800019529
8 Feb 2019Registered with MahaRERA
30 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
2Buildings
681Units registered490 booked (72%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
Flat n 1, Flat n 10, Flat n 11, Flat n 17, Flat n 18, Flat n 21, Flat n 22, Flat n 6, Flat n 8, Flat no 16, Flat no 17, Flat no 9, Shop type 20, Shop type 26, Shop type 35, Shop type 4, Shop type 48, Shop type 49, Shop type 52, Shop type 64, Comm office 2nd flr, Daigonstic center, Departmental store f, Departmental store g, Intermediate basemen, Office no 1, Office no 11, Office no 2, Office no 3, Office no 4, Office no 5, Office no 6, Office no 7, Office no 8, Office no 9, Shop no 1, Shop no 10, Shop no 11, Shop no 12, Shop no 13, Shop no 14, Shop no 15, Shop no 16, Shop no 17, Shop no 18, Shop no 2, Shop no 3, Shop no 4, Shop no 5, Shop no 6, Shop no 7, Shop no 8, Shop no 9, Type1, Type10, Type11, Type12, Type13, Type14, Type15, Type16, Type17, Type18, Type2, Type3, Type4, Type5, Type6, Type7, Type8, Type9681 units in all
Address
712 713 714 715 And Other As Per Loi, Santoshi Mata Temple Road, Vaishetpada Kurar Village Malad EastPIN 400097
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.18437, 72.86426
Royal Pristo is at latitude 19.18437, longitude 72.86426.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
8 Feb 2019
Promised
30 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000195298 Feb 201930 Dec 202630 Apr 2027Royal RealtorsProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Royal Parv2821
Royal Pristo25660

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

490 of 681 units booked (72%), as the promoter reported to MahaRERA

Flat n 1 · 1 unitFlat n 10 · 1 unitFlat n 11 · 1 unitFlat n 17 · 1 unitFlat n 18 · 1 unitFlat n 21 · 1 unitFlat n 22 · 1 unitFlat n 6 · 1 unitFlat n 8 · 1 unitFlat no 16 · 1 unitFlat no 17 · 1 unitFlat no 9 · 1 unitShop type 20 · 1 unitShop type 26 · 1 unitShop type 35 · 1 unitShop type 4 · 2 unitsShop type 48 · 1 unitShop type 49 · 1 unitShop type 52 · 1 unitShop type 64 · 1 unitComm office 2nd flr · 1 unitDaigonstic center · 1 unitDepartmental store f · 1 unitDepartmental store g · 1 unitIntermediate basemen · 1 unitOffice no 1 · 1 unitOffice no 11 · 1 unitOffice no 2 · 1 unitOffice no 3 · 1 unitOffice no 4 · 1 unitOffice no 5 · 1 unitOffice no 6 · 1 unitOffice no 7 · 1 unitOffice no 8 · 1 unitOffice no 9 · 1 unitShop no 1 · 1 unitShop no 10 · 1 unitShop no 11 · 1 unitShop no 12 · 1 unitShop no 13 · 1 unitShop no 14 · 1 unitShop no 15 · 1 unitShop no 16 · 1 unitShop no 17 · 1 unitShop no 18 · 1 unitShop no 2 · 1 unitShop no 3 · 1 unitShop no 4 · 1 unitShop no 5 · 1 unitShop no 6 · 1 unitShop no 7 · 1 unitShop no 8 · 1 unitShop no 9 · 1 unitType1 · 45 unitsType10 · 10 unitsType11 · 10 unitsType12 · 5 unitsType13 · 5 unitsType14 · 384 unitsType15 · 1 unitType16 · 1 unitType17 · 5 unitsType18 · 1 unitType2 · 30 unitsType3 · 30 unitsType4 · 30 unitsType5 · 15 unitsType6 · 15 unitsType7 · 15 unitsType8 · 15 unitsType9 · 10 units
BuildingTypeCarpet areaUnitsBooked
Royal ParvFlat n 138.09 sq m · 410 sq ft11
Royal ParvFlat n 1032.84 sq m · 353 sq ft10
Royal ParvFlat n 1129.63 sq m · 319 sq ft11
Royal ParvFlat n 1742.34 sq m · 456 sq ft10
Royal ParvFlat n 1836.49 sq m · 393 sq ft11
Royal ParvFlat n 2130.35 sq m · 327 sq ft10
Royal ParvFlat n 2239.74 sq m · 428 sq ft11
Royal ParvFlat n 645.25 sq m · 487 sq ft11
Show all 72 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Royal ParvFlat n 840.76 sq m · 439 sq ft10
Royal ParvFlat no 1624.29 sq m · 261 sq ft11
Royal ParvFlat no 1721.7 sq m · 234 sq ft11
Royal ParvFlat no 937.41 sq m · 403 sq ft10
Royal ParvShop type 2010.62 sq m · 114 sq ft10
Royal ParvShop type 2622.25 sq m · 239 sq ft10
Royal ParvShop type 3511.79 sq m · 127 sq ft10
Royal ParvShop type 44.48 sq m · 48 sq ft10
Royal ParvShop type 46.5 sq m · 70 sq ft10
Royal ParvShop type 4814.02 sq m · 151 sq ft10
Royal ParvShop type 4952.97 sq m · 570 sq ft10
Royal ParvShop type 5212.64 sq m · 136 sq ft10
Royal ParvShop type 6411.63 sq m · 125 sq ft10
Royal PristoComm office 2nd flr445.56 sq m · 4,796 sq ft11
Royal PristoDaigonstic center61.46 sq m · 662 sq ft10
Royal PristoDepartmental store f407.7 sq m · 4,388 sq ft11
Royal PristoDepartmental store g299.66 sq m · 3,226 sq ft10
Royal PristoIntermediate basemen434.95 sq m · 4,682 sq ft10
Royal PristoOffice no 130.33 sq m · 326 sq ft10
Royal PristoOffice no 1185.18 sq m · 917 sq ft10
Royal PristoOffice no 223 sq m · 248 sq ft10
Royal PristoOffice no 320.77 sq m · 224 sq ft11
Royal PristoOffice no 423.18 sq m · 250 sq ft11
Royal PristoOffice no 520.59 sq m · 222 sq ft10
Royal PristoOffice no 623.46 sq m · 253 sq ft10
Royal PristoOffice no 721.9 sq m · 236 sq ft10
Royal PristoOffice no 821.9 sq m · 236 sq ft10
Royal PristoOffice no 920.78 sq m · 224 sq ft10
Royal PristoShop no 139.42 sq m · 424 sq ft11
Royal PristoShop no 1027.76 sq m · 299 sq ft11
Royal PristoShop no 1125.92 sq m · 279 sq ft11
Royal PristoShop no 1225.92 sq m · 279 sq ft11
Royal PristoShop no 1324.58 sq m · 265 sq ft11
Royal PristoShop no 1423.13 sq m · 249 sq ft10
Royal PristoShop no 1526.15 sq m · 281 sq ft10
Royal PristoShop no 1626.53 sq m · 286 sq ft10
Royal PristoShop no 1729.43 sq m · 317 sq ft11
Royal PristoShop no 1817.1 sq m · 184 sq ft10
Royal PristoShop no 231.47 sq m · 339 sq ft11
Royal PristoShop no 325.9 sq m · 279 sq ft11
Royal PristoShop no 427.52 sq m · 296 sq ft11
Royal PristoShop no 528.45 sq m · 306 sq ft11
Royal PristoShop no 627.17 sq m · 292 sq ft11
Royal PristoShop no 721.57 sq m · 232 sq ft11
Royal PristoShop no 824.36 sq m · 262 sq ft11
Royal PristoShop no 924.36 sq m · 262 sq ft11
Royal PristoType159.99 sq m · 646 sq ft4531
Royal PristoType1046.22 sq m · 498 sq ft109
Royal PristoType1145.79 sq m · 493 sq ft105
Royal PristoType1244.27 sq m · 477 sq ft51
Royal PristoType1362.54 sq m · 673 sq ft55
Royal PristoType1430 sq m · 323 sq ft384305
Royal PristoType1536.24 sq m · 390 sq ft10
Royal PristoType1637.36 sq m · 402 sq ft10
Royal PristoType1744.44 sq m · 478 sq ft54
Royal PristoType1841.12 sq m · 443 sq ft11
Royal PristoType259.64 sq m · 642 sq ft3018
Royal PristoType342.29 sq m · 455 sq ft3024
Royal PristoType441.96 sq m · 452 sq ft3022
Royal PristoType540.61 sq m · 437 sq ft158
Royal PristoType640.44 sq m · 435 sq ft159
Royal PristoType758.8 sq m · 633 sq ft155
Royal PristoType863.19 sq m · 680 sq ft158
Royal PristoType963.26 sq m · 681 sq ft1010

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 100 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportTLR.pdf · uploaded 21 Jan 2019Source
  • Declaration Form BForm B Redue Size 1.pdf · uploaded 21 Jan 2019Source
  • OtherRoyal Pristo Block Plan-Model.pdf · uploaded 29 Jan 2019Source
  • Other1171 OF 2019-High Court order.pdf · uploaded 23 Jul 2022Source
  • OtherWP 1460 OF 2019 High court order.pdf · uploaded 23 Jul 2022Source

Migrated

  • 1 Copy of the legal title reportTLR.pdf · uploaded 21 Jan 2019Source
  • 1 Details of encumbrancesEncumberence Reduce Size.pdf · uploaded 21 Jan 2019Source
Show all 101 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout Plan Reducd Size.pdf · uploaded 21 Jan 2019Source
  • 1 Building Plan Approval (IOD)Combine IOD Letter.pdf · uploaded 21 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCombine CC.pdf · uploaded 21 Jan 2019Source
  • 1 Declaration in FORM BForm B Redue Size 1.pdf · uploaded 21 Jan 2019Source
  • 1 Certificates of CA (Form 3)Royal Pristo CA certificate.pdf · uploaded 28 Jan 2019Source
  • 1 Proforma of Allotment letterLETTER.pdf · uploaded 29 Jan 2019Source
  • 1 OtherRoyal Pristo Block Plan-Model.pdf · uploaded 29 Jan 2019Source
  • 2 Proforma of Allotment letterAllotmentp0.pdf · uploaded 8 Feb 2019Source
  • 3 Proforma of Allotment letterAFS.pdf · uploaded 29 Mar 2019Source
  • 1 Form 2AEngineer RERA Certificate_compressed.pdf · uploaded 13 Jun 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 10 Oct 2019Source
  • 4 Proforma of Allotment letterAFS (RP) (STD).pdf · uploaded 22 Oct 2019Source
  • 5 Proforma of Allotment letterafs.pdf · uploaded 26 Oct 2019Source
  • 2 Details of encumbrancesSelf Declaration with Regards to Encumbrances.pdf · uploaded 7 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Royal Pristo5.pdf · uploaded 7 Dec 2020Source
  • 2 Building Plan Approval (IOD)iod rp.pdf · uploaded 19 Feb 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC rp.pdf · uploaded 19 Feb 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC 21.pdf · uploaded 13 Aug 2021Source
  • 5 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 29 Oct 2021Source
  • 3 Details of encumbrancesletters.pdf · uploaded 15 Nov 2021Source
  • 6 Proforma of Allotment letterafs final.pdf · uploaded 15 Nov 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (Architect Certificate) upto March 2022.pdf · uploaded 11 Jun 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (Engineer Certificate) upto March 2022_compressed (1).pdf · uploaded 11 Jun 2022Source
  • 2 Certificates of CA (Form 3)Form 3 (CA Certificate) upto March 2022_compressed (1).pdf · uploaded 11 Jun 2022Source
  • 2 Other1171 OF 2019-High Court order.pdf · uploaded 23 Jul 2022Source
  • 3 OtherWP 1460 OF 2019 High court order.pdf · uploaded 23 Jul 2022Source
  • 4 Details of encumbrancesEnc RR.pdf · uploaded 15 Feb 2023Source
  • 1 Proforma of Agreement for saleAFS- 2023 -FLAT.pdf · uploaded 18 Mar 2023Source
  • 7 Proforma of Allotment letterALLOTMENT LETTER - 2023.pdf · uploaded 18 Mar 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - June 2022.pdf · uploaded 18 Jul 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Sept 22.pdf · uploaded 18 Jul 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Sept 22.pdf · uploaded 18 Jul 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Dec 22.pdf · uploaded 18 Jul 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate March 23.pdf · uploaded 18 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - June 2022.pdf · uploaded 18 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Sept 2022.pdf · uploaded 18 Jul 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Dec 2022.pdf · uploaded 18 Jul 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate March 23.pdf · uploaded 18 Jul 2023Source
  • 3 Certificates of CA (Form 3)Form 3 30062022.pdf · uploaded 18 Jul 2023Source
  • 4 Certificates of CA (Form 3)Form 3 30092022.pdf · uploaded 18 Jul 2023Source
  • 5 Certificates of CA (Form 3)Form 3 31122022.pdf · uploaded 18 Jul 2023Source
  • 6 Certificates of CA (Form 3)Form 3 31032023.pdf · uploaded 18 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Pristo Form 5 FY 20-21.pdf · uploaded 18 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Pristo Form 5 FY 21-22.pdf · uploaded 18 Jul 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Q2 Pristo.pdf · uploaded 19 Jan 2024Source
  • 6 Commencement Certificates / NA Order for plotted developmentRPCC.pdf · uploaded 17 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Pristo.pdf · uploaded 21 Mar 2024Source
  • 1 Disclosure of sold/ booked inventoryRoyal Pristo Q1_compressed.pdf · uploaded 3 Apr 2024Source
  • 2 Disclosure of sold/ booked inventoryRoyal Pristo Q2_compressed.pdf · uploaded 3 Apr 2024Source
  • 3 Disclosure of sold/ booked inventoryRoyal Pristo Q3_compressed.pdf · uploaded 3 Apr 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Q1 Pristo.pdf · uploaded 5 Apr 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Q2 Pristo.pdf · uploaded 5 Apr 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate RR Jan 2024.pdf · uploaded 22 Apr 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate RR Apr 2024.pdf · uploaded 22 Apr 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate RR Jan 2024.pdf · uploaded 22 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)QAC RPristo RR 22-23_0001 final.pdf · uploaded 3 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)QAC RPristo RR 22-23_0001 final.pdf · uploaded 3 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QAC RPristo RR 23-24_0001final.pdf · uploaded 3 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2.pdf · uploaded 13 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3.pdf · uploaded 13 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1.pdf · uploaded 13 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Q1 Pristo.pdf · uploaded 14 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Q4 Pristo (Revised Cost).pdf · uploaded 14 Feb 2025Source
  • 5 Certificates of CA (Form 3)Form 3 Pristo Dec 2024 upload.pdf · uploaded 21 Feb 2025Source
  • 4 Certificates of CA (Form 3)Form 3 Pristo Sept 2024 upload.pdf · uploaded 21 Feb 2025Source
  • 3 Certificates of CA (Form 3)Form 3 Pristo June 2024.pdf · uploaded 21 Feb 2025Source
  • 2 Certificates of CA (Form 3)Form 3 Pristo Mar 2024_upload.pdf · uploaded 21 Feb 2025Source
  • 1 Certificates of CA (Form 3)Form 3 Pristo June 2023_upload.pdf · uploaded 21 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pristo FY 24-25 Q1.pdf · uploaded 21 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pristo FY 24-25 Q2.pdf · uploaded 21 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pristo FY 24-25 Q3.pdf · uploaded 21 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 signed.pdf · uploaded 22 Feb 2025Source
  • 7 Certificates of CA (Form 3)Pristo_Form 3 Dec 2023_upload.pdf · uploaded 24 Feb 2025Source
  • 6 Certificates of CA (Form 3)Pristo Form 3_Sept 2023_upload.pdf · uploaded 24 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySodl Unsold_Declaration_ Dec 2024 Pristo_11zon.pdf · uploaded 27 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryMar 24.pdf · uploaded 4 Mar 2025Source
  • 3 Disclosure of sold/ booked inventoryJune 24.pdf · uploaded 4 Mar 2025Source
  • 4 Disclosure of sold/ booked inventorySep 24.pdf · uploaded 4 Mar 2025Source
  • Form 1Architect Certificate Form 1 Pristo, Parv.pdf · uploaded 4 Jun 2025Source
  • Form 2A (FY 2024-2025)Royal Realtors Form 2A march 2025.pdf · uploaded 4 Jun 2025Source

Technical

  • DocumentCombine IOD Letter.pdf · uploaded 21 Jan 2019Source
  • DocumentLayout Plan Reducd Size.pdf · uploaded 21 Jan 2019Source
  • Documentiod rp.pdf · uploaded 19 Feb 2021Source

Technical (Architect)

  • DocumentArch Certificate RR Apr 2024.pdf · uploaded 22 Apr 2024Source
  • DocumentForm 1 Q1.pdf · uploaded 13 Feb 2025Source
  • DocumentForm 1 Q2.pdf · uploaded 13 Feb 2025Source
  • DocumentForm 1 Q3.pdf · uploaded 13 Feb 2025Source

Technical (Engineer)

  • DocumentEngineers Certificate RR Jan 2024.pdf · uploaded 22 Apr 2024Source
  • DocumentEngg Certificate Q1 Pristo.pdf · uploaded 14 Feb 2025Source
  • DocumentEngg Certificate Q4 Pristo (Revised Cost).pdf · uploaded 14 Feb 2025Source
  • DocumentForm 2 Pristo FY 24-25 Q1.pdf · uploaded 21 Feb 2025Source
  • DocumentForm 2 Pristo FY 24-25 Q2.pdf · uploaded 21 Feb 2025Source
  • DocumentForm 2 Pristo FY 24-25 Q3.pdf · uploaded 21 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

712 713 714 715

Boundaries

North
13 4 Mt Wide Proposed Dp Road
South
Existing Bldg
East
Existing Bldg
West
18 3 Mt Wide Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSkytech Consultants—
Chartered accountantJ D Shah & Associates—
EngineerAesthetic Engineers—
EngineerMitesh Gada—
EngineerSanghavi And Associates And Consultants Pvt Ltd—
EngineerShubham Suhas Sawant—
OtherSatpanth Assocaites—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology