Milan Bliss

Completion date passed

Andheri, Mumbai Suburban 400069 |Promoter: Milan Interbuilt Private Limited

5 Aug 2022Registered with MahaRERA
28 Feb 2025Promised completion
31 Aug 2025Revised completionPushed back 6 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 months

The latest completion date on record passed 1 year and 2 months ago.

Registered
5 Aug 2022
Promised
28 Feb 2025
Revised
31 Aug 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000464825 Aug 202228 Feb 202531 Aug 2025Milan Interbuilt Private LimitedProject page

Documents

2 documents held by Deedo

Registration certificate

Extension certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Andheri

Survey, CTS, gat or plot numbers

621/4 to 7621(pt)

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology