Skip to content

2a/B · Construction of 94 EWS Ts and 182 LIG Ts on CTS No 43 Unnatnagar Goragaon west

Andheri · RERA P51800000042

8Sanctioned habitable floorsregistration certificate
31 Mar 2018Revised completionpromised 31 Mar 2018
94 of 94Units bookedMahaRERA project page

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51800000042 · registered 16 Jun 2017
Promised completion
31 Mar 2018
Revised completion
31 Mar 2018
Sanctioned habitable floors
8
ProjectId
1,564
ProjectName
Construction of 94 EWS Ts and 182 LIG Ts on CTS No 43 Unnatnagar Goragaon west
TotalUnitCount
0
ProjectBuildingId
156
BuildingNameNumber
2A/B
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P51800000042
ProjectBuildingWingsId
156
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
2A/B
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
resi25 m² (269 sq.ft)9494
Total9494
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology