Aashray

Certificate Signed

Borivali, Mumbai Suburban 400092 |Promoter: Vintage Enterprises

Residential / Group HousingRERAP51800019496
6 Feb 2019Registered with MahaRERA
31 Mar 2020Promised completion
31 Dec 2022Revised completionPushed back 2 years and 9 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Address
164, 164/1 to 6, LT Road, Boriwali (W), Babhai NakaPIN 400092
Designated bank account
159
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 9 months

The latest completion date on record passed 3 years and 10 months ago.

Registered
6 Feb 2019
Promised
31 Mar 2020
Revised
31 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000194966 Feb 201931 Mar 202031 Dec 2022Vintage EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Aashray12—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPan card.PDF · uploaded 23 Jan 2019Source

Legal

  • Declaration Form BForm B.pdf · uploaded 23 Jan 2019Source
  • Legal Title reportTitle report.PDF · uploaded 23 Jan 2019Source

Migrated

  • 1 PAN CardPan card.PDF · uploaded 23 Jan 2019Source
  • 1 Copy of the legal title reportTitle report.PDF · uploaded 23 Jan 2019Source
  • 1 Details of encumbrancesEC.pdf · uploaded 23 Jan 2019Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 23 Jan 2019Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 23 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Jan 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 23 Jan 2019Source
  • 1 Certificates of CA (Form 3)CA certificate.pdf · uploaded 23 Jan 2019Source
  • 1 Proforma of Allotment letterAgreement of sale.pdf · uploaded 23 Jan 2019Source
  • 1 Form 2A2A Certificate Aashray.PDF · uploaded 10 Jun 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5.PDF · uploaded 23 Jan 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng certificate.pdf · uploaded 9 Mar 2020Source
  • 1 Details of Restarting of Construction work post lockdownRERA COVID 19 LETTER.PDF · uploaded 22 Jun 2020Source
  • 2 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 24 Jun 2020Source
  • 2 Form 2AFORM 2A COMP.pdf · uploaded 15 Oct 2020Source
  • 3 Certificates of CA (Form 3)CA.pdf · uploaded 15 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5.PDF · uploaded 15 Oct 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch ankur gangar_compressed.pdf · uploaded 16 Oct 2020Source
  • 4 Certificates of CA (Form 3)Form 3 CA CERTIFICATE December.pdf · uploaded 15 Jan 2021Source
  • 3 Form 2A2A Certificate Aashray March 2021.pdf · uploaded 25 May 2021Source
  • 5 Certificates of CA (Form 3)SIGNED CA CERTIFICATE- VINTAGE MAR'21 (1).pdf · uploaded 25 May 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT FORM 1.pdf · uploaded 20 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A Certificate Aashray June 2021.pdf · uploaded 20 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure_List_Rera_Aashray.pdf · uploaded 20 Jul 2021Source
  • 6 Certificates of CA (Form 3)signed CA CERTIFICATE- VINTAGE.pdf · uploaded 20 Jul 2021Source
  • 1 Declaration about Commencement CertificateVE CC Declaration June 2021.pdf · uploaded 27 Jul 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June to September 2020 (1).pdf · uploaded 12 Aug 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan to March 2021 (1).pdf · uploaded 12 Aug 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 April to June 2021 (1).pdf · uploaded 12 Aug 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - (ARCHITECT).pdf · uploaded 7 Oct 2021Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINER FROM 2.pdf · uploaded 7 Oct 2021Source
  • 4 Form 2A2A aashray (2).pdf · uploaded 7 Oct 2021Source
  • 7 Certificates of CA (Form 3)September Signed CA CERTIFICATE- VINTAGE.pdf · uploaded 7 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Rera Audit Form 5 - Aashray Mar 21_LHs.pdf · uploaded 7 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - RERA ARCHITECT.pdf · uploaded 7 Jan 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aashray.pdf · uploaded 7 Jan 2022Source
  • 8 Certificates of CA (Form 3)signed Ca Certificate form 3.pdf · uploaded 7 Jan 2022Source
  • 1 CERSAI detailscersai declaration.pdf · uploaded 23 Mar 2022Source
  • 2 Disclosure of sold/ booked inventoryrera extension disclosure.pdf · uploaded 29 Mar 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - RERA.pdf · uploaded 6 Apr 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aashray.pdf · uploaded 6 Apr 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FOAM 2A Yogesh Patel.pdf · uploaded 6 Apr 2022Source
  • 9 Certificates of CA (Form 3)Signed Ca Certificate Vintage New Formatdsc.pdf · uploaded 6 Apr 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT FORM 1.pdf · uploaded 6 Jul 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)EngineerForm 2.pdf · uploaded 6 Jul 2022Source
  • 10 Certificates of CA (Form 3)Signed Ca Certificate Vintage June'22 s.pdf · uploaded 6 Jul 2022Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A Yogesh Patel.pdf · uploaded 7 Jul 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2342180_OC_signed.pdf · uploaded 15 Sep 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 - Aashray.pdf · uploaded 24 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (6).pdf · uploaded 26 Mar 2025Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 26 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CA Form 5 VE LH FY 2021-22 (1).pdf · uploaded 26 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FOAM 2A (2021-2022).pdf · uploaded 26 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CA Form 5 VE LH FY 2022-23.pdf · uploaded 26 Mar 2025Source

Technical

  • DocumentIOD.pdf · uploaded 23 Jan 2019Source
  • DocumentLayout.pdf · uploaded 23 Jan 2019Source

Technical (Architect)

  • DocumentARCHITECT FORM 1.pdf · uploaded 6 Jul 2022Source
  • DocumentForm 1 (6).pdf · uploaded 26 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

164164/1 to 6

Boundaries

North
By FP No- 320
South
By CTS No-162 and DP Road
East
By CTS No-163 and DP Road
West
By FP No- 320

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUday V. Dhawan—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology