Skip to content
Deedo home
Menu

Birla Niyaara

Completion due Mar 2029

Ward Gsouth, Maharashtra 400030 |Promoter: Aditya Birla Real Estate Limited

22 Nov 2021Registered with MahaRERAFirst of 2 registrations
31 Mar 2029Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.00688, 72.82607
Birla Niyaara is at latitude 19.00688, longitude 72.82607.

Also registered as

Birla Niyaara Phase-1Birla Niyaara Phase-2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2028

P51900031916
Registered
22 Nov 2021
Promised
31 Mar 2028

Completion promised for 31 Mar 2029

P51900054455
Registered
25 Jan 2024
Promised
31 Mar 2029

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5190003191622 Nov 202131 Mar 2028—Aditya Birla Real Estate LimitedProject page
P5190005445525 Jan 202431 Mar 2029—Aditya Birla Real Estate LimitedProject page

Documents

2 documents held by Deedo

Registration certificate (2)

  • Registration certificateP51900031916 · 16 Sep 2026ViewSource
  • Registration certificateP51900054455 · 1 Oct 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

794 at Ward GSouth

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology