Modispaces Volga

Certificate Signed

Borivali, Mumbai Suburban 400092 |Promoter: Modispaces Real Estate Pvt Ltd

Residential / Group HousingRERAP51800028532
10 Mar 2021Registered with MahaRERA
30 Jun 2024Promised completion
31 Dec 2024Revised completionPushed back 6 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Address
680A/1/5, 680A/1/6 and 680A/1/7, TPS Borivali III, Shimpoli Boriwali W, Rayani Gram LayoutPIN 400092
Designated bank account
85
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 months

The latest completion date on record passed 1 year and 10 months ago.

Registered
10 Mar 2021
Promised
30 Jun 2024
Revised
31 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180002853210 Mar 202130 Jun 202431 Dec 2024Modispaces Real Estate Pvt LtdProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Modispaces Volga25—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPan Card Modispaces RealEstate.pdf · uploaded 29 Jan 2021Source

Legal

  • Legal Title reportTitle Certificate Bmc (22-2-20)_Om Sundar Vichar .pdf · uploaded 30 Jan 2021Source
  • Declaration Form BRE SCAN OF FORM B _Om Sundar Vichar.pdf · uploaded 1 Feb 2021Source
  • Declaration Form BNew Form B (Extension)_Volga.pdf · uploaded 18 May 2024Source

Migrated

  • 1 PAN CardPan Card Modispaces RealEstate.pdf · uploaded 29 Jan 2021Source
  • 1 Copy of the legal title reportTitle Certificate Bmc (22-2-20)_Om Sundar Vichar .pdf · uploaded 30 Jan 2021Source
Show all 89 documentsShow fewer documents

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT RERA FORM (1).pdf · uploaded 30 Jan 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society registration certificate.pdf · uploaded 30 Jan 2021Source
  • 1 Status of ConveyanceIndex2 conveyance-Sadvichar.pdf · uploaded 30 Jan 2021Source
  • 2 Status of ConveyanceIndex2 conveyance-Sundaram.pdf · uploaded 30 Jan 2021Source
  • 1 Details of encumbrancesEncumbarance certificate for RERA uploading.pdf · uploaded 1 Feb 2021Source
  • 1 Copy of Layout Approval (in case of layout)Rayani Gram Layout.pdf · uploaded 1 Feb 2021Source
  • 1 Declaration in FORM BRE SCAN OF FORM B _Om Sundar Vichar.pdf · uploaded 1 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 4 Feb 2021Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)amalgamation Intimation ltr fm Registrar to Om Sadvichar(b)(7-3-19)_Om sunadarvichar.pdf · uploaded 25 Feb 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentIod Plan.pdf · uploaded 26 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted development1st CC.pdf · uploaded 26 Feb 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM NO 03 VOLGA CERTIFIED_compressed.pdf · uploaded 27 Feb 2021Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 27 Feb 2021Source
  • 2 Proforma of Allotment letterRERA Sale Agr.pdf · uploaded 27 Feb 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 24 May 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentAmendent Iod Plan.pdf · uploaded 31 May 2021Source
  • 1 Disclosure of sold/ booked inventoryBooked Inventory.pdf · uploaded 8 Jun 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentFull IOD _Modispaces Volga (22-07-21).pdf · uploaded 27 Jul 2021Source
  • 2 Disclosure of sold/ booked inventoryBooked Inventory (06-08-21).pdf · uploaded 10 Aug 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentFurtherCC_Modispaces Volga.pdf · uploaded 17 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A_Volga.pdf · uploaded 14 Apr 2022Source
  • 1 CERSAI detailsCERSAI DECLARATION_Volga.pdf · uploaded 14 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 fy 20-21 Volga.pdf · uploaded 14 Apr 2022Source
  • 1 Declaration about Commencement CertificateCC Declaration (04-05-22)_Volga.pdf · uploaded 4 May 2022Source
  • 2 CERSAI detailsCERSAI__Report.pdf · uploaded 4 May 2022Source
  • 2 Copy of Layout Approval (in case of layout)plans 1.pdf · uploaded 17 May 2022Source
  • 3 Copy of Layout Approval (in case of layout)plans 2.pdf · uploaded 17 May 2022Source
  • 4 Copy of Layout Approval (in case of layout)plans 3 and 4.pdf · uploaded 17 May 2022Source
  • 5 Copy of Layout Approval (in case of layout)plans 5 and 6.pdf · uploaded 17 May 2022Source
  • 6 Copy of Layout Approval (in case of layout)plans 7.pdf · uploaded 17 May 2022Source
  • 7 Copy of Layout Approval (in case of layout)plans 8 and 9.pdf · uploaded 17 May 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 17 May 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentFinal CC 17-05-22 Volga.pdf · uploaded 16 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 _Volga.pdf · uploaded 3 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Volga.pdf · uploaded 3 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2023 Volga Form1.pdf · uploaded 2 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)June 2023 Volga Form1.pdf · uploaded 2 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sept 2023Volga Form1.pdf · uploaded 2 Feb 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2023 Volga Form1.pdf · uploaded 2 Feb 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of Inventory_31-03-23.pdf · uploaded 13 Feb 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of Inventory_30-06-23.pdf · uploaded 13 Feb 2024Source
  • 5 Disclosure of sold/ booked inventoryDisclosure of Inventory_30-09-23.pdf · uploaded 13 Feb 2024Source
  • 6 Disclosure of sold/ booked inventoryDisclosure of Inventory_31-12-23.pdf · uploaded 13 Feb 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2023 Volga Form1.pdf · uploaded 29 Feb 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)June 2023 Volga Form1.pdf · uploaded 29 Feb 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sept 2023Volga Form1.pdf · uploaded 29 Feb 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2023 Volga Form1.pdf · uploaded 29 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Form 2 Volga format dt 30-06-2023 - Signed.pdf · uploaded 29 Feb 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Form 2 Volga format dt 30-09-2023 - Signed.pdf · uploaded 29 Feb 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Form 2 Volga format dt 31-12-2023.pdf · uploaded 29 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 29 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 29 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 21-22.pdf · uploaded 23 Apr 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 22-23.pdf · uploaded 23 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3 JUNE 23.pdf · uploaded 25 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3 SEP 23.pdf · uploaded 25 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3 DEC 23.pdf · uploaded 25 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)New Form 3_Volga_Mar 2024_signed.pdf · uploaded 17 May 2024Source
  • 2 Declaration in FORM BNew Form B (Extension)_Volga.pdf · uploaded 18 May 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)MODISPACES VOLGA RERA CERTIFICATE JAN 2024 TO MARCH 2024 (2).pdf · uploaded 22 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Form 2 Volga march 2024 - 13-05-2024.pdf · uploaded 22 May 2024Source
  • 7 Disclosure of sold/ booked inventoryNew Disclousure of Inventory_31-03-24 (15-05-24).pdf · uploaded 22 May 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A DOI.pdf · uploaded 25 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Old Bank details.pdf · uploaded 25 May 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 (1).pdf · uploaded 11 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2432537_OC_signed (3).pdf · uploaded 11 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form - 2A - Site Supervisor - 2023-24-1 (1).pdf · uploaded 7 Dec 2024Source

Technical

  • DocumentRayani Gram Layout.pdf · uploaded 1 Feb 2021Source
  • DocumentIOD.pdf · uploaded 4 Feb 2021Source
  • DocumentIod Plan.pdf · uploaded 26 Feb 2021Source
  • DocumentAmendent Iod Plan.pdf · uploaded 31 May 2021Source
  • DocumentFull IOD _Modispaces Volga (22-07-21).pdf · uploaded 27 Jul 2021Source
  • DocumentIOD.pdf · uploaded 17 May 2022Source
  • Documentplans 1.pdf · uploaded 17 May 2022Source
  • Documentplans 2.pdf · uploaded 17 May 2022Source
  • Documentplans 3 and 4.pdf · uploaded 17 May 2022Source
  • Documentplans 5 and 6.pdf · uploaded 17 May 2022Source
  • Documentplans 7.pdf · uploaded 17 May 2022Source
  • Documentplans 8 and 9.pdf · uploaded 17 May 2022Source

Technical (Architect)

  • DocumentMODISPACES VOLGA RERA CERTIFICATE JAN 2024 TO MARCH 2024 (2).pdf · uploaded 22 May 2024Source

Technical (Engineer)

  • DocumentEngineer Form 2 Volga march 2024 - 13-05-2024.pdf · uploaded 22 May 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

680A/1/5680A/1/6680A/1/7

Boundaries

North
Existing Road
South
Sahakar CHSL
East
Internal Layout Road
West
Om Sadachar CHSL

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectChogle & Associates—
Chartered accountantSwaroop Jain & Co—
EngineerSura & Associates—
OtherEco Mep Consultant—
OtherSpag Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology