Aarambh
Completion date passedBorivali, Mumbai Suburban 400097 |Promoter: Satellite Developers Pvt Ltd
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 5 months
P51800015002The latest completion date on record passed 3 years and 4 months ago.
- Registered
- 22 Jan 2018
- Promised
- 25 Jan 2023
- Revised
- 30 Jun 2023
Completion pushed back 6 months
P51800015057The latest completion date on record passed 3 years and 1 month ago.
- Registered
- 22 Jan 2018
- Promised
- 15 Mar 2023
- Revised
- 30 Sep 2023
Completion pushed back 10 months
P51800028424The latest completion date on record passed 1 year and 3 months ago.
- Registered
- 2 Mar 2021
- Promised
- 30 Sep 2024
- Revised
- 31 Jul 2025
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800015002 | 22 Jan 2018 | 25 Jan 2023 | 30 Jun 2023 | Satellite Developers Pvt Ltd | Project page |
| P51800015057 | 22 Jan 2018 | 15 Mar 2023 | 30 Sep 2023 | Satellite Developers Pvt Ltd | Project page |
| P51800028424 | 2 Mar 2021 | 30 Sep 2024 | 31 Jul 2025 | Satellite Developers Pvt Ltd | Project page |
Documents
6 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Borivali
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.