Aum Aura
Certificate SignedBandra, Mumbai Suburban 400054 |Promoter: M/S Aum Serenity
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —17 units in all
- Address
- Linking Road, Santacruz WestPIN 400054
- Designated bank account
- 76
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 15 Jul 2027
- Registered
- 1 Aug 2025
- Promised
- 15 Jul 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1180002500449 | 1 Aug 2025 | 15 Jul 2027 | — | M/S Aum Serenity | Project page |
Units and parking
17 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 17 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 60 filings listed on MahaRERA's project page
Finance
- PAN CardAUM SERENITY PANCARD f.pdf · uploaded 19 May 2025Source
Legal
- Declaration Form BForm B Promoter Declaration_0001.pdf · uploaded 19 May 2025Source
- OthersNO ENCUMBRANCE LEGAL_0001.pdf · uploaded 20 May 2025Source
- OthersNO ENCUMBRANCE FINANCE_0001.pdf · uploaded 20 May 2025Source
- Declaration Form BDA - 1 - 60 - converted.pdf · uploaded 20 May 2025Source
- Declaration Form BDA - 61 - 120 - converted.pdf · uploaded 20 May 2025Source
- Declaration Form BDA - 121 - 150 - converted.pdf · uploaded 20 May 2025Source
Show all 61 documentsShow fewer documents
Legal
- Declaration Form BDA - 151 - 180 - converted.pdf · uploaded 20 May 2025Source
- Declaration Form BDA - 181 - 218 - converted.pdf · uploaded 20 May 2025Source
- Declaration Form BPOA by maitreyi to Sudhir Parikh & Sahil Parikh BDR 9-11394-2024 (5) - converted.pdf · uploaded 20 May 2025Source
- Declaration Form BRERA Title certificate dated 26th May 2025.pdf · uploaded 26 May 2025Source
- OthersDOI SUDHIR SIR (2).pdf · uploaded 30 Jun 2025Source
- OthersDOI SAHIL SIR (2).pdf · uploaded 30 Jun 2025Source
- OthersDOI SADHANA PARIKH (2).pdf · uploaded 30 Jun 2025Source
Migrated
- Withdrawal Update Form 1Aum Aura - Architect certificate form 1.pdf · uploaded 13 Jan 2026Source
- Withdrawal Update Form 2Aum Aura - Engineering Certificate Form 2.pdf · uploaded 13 Jan 2026Source
- Withdrawal Update Form 3Aum Aura - CA Certificate Form 3.pdf · uploaded 13 Jan 2026Source
- Withdrawal Update Form 1Aum Aura - Architect certificate form 1.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Aum Aura - Architect certificate form 1.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Aum Aura - Architect certificate form 1.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Aum Aura - Architect certificate form 1.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Aum Aura - Engineering Certificate Form 2.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Aum Aura - Engineering Certificate Form 2.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Aum Aura - Engineering Certificate Form 2.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Aum Aura - Engineering Certificate Form 2.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Aum Aura - CA Certificate Form 3.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Aum Aura - CA Certificate Form 3.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Aum Aura - CA Certificate Form 3.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Aum Aura - CA Certificate Form 3.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Withdrawal Application Form1 -S.pdf · uploaded 17 Jun 2026Source
- Withdrawal Update Form 2Withdrawal Application Form - 2 -S.pdf · uploaded 17 Jun 2026Source
- Withdrawal Update Form 3AUM AURA CA CERTIFICATE DT 10th June 2026.pdf · uploaded 17 Jun 2026Source
Planning Authority
- DocumentMCGM_1733113827-25-06-2024 12-19-30$_$Remark_ReportDP34202405111533047.pdf · uploaded 19 May 2025Source
- DocumentMCGM_281986729-06-08-2024 10-50-07$_$PRC.pdf · uploaded 19 May 2025Source
- DocumentMCGM_2455044AmendLetter_signed.pdf · uploaded 19 May 2025Source
- DocumentMCGM_2447722_IOD_signed.pdf · uploaded 19 May 2025Source
- DocumentMCGM_2464766_FirstCC_signed.pdf · uploaded 19 May 2025Source
- DocumentMCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051701070215244845916.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051803070215246261016.pdf · uploaded 19 May 2025Source
- DocumentMCGM_052103070215246261116.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051501070215246261216.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051803070215246508716.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051701070215246761416.pdf · uploaded 19 May 2025Source
- DocumentMCGM_051701070215247659716.pdf · uploaded 19 May 2025Source
Technical
- DocumentIOD of Maitreyi.pdf · uploaded 19 May 2025Source
- DocumentDrawing_1.pdf · uploaded 19 May 2025Source
- DocumentDrawing_2.pdf · uploaded 19 May 2025Source
- OthersMaitreti PRC (1).pdf · uploaded 20 May 2025Source
- OthersDECLARATION ABOUT CC.pdf · uploaded 20 May 2025Source
- OthersC C Rectification Maitreyi.pdf · uploaded 20 May 2025Source
- DocumentOrder 50 Dt 27 05 2025.pdf · uploaded 27 May 2025Source
- OthersZero Letter - S.pdf · uploaded 27 May 2025Source
- DocumentDrawing_4.pdf · uploaded 4 Jul 2025Source
- DocumentDrawing_5.pdf · uploaded 4 Jul 2025Source
- DocumentDrawing_3.pdf · uploaded 4 Jul 2025Source
- DocumentAUM AURA Drawing Dt 23 09 2025_compressed.pdf · uploaded 19 Jun 2026Source
- DocumentIOD Of Maitreyi Latest.pdf · uploaded 19 Jun 2026Source
Technical (Architect)
- DocumentWithdrawal Application Form1 -S.pdf · uploaded 17 Jun 2026Source
Technical (Engineer)
- DocumentWithdrawal Application Form - 2 -S.pdf · uploaded 17 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bandra, Andheri taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- C.T.S. No. 357B
- South
- C.T.S. No 361
- East
- 27.24 Linking Road
- West
- C.T.S. No 361
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Chaitanya R Mehta | — |
Source: MahaRERA project page. Contact details are not shown.