Divine

Certificate Signed

Bandra, Mumbai Suburban 400054 |Promoter: Navish Realty

Residential / Group HousingRERAP51800055711
15 Apr 2024Registered with MahaRERA
31 Mar 2026Promised completion
31 Jul 2026Revised completionPushed back 4 months
1Building
10Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
3BHK, Existing tenant10 units in all
Address
CTS No. 396/8, GURUDWARA ROAD, SANTACRUZ (W)PIN 400054
Designated bank account
171
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

The latest completion date on record passed 3 months ago.

Registered
15 Apr 2024
Promised
31 Mar 2026
Revised
31 Jul 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180005571115 Apr 202431 Mar 202631 Jul 2026Navish RealtyProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Divine1110

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 10 units booked (0%), as the promoter reported to MahaRERA

3BHK · 3 unitsExisting tenant · 7 units
TypeCarpet areaUnitsBooked
3BHK143.78 sq m · 1,548 sq ft30
Existing tenant80.44 sq m · 866 sq ft10
Existing tenant119.65 sq m · 1,288 sq ft20
Existing tenant143.78 sq m · 1,548 sq ft30
Existing tenant204.32 sq m · 2,199 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1 NAVISH REALTY PAN CARD.pdf · uploaded 23 Feb 2024Source

Legal

  • Legal Title report3096 title report.pdf · uploaded 23 Feb 2024Source
  • Declaration Form Bform b.pdf · uploaded 23 Feb 2024Source

Migrated

  • 1 PAN Card1 NAVISH REALTY PAN CARD.pdf · uploaded 23 Feb 2024Source
  • 1 Copy of the legal title report3096 title report.pdf · uploaded 23 Feb 2024Source
  • 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance (8) (1).pdf · uploaded 23 Feb 2024Source
  • 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance (8) (1).pdf · uploaded 23 Feb 2024Source
Show all 63 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)plan.pdf · uploaded 23 Feb 2024Source
  • 1 Building Plan Approval / NA Order for plotted development2390356_IOD_signed.pdf · uploaded 23 Feb 2024Source
  • 1 Commencement Certificates / NA Order for plotted development2396674_FirstCC_signed.pdf · uploaded 23 Feb 2024Source
  • 1 Declaration about Commencement CertificateFormat D (3).pdf · uploaded 23 Feb 2024Source
  • 1 Declaration in FORM Bform b.pdf · uploaded 23 Feb 2024Source
  • 1 CERSAI details1 CERSAI details (6) (1).pdf · uploaded 23 Feb 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate.pdf · uploaded 23 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A DOI (28).pdf · uploaded 23 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK LETTER.pdf · uploaded 23 Feb 2024Source
  • 1 Proforma of Agreement for sale3096 v5 RERA Agreement for sale (3).pdf · uploaded 29 Feb 2024Source
  • 1 Proforma of Allotment letter3096 Allotment Letter (1).pdf · uploaded 29 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letterdeviation clause 2 (1).pdf · uploaded 29 Feb 2024Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation agrement.pdf · uploaded 29 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - SEP 2024.pdf · uploaded 30 Apr 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I DEC 2024.pdf · uploaded 30 Apr 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I-1.pdf · uploaded 30 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - JUNE 2024.pdf · uploaded 30 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Navish - Form 3 - apr to june 24.pdf · uploaded 30 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Navish - Form 3 - july to sep 24.pdf · uploaded 30 Apr 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Navish - Form 3 - oct to dec.pdf · uploaded 30 Apr 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Navish - Form 3 jan to march 25.pdf · uploaded 30 Apr 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 march 25 (1).pdf · uploaded 30 Apr 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 dec 24 (1).pdf · uploaded 30 Apr 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 sept 24.pdf · uploaded 30 Apr 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 june 24-2.pdf · uploaded 30 Apr 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Navish - Form 3 jan to march 25.pdf · uploaded 30 Apr 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Navish - Form 3 - oct to dec.pdf · uploaded 30 Apr 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 march 25 (1).pdf · uploaded 30 Apr 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 dec 24 (1).pdf · uploaded 30 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 sept 24.pdf · uploaded 30 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 june 24-2.pdf · uploaded 30 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - JUNE 2024.pdf · uploaded 8 May 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - SEP 2024.pdf · uploaded 8 May 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - DEC 2024.pdf · uploaded 8 May 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AJIT NIWAS RERA FORM I - MARCH 2025.pdf · uploaded 8 May 2025Source

Technical

  • Document2390356_IOD_signed.pdf · uploaded 23 Feb 2024Source
  • Documentplan.pdf · uploaded 23 Feb 2024Source

Technical (Architect)

  • DocumentAJIT NIWAS RERA FORM I - JUNE 2024.pdf · uploaded 30 Apr 2025Source
  • DocumentAJIT NIWAS RERA FORM I - SEP 2024.pdf · uploaded 30 Apr 2025Source
  • DocumentAJIT NIWAS RERA FORM I DEC 2024.pdf · uploaded 30 Apr 2025Source
  • DocumentAJIT NIWAS RERA FORM I-1.pdf · uploaded 30 Apr 2025Source
  • DocumentAJIT NIWAS RERA FORM I - JUNE 2024.pdf · uploaded 8 May 2025Source
  • DocumentAJIT NIWAS RERA FORM I - SEP 2024.pdf · uploaded 8 May 2025Source
  • DocumentAJIT NIWAS RERA FORM I - DEC 2024.pdf · uploaded 8 May 2025Source
  • DocumentAJIT NIWAS RERA FORM I - MARCH 2025.pdf · uploaded 8 May 2025Source

Technical (Engineer)

  • Documentform 2 june 24-2.pdf · uploaded 30 Apr 2025Source
  • Documentform 2 sept 24.pdf · uploaded 30 Apr 2025Source
  • Documentform 2 dec 24 (1).pdf · uploaded 30 Apr 2025Source
  • Documentform 2 march 25 (1).pdf · uploaded 30 Apr 2025Source
  • DocumentNavish - Form 3 - oct to dec.pdf · uploaded 30 Apr 2025Source
  • DocumentNavish - Form 3 jan to march 25.pdf · uploaded 30 Apr 2025Source
  • Documentform 2 june 24-2.pdf · uploaded 30 Apr 2025Source
  • Documentform 2 sept 24.pdf · uploaded 30 Apr 2025Source
  • Documentform 2 dec 24 (1).pdf · uploaded 30 Apr 2025Source
  • Documentform 2 march 25 (1).pdf · uploaded 30 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bandra, Andheri taluka

Survey, CTS, gat or plot numbers

CTS No. 396/8

Boundaries

North
CTS No G 396 3
South
CTS No G 396 11
East
CTS No G 396 9
West
CTS No G 396 7

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectChirag S. Rayani—
Chartered accountantKinjal Patel—
EngineerMahendra A Mane—

Source: MahaRERA project page. Contact details are not shown.