Wing B · Kalpataru One - Wing B
Ward Gsouth · RERA P51900079410
IDBLD_08947737 floorsExtended 4 mo
37Sanctioned habitable floorsregistration certificate
31 Jul 2032Revised completionpromised 31 Mar 2032
0 of 44Units bookedMahaRERA project page
Floors
37 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51900079410 · registered 4 Mar 2025
- Promised completion
- 31 Mar 2032
- Revised completion
- 31 Jul 2032
- Sanctioned habitable floors
- 37
- ProjectId
- 54,435
- ProjectName
- Kalpataru One - Wing B
- TotalUnitCount
- 68
- ProjectBuildingId
- 1,54,063
- BuildingNameNumber
- Wing B
- FsiWithSanctionSqmts
- 36
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 68
- ProjectRegistartionNo
- P51900079410
- ProjectBuildingWingsId
- 1,57,488
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- Wing B
- NoOfBuildingWingFloorProposed
- 52
- NoOfBuildingWingFloorHabitable
- 37
- NoOfBuildingWingFloorSanctioned
- 52
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4BHK | 311.1 m² (3,348 sq.ft) | 36 | 0 |
| 4BHK | 312.8 m² (3,367 sq.ft) | 4 | 0 |
| 5BHK & more | 440.6 m² (4,742 sq.ft) | 4 | 0 |
| Total | 44 | 0 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology