Skip to content
Deedo home
Menu

Krishnam

Completed

Borivali, Mumbai Suburban 400064 |Promoter: Bhalani & Mehta (Aop)

Residential / Group HousingRERAP51800021871
8 Aug 2019Registered with MahaRERA
30 Dec 2022Promised completion
1Building
11Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, 2BHK, Existing member 201, Existing member 401, Office space, Shop11 units in all
Land area for this project
306 sq m (3,296 sq ft)
Permissible built-up area
909 sq m (9,789 sq ft)
Sanctioned built-up area
553 sq m (5,953 sq ft)
Recreational open space
212 sq m (2,279 sq ft)
Address
519, 519/1-2, Adarsh Dughdhalay Lane, Malad WestPIN 400064
Designated bank account
South Indian Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Krishnam is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
8 Aug 2019
Promised
30 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000218718 Aug 201930 Dec 2022—Bhalani & Mehta (Aop)Project page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Krishnam911

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

11 units registered

1BHK · 3 units2BHK · 1 unitExisting member 201 · 1 unitExisting member 401 · 1 unitOffice space · 3 unitsShop · 2 units
TypeCarpet areaUnits
1BHK47.19 sq m · 508 sq ft2
1BHK49.39 sq m · 532 sq ft1
2BHK57.14 sq m · 615 sq ft1
Existing member 2013.25 sq m · 35 sq ft1
Existing member 40110.03 sq m · 108 sq ft1
Office space33.77 sq m · 363 sq ft1
Office space51.47 sq m · 554 sq ft1
Office space55.06 sq m · 593 sq ft1
Shop49.6 sq m · 534 sq ft1
Shop51.09 sq m · 550 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00003
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Krishnam

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingCOMPLETED100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalCOMPLETED100%
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWIP100%
  • Electrical meter room, sub-station, receiving stationWIP100%
  • Aggregate area of recreational Open SpaceWIP0%
  • Open ParkingWIP0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

64 documents held by Deedo, 78 filings listed on MahaRERA's project page

Other (63)

Show all 142 documentsShow fewer documents

Other (63)

Registration certificate

Document library

  • Details of encumbrancesDeclaration for Non Encumbrances.pdf · uploaded 29 Jun 2019View
  • Status of ConveyanceCONVEYANCE INDEX 2.pdf · uploaded 29 Jun 2019View
  • Copy of the legal title reportTitle Certificate.pdf · uploaded 29 Jun 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 Jun 2019View
  • Building Plan Approval (IOD)Original IOD.pdf · uploaded 29 Jun 2019View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 29 Jun 2019View
  • Copy of Layout Approval (in case of layout)Block Plan Location Plan.pdf · uploaded 29 Jun 2019View
  • Proforma of Allotment letterRERA SALE AGREEMENT.pdf · uploaded 29 Jun 2019View
  • Building Plan Approval (IOD)Original IOD Drawing.pdf · uploaded 29 Jun 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form2 ENGINEER CERTIFICATE.pdf · uploaded 19 Jul 2019View
  • Declaration in FORM BDeclaration 001.pdf · uploaded 2 Aug 2019View
  • Declaration in FORM BDeclaration 002.pdf · uploaded 2 Aug 2019View
  • Declaration in FORM BDeclaration 003.pdf · uploaded 2 Aug 2019View
  • Declaration in FORM BDeclaration 004.pdf · uploaded 2 Aug 2019View
  • Commencement Certificates / NA Order for plotted developmentKRISHNAM CC.pdf · uploaded 3 Jul 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 01.pdf · uploaded 6 Jul 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 02.pdf · uploaded 6 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A - FY 2019-20_compressed.pdf · uploaded 6 Jul 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A - FY 2020-21_compressed.pdf · uploaded 6 Jul 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 01_compressed.pdf · uploaded 6 Jul 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 02.pdf · uploaded 6 Jul 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CA Certificate.pdf · uploaded 8 Jul 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA Certificate.pdf · uploaded 8 Jul 2021View
  • Declaration about Commencement CertificateRERA CC Decleration.pdf · uploaded 15 Jul 2021View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf · uploaded 15 Jul 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 6 Aug 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG.pdf · uploaded 6 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A_compressed.pdf · uploaded 6 Aug 2021View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf · uploaded 6 Aug 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE Upto Sept 2021.pdf · uploaded 6 Oct 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE Upto Sept 2021.pdf · uploaded 6 Oct 2021View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf · uploaded 6 Oct 2021View
  • Declaration about Commencement CertificateFORMAT D - CC Decleration (1).pdf · uploaded 6 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A - FY 2021-22 2nd Qtr_compressed.pdf · uploaded 6 Oct 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)arch comp.pdf · uploaded 18 Jan 2022View
  • Commencement Certificates / NA Order for plotted developmentoutput.pdf · uploaded 18 Jan 2022View
  • Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 18 Jan 2022View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng comp.pdf · uploaded 18 Jan 2022View
  • Copy of Layout Approval (in case of layout)floor plan.pdf · uploaded 18 Jan 2022View
  • Disclosure of sold/ booked inventorydis sold unsold.pdf · uploaded 18 Jan 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2a.pdf · uploaded 18 Jan 2022View
  • Declaration about Commencement CertificateFORMAT D - CC Decleration.pdf · uploaded 18 Jan 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_compressed.pdf · uploaded 22 Apr 2022View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 22 Apr 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 22 Apr 2022View
  • CERSAI detailsupload cersai.pdf · uploaded 22 Apr 2022View
  • Declaration about Commencement CertificateFORMAT D - CC Decleration.pdf · uploaded 22 Apr 2022View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY - 4th Qtr.pdf · uploaded 22 Apr 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH.pdf · uploaded 19 Jul 2022View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG.pdf · uploaded 19 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 19 Jul 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 19 Jul 2022View
  • Declaration about Commencement CertificateCC DECL.pdf · uploaded 19 Jul 2022View
  • b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE.pdf · uploaded 6 Aug 2022View
  • b Details of encumbrances concerned to LegalFINANCE ENCUMBRANCE.pdf · uploaded 6 Aug 2022View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK LETTER.pdf · uploaded 6 Aug 2022Source
  • Deviation Report with respect to Allotment letterNO DEVIATION ALLOTMENT.pdf · uploaded 6 Aug 2022View
  • Deviation Report with respect to model copy of AgreementNO DEVIATION AGREEMENT.pdf · uploaded 6 Aug 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentKRISHNAM FULL OC.pdf · uploaded 5 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Certificate.pdf · uploaded 20 Jan 2023View
  • Declaration about Commencement CertificateDECLARATION ABOUT CC.pdf · uploaded 20 Jan 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 20 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-CA (FY 2021-22).pdf · uploaded 20 Jan 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate Upto Dec 2022.pdf · uploaded 20 Jan 2023View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY Upto Dec 2022.pdf · uploaded 20 Jan 2023View
  • Architect’s Certificate on Completion of Project (Form 4)RERA Form 4.pdf · uploaded 23 Jan 2023View
  • Status of Formation of Legal Entity (Society/Co Op etc.)KRISHNAM SOCIETY FORMATION.pdf · uploaded 16 May 2023View

Promoter documents

  • Legal Title reportTitle Certificate.pdf · uploaded 29 Jun 2019View
  • Declaration Form BDeclaration 001.pdf · uploaded 2 Aug 2019View
  • Declaration Form BDeclaration 002.pdf · uploaded 2 Aug 2019View
  • Declaration Form BDeclaration 003.pdf · uploaded 2 Aug 2019View
  • Declaration Form BDeclaration 004.pdf · uploaded 2 Aug 2019View

Technical documents

  • Building Plan ApprovalOriginal IOD.pdfView
  • Layout ApprovalBlock Plan Location Plan.pdfView
  • Building Plan ApprovalOriginal IOD Drawing.pdfView
  • Layout Approvallayout plan.pdfView
  • Layout Approvalfloor plan.pdfView

Proforma allotment letter

  • Proforma allotment letterRERA SALE AGREEMENT.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

519519/12

As published on MahaRERA's project page

519, 519/1-2

Boundaries

North
Cts No 518
South
Cts No 520
East
Cts No 522
West
Existing Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDivyesh H. Parekh—
Chartered accountantShah Consultancy Services Ca—
EngineerJitendra Jadav Engineer—
OtherRutuj Construction—
OtherUmesh Chaurasia Structural Engineer—

Source: MahaRERA project page. Contact details are not shown.

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology