Jessika Chs.Ltd.

Certificate Signed

Borivali, Mumbai Suburban 400092 |Promoter: Vinayak Developers

Residential / Group HousingRERAP51800011498
31 Aug 2017Registered with MahaRERA
30 Dec 2020Promised completion
30 Jun 2025Revised completionPushed back 4 years and 6 months
1Building
36Units registered5 booked (14%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK MEMBER REHAB, 1 BHK SOLD, 1BHK SOLD, 1BHK UNSOLD PROMOTER, 2 BHK MEMBER REHAB, 2BHK MEMBER REHAB, 2BHK SOLD, 2BHK UNSOLD PROMOTER, 3BHK MEMBER REHAB36 units in all
Address
137/A, natakwala lane, Borivali(W)PIN 400092
Designated bank account
212
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.22477, 72.85494
Jessika Chs.Ltd. is at latitude 19.22477, longitude 72.85494.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 years and 6 months

The latest completion date on record passed 1 year and 4 months ago.

Registered
31 Aug 2017
Promised
30 Dec 2020
Revised
30 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180001149831 Aug 201730 Dec 202030 Jun 2025Vinayak DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A and B1036

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

5 of 36 units booked (14%), as the promoter reported to MahaRERA

1BHK MEMBER REHAB · 7 units1 BHK SOLD · 1 unit1BHK SOLD · 3 units1BHK UNSOLD PROMOTER · 1 unit2 BHK MEMBER REHAB · 1 unit2BHK MEMBER REHAB · 13 units2BHK SOLD · 1 unit2BHK UNSOLD PROMOTER · 6 units3BHK MEMBER REHAB · 3 units
TypeCarpet areaUnitsBooked
1BHK MEMBER REHAB36.11 sq m · 389 sq ft30
1BHK MEMBER REHAB42.73 sq m · 460 sq ft30
1BHK MEMBER REHAB46.81 sq m · 504 sq ft10
1 BHK SOLD41.79 sq m · 450 sq ft11
1BHK SOLD42.73 sq m · 460 sq ft22
1BHK SOLD46.81 sq m · 504 sq ft11
1BHK UNSOLD PROMOTER46.81 sq m · 504 sq ft10
2 BHK MEMBER REHAB56.68 sq m · 610 sq ft10
Show all 18 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK MEMBER REHAB63.2 sq m · 680 sq ft20
2BHK MEMBER REHAB63.8 sq m · 687 sq ft40
2BHK MEMBER REHAB68.1 sq m · 733 sq ft40
2BHK MEMBER REHAB69.5 sq m · 748 sq ft30
2BHK SOLD68.1 sq m · 733 sq ft11
2BHK UNSOLD PROMOTER56.68 sq m · 610 sq ft10
2BHK UNSOLD PROMOTER68.1 sq m · 733 sq ft30
2BHK UNSOLD PROMOTER69.5 sq m · 748 sq ft10
2BHK UNSOLD PROMOTER69.7 sq m · 750 sq ft10
3BHK MEMBER REHAB90.72 sq m · 977 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 59 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN VIN.pdf · uploaded 21 Jun 2022Source

Legal

  • Legal Title report317-343` Tilte Certificate.pdf · uploaded 20 Jun 2017Source
  • Declaration Form Baffidavit cum declaration.pdf · uploaded 29 Jul 2017Source
  • OtherJessika Share Certi.pdf · uploaded 11 Apr 2018Source
  • OtherTERMINATION COPRAMOTER_.pdf · uploaded 29 Nov 2023Source
  • Declaration Form BLIMAY P51800011498_FileName_1.pdf · uploaded 16 Oct 2024Source
Show all 61 documentsShow fewer documents

Legal

  • Declaration Form Baffidavit jessika rera.pdf · uploaded 16 Oct 2024Source

Migrated

  • 1 Copy of the legal title report317-343` Tilte Certificate.pdf · uploaded 20 Jun 2017Source
  • 1 Commencement Certificates / NA Order for plotted development2068360_furthercc_signed.pdf · uploaded 20 Jun 2017Source
  • 1 Proforma of Allotment letterDraft.pdf · uploaded 20 Jun 2017Source
  • 1 Copy of Layout Approval (in case of layout)IOD Issued Approved Plan.pdf · uploaded 21 Jun 2017Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 21 Jun 2017Source
  • 1 Details of encumbrancesEncrumbrance.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect certificate.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)certificate of engineer-.pdf · uploaded 26 Jul 2017Source
  • 1 Declaration in FORM Baffidavit cum declaration.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)JESSIKA CAC Form-3.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate form 1.pdf · uploaded 31 Oct 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer cerificate.pdf · uploaded 31 Oct 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Jessika arc certificate.pdf · uploaded 31 Jan 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng certificate jessika.pdf · uploaded 31 Jan 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Jessika Share Certi.pdf · uploaded 11 Apr 2018Source
  • 1 OtherJessika Share Certi.pdf · uploaded 11 Apr 2018Source
  • 1 Declaration about Commencement Certificatecc declaration.pdf · uploaded 20 Jun 2022Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect form 1.pdf · uploaded 20 Jun 2022Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer form 2.pdf · uploaded 20 Jun 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200239213942_For_Asset_Based_Search_08_06_2022_11_02_26_969.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)JESSIKA-FORM-5-FY-2017-18.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)JESSIKA-FORM-5-FY-2018-19.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)JESSIKA-FORM-5-FY-2019-20.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)JESSIKA-FORM-5-FY-2020-21.pdf · uploaded 20 Jun 2022Source
  • 1 PAN CardPAN VIN.pdf · uploaded 21 Jun 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of inventory.pdf · uploaded 21 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)engineer form 2A 19-20.pdf · uploaded 22 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer form 2A 20-21.pdf · uploaded 22 Jun 2022Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSER OF SOLD AND ALLOTMENT INVENTORY.pdf · uploaded 13 Jul 2022Source
  • 2 OtherTERMINATION COPRAMOTER_.pdf · uploaded 29 Nov 2023Source
  • 1 Declaration in FORM BLIMAY P51800011498_FileName_1.pdf · uploaded 16 Oct 2024Source
  • 2 Declaration in FORM Baffidavit jessika rera.pdf · uploaded 16 Oct 2024Source
  • 1 Certificates of CA (Form 3)new FORM 3 .pdf · uploaded 16 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryRERA Jessika List (2).pdf · uploaded 16 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Declaration about RERA Designated Bank Accounts for Real Estate Projects-output.pdf · uploaded 23 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsMohod Dis of Intresr-output.pdf · uploaded 23 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations copy-output.pdf · uploaded 23 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Sanctioned Plan-compressed.pdf · uploaded 25 Oct 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)final form 1 (1).pdf · uploaded 25 Oct 2024Source
  • 2 Certificates of CA (Form 3)Form 3 Final.pdf · uploaded 25 Oct 2024Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)final form 2 (1).pdf · uploaded 25 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2a Final.pdf · uploaded 25 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 vi.pdf · uploaded 25 Oct 2024Source
  • 3 Certificates of CA (Form 3)vinayak form 3-output (1).pdf · uploaded 6 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD vd.pdf · uploaded 7 Nov 2024Source

Technical

  • DocumentIOD.pdf · uploaded 21 Jun 2017Source
  • DocumentIOD Issued Approved Plan.pdf · uploaded 21 Jun 2017Source
  • DocumentSanctioned Plan-compressed.pdf · uploaded 25 Oct 2024Source

Technical (Architect)

  • DocumentArchletternew.pdf · uploaded 27 Sep 2024Source
  • Documentfinal form 1 (1).pdf · uploaded 25 Oct 2024Source

Technical (Engineer)

  • Documentengineer letter.pdf · uploaded 27 Sep 2024Source
  • Documentfinal form 2 (1).pdf · uploaded 25 Oct 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

137/A

Boundaries

North
Padam Society
South
Park View Society
East
borivaly Railway Station
West
N R Karode Marg

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUmesh Bhatt—
Chartered accountantHiral Shah—
Chartered accountantRajesh R Shah—
EngineerVidyut Y Raja—

Source: MahaRERA project page. Contact details are not shown.